15. The Jubilee Reservoir at Shing Mun was taken over from the Consulting Engineers on 1st May. Certain defects in Pineapple Pass Dam were discovered in September and were referred to the Consulting Engineers whose final decision had not been received at the close of the year.

16. The disastrous typhoon of 2nd September caused only minor damage to Water Works.

17. During the year experimental waste detection work was carried out and reports were submitted to Government with a view to the establishment of a permanent waste detection branch.

18. On the construction side the following works were carried out:

19. The laying of the first section of the second 24" diameter trunk main from the Shing Mun Valley between Shek Lai Pui Service Reservoir and Waterloo Road was completed and brought into use in July.

20. The total length of main laid was 16,876 feet of which 16,286 feet consisted of new pipes.

21. The third section of the rapid gravity filters for the Shing Mun Valley Scheme was completed and brought into use in July. With the completion of this section, which deals with five million gallons per day the total filtration capacity of the plant is now fifteen million gallons per day. Provision has been made for the addition of a further five million gallons per day at a future date.

22. The following works in connection with a general extension of the Water Works and described in Sessional Paper No. 3/1937 were approved by the Secretary of State: - supply to Albany; supply to Peak Road; new Cross Harbour Pipes; rapid gravity filters at Eastern; Kowloon Tsai Service Reservoir and Supply Mains thereto; Distribution-Island and Mainland and Shing Mun Valley Scheme Catchwaters.

23. Of the above a contract was let in October for the first section of the Shing Mun Catchwaters, on which good progress was made. Pipes and specials were ordered through the Crown Agents for the Cross Harbour Pipes. Of the remaining items work was mainly restricted to preliminary investigations, designs, detailed estimates and the preparation of contract documents.

RECLAMATIONS.

24. At North Point and Kennedy Town, areas of about 0.75 acres and 1 acre respectively were reclaimed by free deposits of building debris. At Kun Tong an area of about 2 acres has now been reclaimed by the depositing of town's refuse by the Urban Council.

Edit History

2026-05-10 04:30:42 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
40 15. The Jubilee Reservoir at Shing Mun was taken over from the Consulting Engineers on 1st May. Certain defects in Pineapple Pass Dam were discovered in September and were referred to the Consulting Engineers whose final decision had not been received at the close of the year. 16. The disastrous typhoon of 2nd September caused only minor damage to Water Works. 17. During the year experimental waste detection work was carried out and reports were submitted to Government with a view to the establishment of a permanent waste detection branch. 18. On the construction side the following works were carried out: 19. The laying of the first section of the second 24" diameter trunk main from the Shing Mun Valley between Shek Lai Pui Service Reservoir and Waterloo Road was completed and brought into use in July. 20. The total length of main laid was 16,876 feet of which 16,286 feet consisted of new pipes. 21. The third section of the rapid gravity filters for the Shing Mun Valley Scheme was completed and brought into use in July. With the completion of this section, which deals with five million gallons per day the total filtration capacity of the plant is now fifteen million gallons per day. Provision has been made for the addition of a further five million gallons per day at a future date. 22. The following works in connection with a general extension of the Water Works and described in Sessional Paper No. 3/1937 were approved by the Secretary of State: - supply to Albany; supply to Peak Road; new Cross Harbour Pipes; rapid gravity filters at Eastern; Kowloon Tsai Service Reservoir and Supply Mains thereto; Distribution-Island and Mainland and Shing Mun Valley Scheme Catchwaters. 23. Of the above a contract was let in October for the first section of the Shing Mun Catchwaters, on which good progress was made. Pipes and specials were ordered through the Crown Agents for the Cross Harbour Pipes. Of the remaining items work was mainly restricted to preliminary investigations, designs, detailed estimates and the preparation of contract documents. RECLAMATIONS. 24. At North Point and Kennedy Town, areas of about 0.75 acres and 1 acre respectively were reclaimed by free deposits of building debris. At Kun Tong an area of about 2 acres has now been reclaimed by the depositing of town's refuse by the Urban Council.
Baseline (Original)
40 15. The Jubilee Reservoir at Shing Mun was taken over from the Consulting Engineers on 1st May. Certain defects in Pineapple Pass Dam were discovered in September and were referred to the Consulting Engineers whose final decision had not been received at the close of the year. 16. The disastrous typhoon of 2nd September caused only minor damage to Water Works. 17. During the year experimental waste detection work was carried out and reports were submitted to Government with a view to the establishment of a permanent waste detection branch. 18. On the construction side the following works were carried out: 19. The laying of the first section of the second 24" diameter trunk main from the Shing Mun Valley between Shek Lai Pui Service Reservoir and Waterloo Road was completed and brought into use in July. 20. The total length of main laid was 16,876 feet of which 16,286 feet consisted of new pipes. 21. The third section of the rapid gravity filters for the Shing Mun Valley Scheme was completed and brought into use in July. With the completion of this section, which deals with five million gallons per day the total filtration capacity of the plant is now fifteen million gallons per day. Provision has been made for the addition of a further five million gallons per day at a future date. 22. The following works in connection with a general ex- tension of the Water Works and described in Sessional Paper No. 3/1937 were approved by the Secretary of State: -supply to Albany; supply to Peak Road; new Cross Harbour Pipes; rapid gravity filters at Eastern; Kowloon Tsai Service Reservoir and Supply Mains thereto; Distribution-Island and Mainland and Shing Mun Valley Scheme Catchwaters. October for the on which good ordered through 23. Of the above a contract was let in first section of the Shing Mun Catchwaters, progress was made. Pipes and specials were the Crown Agents for the Cross Harbour Pipes. Of the remain- ing items work was mainly restricted preliminary investigations, designs, detailed estimates and the preparation of contract documents. RECLAMATIONS. to 24. At North Point and Kennedy Town, areas of about 0.75 acres and 1 acre respectively were reclaimed by free deposits of building debris. At Kun Tong an area of about 2 acres has now been reclaimed by the depositing of town's refuse by the Urban Council.
2026-05-10 04:30:42 · Baseline
View content

40

15. The Jubilee Reservoir at Shing Mun was taken over from the Consulting Engineers on 1st May. Certain defects in Pineapple Pass Dam were discovered in September and were referred to the Consulting Engineers whose final decision had not been received at the close of the year.

16. The disastrous typhoon of 2nd September caused only minor damage to Water Works.

17. During the year experimental waste detection work was carried out and reports were submitted to Government with a view to the establishment of a permanent waste detection branch.

18. On the construction side the following works were carried out:

19. The laying of the first section of the second 24" diameter trunk main from the Shing Mun Valley between Shek Lai Pui Service Reservoir and Waterloo Road was completed and brought into use in July.

20. The total length of main laid was 16,876 feet of which 16,286 feet consisted of new pipes.

21. The third section of the rapid gravity filters for the Shing Mun Valley Scheme was completed and brought into use in July. With the completion of this section, which deals with five million gallons per day the total filtration capacity of the plant is now fifteen million gallons per day. Provision has been made for the addition of a further five million gallons per day at a future date.

22. The following works in connection with a general ex- tension of the Water Works and described in Sessional Paper No. 3/1937 were approved by the Secretary of State: -supply to Albany; supply to Peak Road; new Cross Harbour Pipes; rapid gravity filters at Eastern; Kowloon Tsai Service Reservoir and Supply Mains thereto; Distribution-Island and Mainland and Shing Mun Valley Scheme Catchwaters.

October for the on which good ordered through

23. Of the above a contract was let in first section of the Shing Mun Catchwaters, progress was made. Pipes and specials were the Crown Agents for the Cross Harbour Pipes. Of the remain- ing items work was mainly restricted preliminary investigations, designs, detailed estimates and the preparation of contract documents.

RECLAMATIONS.

to

24. At North Point and Kennedy Town, areas of about 0.75 acres and 1 acre respectively were reclaimed by free deposits of building debris. At Kun Tong an area of about 2 acres has now been reclaimed by the depositing of town's refuse by the Urban Council.