193. Improvements to Taipo Water Works.-Owing to the rapid development at Taipo Market during the past ten years, increasing difficulty has been experienced in maintaining adequate pressure, particularly to the higher situated houses within the supply area. It was therefore decided, as a first step, to construct a balance tank above Taipo Market, completed by the end of the year, with the exception of a few minor details. In order to take full advantage of the tank, a complete new main of larger capacity will be required.

This was

The tank has a capacity of 111,000 gallons and a maximum depth of thirteen feet, whilst its top water level is 233.00 above O.D.

Expenditure
$9,954.35

194. Improvements to Fanling Water Works. The duplication of the main from the intake was completed, some 4,700 feet of 4″ wrought iron piping having been laid and connected up with the Fanling Village supply. The existing pipe was capped at the road below the Ladies Club House and reserved to supply the Golf Club.

Expenditure
$6,793.03

195. Water Emergency.—To improve water distribution in congested districts during the water shortage, the following works were carried out:- 150 feet of 6″, 2,750 feet of 3″, 4,109 feet of 2½″, 10,000 feet of 2″ and 700 feet of 1½″ diameter wrought iron pipes were laid and 335 temporary street fountains were fixed in groups of five at sixty-seven points in the Colony.

In Kowloon, 10,521 feet of 2″ diameter wrought iron piping were laid and 155 temporary fountains in groups of five were erected.

Expenditure
$56,922.54

LOAN WORKS

196. New Goal at Wong Ma Kok.—This work was referred to in paragraph 255 of the Report for 1930. A Committee was appointed and selected the site at Wong Ma Kok as being the more suitable. Working drawings for the site formation were then prepared and trial pits dug at various positions to ascertain the nature of the ground for the foundations. During the year, circumstances arose which necessitated reconsideration of the site, and a revised layout plan was prepared showing sites for two separate Prisons for males and females, Staff Quarters, and a Police Training School on the alternative site near Stanley. The scheme was submitted to the Committee, and the layout plan and sites were approved by the Governor in Council on 8th December, 1932. Working drawings for the site formation were commenced; the resumption of certain agricultural lots in connection with the access road was carried out.

1932 Expenditure.....
$46,579.78

This

Edit History

2026-05-09 10:52:16 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
46 193. Improvements to Taipo Water Works.-Owing to the rapid development at Taipo Market during the past ten years, increasing difficulty has been experienced in maintaining adequate pressure, particularly to the higher situated houses within the supply area. It was therefore decided, as a first step, to construct a balance tank above Taipo Market, completed by the end of the year, with the exception of a few minor details. In order to take full advantage of the tank, a complete new main of larger capacity will be required. This was The tank has a capacity of 111,000 gallons and a maximum depth of thirteen feet, whilst its top water level is 233.00 above O.D. Expenditure$9,954.35 194. Improvements to Fanling Water Works. The duplication of the main from the intake was completed, some 4,700 feet of 4″ wrought iron piping having been laid and connected up with the Fanling Village supply. The existing pipe was capped at the road below the Ladies Club House and reserved to supply the Golf Club. Expenditure$6,793.03 195. Water Emergency.—To improve water distribution in congested districts during the water shortage, the following works were carried out:- 150 feet of 6″, 2,750 feet of 3″, 4,109 feet of 2½″, 10,000 feet of 2″ and 700 feet of 1½″ diameter wrought iron pipes were laid and 335 temporary street fountains were fixed in groups of five at sixty-seven points in the Colony. In Kowloon, 10,521 feet of 2″ diameter wrought iron piping were laid and 155 temporary fountains in groups of five were erected. Expenditure$56,922.54 LOAN WORKS 196. New Goal at Wong Ma Kok.—This work was referred to in paragraph 255 of the Report for 1930. A Committee was appointed and selected the site at Wong Ma Kok as being the more suitable. Working drawings for the site formation were then prepared and trial pits dug at various positions to ascertain the nature of the ground for the foundations. During the year, circumstances arose which necessitated reconsideration of the site, and a revised layout plan was prepared showing sites for two separate Prisons for males and females, Staff Quarters, and a Police Training School on the alternative site near Stanley. The scheme was submitted to the Committee, and the layout plan and sites were approved by the Governor in Council on 8th December, 1932. Working drawings for the site formation were commenced; the resumption of certain agricultural lots in connection with the access road was carried out. 1932 Expenditure.....$46,579.78 This
Baseline (Original)
46 193. Improvements to Taipo Water Works.-Owing to the rapid development at Taipo Market during the past ten years increasing difficulty has been experienced in maintaining adequate pressure, particularly to the higher situated houses within the supply area. It was therefore decided, as a first step. to construct a balance tank above Taipo Market. completed by the end of the year, with the exception of a few minor details. In order to take full advantage of the tank a complete new main of larger capacity will be required. This was The tank has a capacity of 111,000 gallons and a maximum depth of thirteen feet whilst its top water level is 233.00 above O.D. Expenditure $9,954.35 194. Improvements to Fanling Water Works. The duplica- tion of the main from the intake was completed, some 4,700 feet of 4′′ wrought iron piping having been laid and connected ap with the Fanling Village supply. The existing pipe was cappes at the road below the Ladies Club House and reserved to supris the Golf Club. Expenditure $6,793.03 195. Water Emergency.—To improve water distribution b congested districts during the water shortage, the following works were carried out:-150 feet of 6", 2,750 feet of 3", 4, 109 feet of 23": 23′′. 10,000 10,000 feet of 2" and 700 feet of 3" diamete wrought iron pipes were laid and 335 temporary street fountain- were fixed in groups of five at sixty seven points in the Colony In Kowloon 10,521 feet of 2" diameter wrought iron piping were laid and 155 temporary fountains in groups of five were erected. Expenditure $56.922.54 LOAN WORKS. 196. New Gool at Wong Ma Kok.—This work was referred to in paragraph 255 of the Report for 1930. A Committee was ap- pointed and selected the site at Wong Ma Kok as being the more suitable. Working drawings for the site formation were then prepared and trial pits dug at various positions to ascertain the nature of the ground for the foundations. During the year cir- cumstances arose which necessitated reconsideration of the site and a revised layout plan was prepared showing sites for two separate Prisons for males and females, Staff Quarters, and a Police Training School on the alternative site near Stanley. scheme was submitted to the Committee and the layout plan and sites were approved by the Governor in Council on Sth December, 1932. Working drawings Working drawings for the site formation were commenced, the resumption of certain agricultural lots in connection with the access road was carried out. 1932 Expenditure..... $46,579.78 This
2026-05-09 10:52:16 · Baseline
View content

46

193. Improvements to Taipo Water Works.-Owing to the rapid development at Taipo Market during the past ten years increasing difficulty has been experienced in maintaining adequate pressure, particularly to the higher situated houses within the supply area. It was therefore decided, as a first step. to construct a balance tank above Taipo Market. completed by the end of the year, with the exception of a few minor details. In order to take full advantage of the tank a complete new main of larger capacity will be required.

This was

The tank has a capacity of 111,000 gallons and a maximum depth of thirteen feet whilst its top water level is 233.00 above O.D.

Expenditure

$9,954.35

194. Improvements to Fanling Water Works. The duplica- tion of the main from the intake was completed, some 4,700 feet of 4′′ wrought iron piping having been laid and connected ap with the Fanling Village supply. The existing pipe was cappes at the road below the Ladies Club House and reserved to supris the Golf Club.

Expenditure

$6,793.03

195. Water Emergency.—To improve water distribution b congested districts during the water shortage, the following works were carried out:-150 feet of 6", 2,750 feet of 3", 4, 109 feet of 23":

23′′. 10,000

10,000 feet of 2" and 700 feet of 3" diamete wrought iron pipes were laid and 335 temporary street fountain- were fixed in groups of five at sixty seven points in the Colony

In Kowloon 10,521 feet of 2" diameter wrought iron piping were laid and 155 temporary fountains in groups of five were erected.

Expenditure

$56.922.54

LOAN WORKS.

196. New Gool at Wong Ma Kok.—This work was referred to in paragraph 255 of the Report for 1930. A Committee was ap- pointed and selected the site at Wong Ma Kok as being the more suitable. Working drawings for the site formation were then prepared and trial pits dug at various positions to ascertain the nature of the ground for the foundations. During the year cir- cumstances arose which necessitated reconsideration of the site and a revised layout plan was prepared showing sites for two separate Prisons for males and females, Staff Quarters, and a Police Training School on the alternative site near Stanley. scheme was submitted to the Committee and the layout plan and sites were approved by the Governor in Council on Sth December, 1932. Working drawings

Working drawings for the site formation were commenced, the resumption of certain agricultural lots in connection with the access road was carried out.

1932 Expenditure.....

$46,579.78