Monday, January 29, 1973
Besides the work for the multi-storey complex, the Phase 2 work
will also involve the planning of vehicular ramps to and from Prince
Edward Road. Construction of these ramps will considerably improve the
access to the terminal building from the external road system.
This phase of the project, costing about $45 million, will also
see a re-arrangement and improvement of the facilities for arriving passengers
1
and people meeting passengers.
النور
.|
This will include the expansion of the present arrival hall by
absorbing the section of road space outside the hall.
Phase Two
The building work of Phase 2 is to start in the middle of this
year, and is scheduled for completion in 1975 when Phase 1 and 2 of Stage IV
modifications should be completed.
A specialised study of the baggage handling system for arriving and
departing baggage is currently being undertaken by a consultant firm, for
inclusion in Phase 3 of the Stage IV modifications to the airport.
The consultants, now examining the type of system best suited for
the airport, are expected to have finalised their report by March.
The overall Stage IV project, including Phase 3, will increase
the airport terminal building's passenger handling capability to just
short of 4,000 passengers an hour.
13