XN000022-1976-11-25 — Page 14

Daily Information Bulletin 新聞公報 All

1

ลง

Foundation work on the second phase of the housing scheme

is also being carried out and excavation for caisson work is almost

completed.

Three more twin-tower housing blocks, another carpark and

a primary school will be built on this site,

At Ngau Chi Wan Estate, foundation work, including caissons

and piling, is being carried out on the 40-acre site formed on both

sides of Clearwater Bay Road.

Building of the super-structures on this estate will begin

early next year and the two sections of the estate will be linked by

elevated walkways over Clearwater Bay Road.

Fri Shan Estate is being developed on a samller site close

to Choi Hung Estate. Sub-structure work is now at an advanced stage.

The estate comprises three housing blocks and a commercial

centre, together with a carpark, a primary school and other ancilliary

facilities.

*

k

*

Comments

Approved members can add comments, bookmarks, and private notes.

No comments yet.

Private Research Note

Private notes are available after approval.