P.W.E. New Kowloon.

Q 94

180. Latrine and Bath House at Kowloon City, North of New Police Station.—This work was referred to in paragraph 207 of last year's Report and was completed and opened for the use of the Public by the end of July, 1930.

Estimates
Expenditure

$7,000.00
$2,721.02

181. Married Quarters, Lai Chi Kok Prison. This work is described in paragraph 208 of last year's report.

A contract of $123,893.24 was let to the Tung Shan Co. in August, work was commenced immediately and, by the end of the year, the framework of the building had been erected to First Floor level.

Estimates
Expenditure

General Works:
$85,000.00
$32,651.55

182. Roads.—The following is a brief statement of the principal works carried out under this heading:

The undermentioned roads were macadamized, kerbed, channelled and laid to approved levels, the footpaths being paved with granolithic paving slabs and the necessary improvements made in front of the new buildings erected during the year.

Apliu Street, Boundary Street, Cornwall Road, Castle Peak Road, Cheung Sha Wan Road, Dorset Crescent, Devon Road, Now Fuk Wing Street, Haitan Street, Kweilin Street, Ki Lung Street, Kent Road, Laichikok Road, Ngai Tsin Wai Road, Nan Chang Street, Fuk Wa Street, Peiho Street, Prince Edward Road, Sai Kung Road, Shek Kip Mei Street, Tak Ku Ling Road, Tung Chau Street, Un Chau Street, Wong Chuk Street, Waterloo Road, Yen Chau Street, Yee Kuk Street.

Estimates
Expenditure

Drainage :-
$80,000.00
$66,729.11

183. Training Nullahs.—Nullah was diverted in culvert form from north-east side of Taipo Road from streamcourse opposite Peiho Street to Nanchang Street nullah, Shamshuipo.

Estimates, Expenditure,
$10,000.00
$7,952.85

Edit History

2026-05-09 06:05:37 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
P.W.E. New Kowloon. Q 94 180. Latrine and Bath House at Kowloon City, North of New Police Station.—This work was referred to in paragraph 207 of last year's Report and was completed and opened for the use of the Public by the end of July, 1930. Estimates Expenditure $7,000.00 $2,721.02 181. Married Quarters, Lai Chi Kok Prison. This work is described in paragraph 208 of last year's report. A contract of $123,893.24 was let to the Tung Shan Co. in August, work was commenced immediately and, by the end of the year, the framework of the building had been erected to First Floor level. Estimates Expenditure General Works: $85,000.00 $32,651.55 182. Roads.—The following is a brief statement of the principal works carried out under this heading: The undermentioned roads were macadamized, kerbed, channelled and laid to approved levels, the footpaths being paved with granolithic paving slabs and the necessary improvements made in front of the new buildings erected during the year. Apliu Street, Boundary Street, Cornwall Road, Castle Peak Road, Cheung Sha Wan Road, Dorset Crescent, Devon Road, Now Fuk Wing Street, Haitan Street, Kweilin Street, Ki Lung Street, Kent Road, Laichikok Road, Ngai Tsin Wai Road, Nan Chang Street, Fuk Wa Street, Peiho Street, Prince Edward Road, Sai Kung Road, Shek Kip Mei Street, Tak Ku Ling Road, Tung Chau Street, Un Chau Street, Wong Chuk Street, Waterloo Road, Yen Chau Street, Yee Kuk Street. Estimates Expenditure Drainage :- $80,000.00 $66,729.11 183. Training Nullahs.—Nullah was diverted in culvert form from north-east side of Taipo Road from streamcourse opposite Peiho Street to Nanchang Street nullah, Shamshuipo. Estimates, Expenditure, $10,000.00 $7,952.85
Baseline (Original)
P.W.E. New Kowloon. Q 94 180. Latrine and Bath House at Kowloon City, North of New Police Station.—This work was referred to in paragraph 207 of last year's Report and was completed and opened for the use of the Public by the end of July, 1930. Estimates Expenditure $7,000.00 $2,721.02 181. Married Quarters, Lai Chi Kok Prison. This work is described in paragraph 208 of last year's report. A contract of $123,893.24 was let to the Tung Shan Co. in August, work was commenced immediately and, by the end of the year, the framework of the building had been erected to First Floor level. Estimates Expenditure General Works: $85,000.00 $32,651.55 182. Roads.-The following is a brief statement of the principal works carried out under this heading: The undermentioned roads were uacadamized, kerbed chan- nelled and laid to approved levels, the footpaths being paved with granolithic paving slabs and the necessary improvements made in front of the new buildings erected during the year. Apliu Street, Boundary Street, Cornwall Road, Castle Peak Road, Cheung Sha Wan Road, Dorset Crescent, Devon Road, Now Fuk Wing Street, Haitan Street, Kweilin Street, Ki Lung Street, Kent Road, Laichikok Road, Ngai Tsin Wai Road, Nan Chang Street, Fuk Wa Street, Peiho Street, Prince Edward Road, Sai Kung Road, Shek Kip Mi Street, Tak Ku Ling Road. Tung Chau Street, Un Chau Street, Wong Chuk Street, Waterloo. Road, Yen Chau Street, Yee Kuk Street. Estimates Expenditure Drainage :- $80,000.00 $66,729.11 183. Training Nullahs.--Nullah was diverted in culvert form from north-east side of Taipo Road from streamcourse opposite Peiho Street to Nanchang Street nullah, Shamshuipo. Estimates, Expenditure, $10,000.00 $ 7.952.85
2026-05-09 06:05:37 · Baseline
View content

P.W.E. New Kowloon.

Q 94

180. Latrine and Bath House at Kowloon City, North of New Police Station.—This work was referred to in paragraph 207 of last year's Report and was completed and opened for the use of the Public by the end of July, 1930.

Estimates

Expenditure

$7,000.00

$2,721.02

181. Married Quarters, Lai Chi Kok Prison. This work is described in paragraph 208 of last year's report.

A contract of $123,893.24 was let to the Tung Shan Co. in August, work was commenced immediately and, by the end of the year, the framework of the building had been erected to First Floor level.

Estimates

Expenditure

General Works:

$85,000.00

$32,651.55

182. Roads.-The following is a brief statement of the principal works carried out under this heading:

The undermentioned roads were uacadamized, kerbed chan- nelled and laid to approved levels, the footpaths being paved with granolithic paving slabs and the necessary improvements made in front of the new buildings erected during the year.

Apliu Street, Boundary Street, Cornwall Road, Castle Peak Road, Cheung Sha Wan Road, Dorset Crescent, Devon Road, Now Fuk Wing Street, Haitan Street, Kweilin Street, Ki Lung Street, Kent Road, Laichikok Road, Ngai Tsin Wai Road, Nan Chang Street, Fuk Wa Street, Peiho Street, Prince Edward Road, Sai Kung Road, Shek Kip Mi Street, Tak Ku Ling Road. Tung Chau Street, Un Chau Street, Wong Chuk Street, Waterloo. Road, Yen Chau Street, Yee Kuk Street.

Estimates

Expenditure

Drainage :-

$80,000.00

$66,729.11

183. Training Nullahs.--Nullah was diverted in culvert form from north-east side of Taipo Road from streamcourse opposite Peiho Street to Nanchang Street nullah, Shamshuipo.

Estimates, Expenditure,

$10,000.00

$ 7.952.85

Comments

Approved members can add comments, bookmarks, and private notes.

No comments yet.

Private Research Note

Private notes are available after approval.