TEMPORARY STEEL FLYOVER IN PRINCE EDWARD ROAD

To Ease Congestion During Work On Interchange

Work will begin on Tuesday, June 13, on the foundations for

a temporary steel flyover to be erected along Prince Edward Road

crossing over Waterloo Road.

The flyover, the first of its kind in Hong Kong, is being built

to ease traffic congestion at ground level during the construction later

this year of Hong Kong's first multi-level interchange at the junctions

of Waterloo Road with Prince Edward Road and Boundary Street.

During work on the foundations for the steel flyover, some

restriction of traffic lanes along Prince Edward Road in the vicinity

of the junction with Waterloo Road will be necessary.

Delays to traffic are expected, especially during rush hours.

Motorists are strongly advised to use alternative routes and

to avoid, whenever possible, using this section of Prince Edward Road

during this period.

The steel superstructure for the temporary flyover is presently

being fabricated in Japan and shipment of the steelwork will commence

towards the end of July.

It is planned to erect the steel superstructure of the flyover

at the end of August, over the long weekend, and details regarding

temporary road closures and traffic diversions will be announced later.