Laying of fresh water mains on Lamma Island

The Water Supplies Department is inviting tenders for the laying of fresh water mains on Lamma Island to meet the rapidly increasing demand for water on the island.

The contract works include the laying of about three kilometres of water mains with a diameter of 300 millimetres from Pak Kok to Tai Ling Tsuen and the Lamma Power Station.

A temporary access road will be provided for pedestrians during the construction period.

Works are expected to commence in November to be completed in 12 months.

Tender forms and further particulars can be obtained from the Water Supplies Department, Immigration Tower, 44th floor, 7 Gloucester Road, Wan Chai, Hong Kong.

Tender offers will close at noon on August 18,

End/Friday, July 28, 1995

Tung Chung Outline Zoning Plan approved

The Governor-in-Council has approved the Tung Chung Town Centre Area Outline Zoning Plan, a spokesman for the Town Planning Board said today (Friday).

"The plan provides a statutory planning framework to guide public and private developments in the Tung Chung Town Centre area," he said.

The approved plan (No. S/I-TCTC/1) is available for public inspection until next Friday (August 4) from:

Planning Department,

16th floor, Murray Building, Garden Road,