184. Refuse Bont Pier at Kweilin Street, Shamshuipo:- This work was referred to in paragraph 176 of last year's Report. The only expenditure under this head was on account of the payment of retention money amounting to $500 which became due to the Contractor on expiration of the maintenance period of six months.

Expenditure
$ 500.00
Expenditure to 31st Dec., 1936...$11,441.55

PUBLIC HEALTH AND BUILDINGS ORDINANCE.

185. Compensation and Resumptions:- Minor resumptions were carried out in connection with the development of the district in accordance with the approved Town Planning Scheme.

Expenditure
$ 42.00

ANTI-MALARIAL WORKS.

186. Anti-Malarial Works, including cost of resumptions- No works were carried out during the year.

Expenditure
$ Nil

NEW TERRITORIES.

BUILDINGS.

187. Market at Tsun Wan:- Sketch plans were prepared providing accommodation for twelve meat, six vegetable and six fish stalls, coolie quarters and a water-closet and urinal. A contract was let and signed by Messrs. Hop Shing & Co. on 18th February and the work was satisfactorily completed on the 18th August. 413 feet of 2″ wrought iron piping were laid under the above head primarily as a supply to the new market. Thirty-one electric lights were installed.

Expenditure
$11,514.86
Expenditure to 31st Dec., 1936 $26,266.10

188. Block House and Well-Ta Ku Ling:- Sketch plans were prepared providing accommodation for two European police officers, twenty-six Indian constables, four Indian sergeants, four Chinese detectives, servants quarters and the boring of a well for fresh water supply. A contract was let

Edit History

2026-05-10 03:44:48 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
Q 51 184. Refuse Bont Pier at Kweilin Street, Shamshuipo:- This work was referred to in paragraph 176 of last year's Report. The only expenditure under this head was on account of the payment of retention money amounting to $500 which became due to the Contractor on expiration of the maintenance period of six months. Expenditure$ 500.00Expenditure to 31st Dec., 1936...$11,441.55 PUBLIC HEALTH AND BUILDINGS ORDINANCE. 185. Compensation and Resumptions:- Minor resumptions were carried out in connection with the development of the district in accordance with the approved Town Planning Scheme. Expenditure$ 42.00 ANTI-MALARIAL WORKS. 186. Anti-Malarial Works, including cost of resumptions- No works were carried out during the year. Expenditure$ Nil NEW TERRITORIES. BUILDINGS. 187. Market at Tsun Wan:- Sketch plans were prepared providing accommodation for twelve meat, six vegetable and six fish stalls, coolie quarters and a water-closet and urinal. A contract was let and signed by Messrs. Hop Shing & Co. on 18th February and the work was satisfactorily completed on the 18th August. 413 feet of 2″ wrought iron piping were laid under the above head primarily as a supply to the new market. Thirty-one electric lights were installed. Expenditure$11,514.86Expenditure to 31st Dec., 1936 $26,266.10 188. Block House and Well-Ta Ku Ling:- Sketch plans were prepared providing accommodation for two European police officers, twenty-six Indian constables, four Indian sergeants, four Chinese detectives, servants quarters and the boring of a well for fresh water supply. A contract was let
Baseline (Original)
Q 51 184. Refuse Bout Pier at Kweilin Street, Shamshuipo:- This work was referred to in paragraph 176 of last year's Report. The only expenditure under this head was on account of the payment of retention money amounting to $500 which became due to the Contractor on expiration of the maintenance period of six months. Expenditure $ 500.00 Expenditure to 31st Dec., 1936...$11,441.55 PUBLIC HEALTH AND BUILDINGS ORDinance. 185. Compensation and Resumptions:-Minor resump- tions were carried out in connection with the development of the district in accordance with the approved Town Planning Scheme. Expenditure $ 42.00 ANTI-MALARIAL WORKS. 186. Anti-Malarial Works, including cost of resump- tions-No works were carried out during the year. Expenditure $ Nil NEW TERRITORIES. BUILDINGS. 187. Market at Tsun Wan:-Sketch plans were prepared providing accommodation for twelve meat, six vegetable and six fish stalls, coolie quarters and a water-closet and urinal. A contract was let and signed by Messrs. Hop Shing & Co. on 18th February and the work was satisfactorily completed on the 18th August. 413 feet of 2′′ wrought iron piping were laid under the above head primarily as a supply to the new market. Thirty-one electric lights were installed. Expenditure $11,514.86 Expenditure to 31st Dec., 1936 $26,266.10 188. Block House and Well-Ta Ku Ling:-Sketch plans were prepared providing accommodation for two Euro- pean police officers, twenty-six Indian constables, four Indian sergeants, four Chinese detectives, servants quarters and the boring of a well for fresh water supply. A contract was let
2026-05-10 03:44:48 · Baseline
View content

Q 51

184. Refuse Bout Pier at Kweilin Street, Shamshuipo:- This work was referred to in paragraph 176 of last year's Report. The only expenditure under this head was on account of the payment of retention money amounting to $500 which became due to the Contractor on expiration of the maintenance period of six months.

Expenditure

$ 500.00

Expenditure to 31st Dec., 1936...$11,441.55

PUBLIC HEALTH AND BUILDINGS ORDinance.

185. Compensation and Resumptions:-Minor resump- tions were carried out in connection with the development of the district in accordance with the approved Town Planning Scheme.

Expenditure

$ 42.00

ANTI-MALARIAL WORKS.

186. Anti-Malarial Works, including cost of resump- tions-No works were carried out during the year.

Expenditure

$ Nil

NEW TERRITORIES.

BUILDINGS.

187. Market at Tsun Wan:-Sketch plans were prepared providing accommodation for twelve meat, six vegetable and six fish stalls, coolie quarters and a water-closet and urinal. A contract was let and signed by Messrs. Hop Shing & Co. on 18th February and the work was satisfactorily completed on the 18th August. 413 feet of 2′′ wrought iron piping were laid under the above head primarily as a supply to the new market. Thirty-one electric lights were installed.

Expenditure

$11,514.86

Expenditure to 31st Dec., 1936 $26,266.10

188. Block House and Well-Ta Ku Ling:-Sketch plans were prepared providing accommodation for two Euro- pean police officers, twenty-six Indian constables, four Indian sergeants, four Chinese detectives, servants quarters and the boring of a well for fresh water supply. A contract was let