MORE PARKING PIERS FOR JUMBO JETS AT KAI TAK
Two 747 nose-in piers and three bus docks will be built at Kai Tak
Airport shortly.
The principal work of this project will be carried out at bays 3 and
4 on the apron side of the Terminal Building.
to five.
On completion, the total number of 747 nose-in piers will increase
Three apron bus docks will also be built to provide better transfer
facilities to speed up the movement of passengers between the Terminal Building
and aircraft parked at the outer stands.
Docks will be three storeys high with escalators for inter-floor
connection.
Work on the project is expected to begin in April and will take
about eleven months to complete.