MORE PARKING PIERS FOR JUMBO JETS AT KAI TAK

Two 747 nose-in piers and three bus docks will be built at Kai Tak

Airport shortly.

The principal work of this project will be carried out at bays 3 and

4 on the apron side of the Terminal Building.

to five.

On completion, the total number of 747 nose-in piers will increase

Three apron bus docks will also be built to provide better transfer

facilities to speed up the movement of passengers between the Terminal Building

and aircraft parked at the outer stands.

Docks will be three storeys high with escalators for inter-floor

connection.

Work on the project is expected to begin in April and will take

about eleven months to complete.