Q 103

P.W.E. New Kowloon.

(d) 360 lineal feet of 6" main laid in Fir Street, Shamshuipo.

Estimates, $10,000.00

Expenditure, $9,629.48

235. Filtered water supply to Dairy Farm Lots at Diamond Hill.-A Galvanised Wrot Iron Pipe was laid from Sai Kung Road, Kowloon City to these lots, the total length of pipe being about 3,900 lineal feet. A start was made with the erection of a 30,000 gallons Mild Steel Plate Tank.

The main consists of about 1,900 feet of 4" Wrot Iron Pipe from Sai Kung Road to Shek Ku Lung Village and from there to the lots the main is of 3" pipe about 2,000 feet in length.

Estimates, $20,000.00

Expenditure, $9,394.27

Port Works:-

236. Further Reclamation at Shamshuipo.-This work was referred to in paragraph 186 of last year's Report.

The dredging of materials overlying the rubble mound foundations were completed, the deposit removed amounted to a total of about 12,500 cube yards. About 6,560 cube yards of rubble were deposited to bring the foundations to correct levels. The sea wall was completed for a distance of about 1,575 feet out of a total distance of 1,600 feet.

A slipway was constructed for the use of the Military Authorities, this slipway takes up a distance of 25 feet frontage on the Western extremity of the reclamation.

33,860 cube yards of filling materials were deposited during the year, making a total of 46,860 cube yards of filling deposited under the present Contract.

The foundations of the sea wall settled vertically for a distance of about 180 lineal feet, the maximum settlement amounted to about 6 feet. The settlement was apparently due to the displacement of a thick strata of mud beneath the foundations. The building of the settled portion of the sea wall to proper level was well advanced at the end of the year.

Estimates, $60,000.00

Total Estimates, $783,662.00

Total Expenditure to 31.12.29, $745,981.11

Expenditure, $53,817.21

Edit History

2026-05-09 03:37:56 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
Q 103 P.W.E. New Kowloon. (d) 360 lineal feet of 6" main laid in Fir Street, Shamshuipo. Estimates, $10,000.00 Expenditure, $9,629.48 235. Filtered water supply to Dairy Farm Lots at Diamond Hill.-A Galvanised Wrot Iron Pipe was laid from Sai Kung Road, Kowloon City to these lots, the total length of pipe being about 3,900 lineal feet. A start was made with the erection of a 30,000 gallons Mild Steel Plate Tank. The main consists of about 1,900 feet of 4" Wrot Iron Pipe from Sai Kung Road to Shek Ku Lung Village and from there to the lots the main is of 3" pipe about 2,000 feet in length. Estimates, $20,000.00 Expenditure, $9,394.27 Port Works:- 236. Further Reclamation at Shamshuipo.-This work was referred to in paragraph 186 of last year's Report. The dredging of materials overlying the rubble mound foundations were completed, the deposit removed amounted to a total of about 12,500 cube yards. About 6,560 cube yards of rubble were deposited to bring the foundations to correct levels. The sea wall was completed for a distance of about 1,575 feet out of a total distance of 1,600 feet. A slipway was constructed for the use of the Military Authorities, this slipway takes up a distance of 25 feet frontage on the Western extremity of the reclamation. 33,860 cube yards of filling materials were deposited during the year, making a total of 46,860 cube yards of filling deposited under the present Contract. The foundations of the sea wall settled vertically for a distance of about 180 lineal feet, the maximum settlement amounted to about 6 feet. The settlement was apparently due to the displacement of a thick strata of mud beneath the foundations. The building of the settled portion of the sea wall to proper level was well advanced at the end of the year. Estimates, $60,000.00 Total Estimates, $783,662.00 Total Expenditure to 31.12.29, $745,981.11 Expenditure, $53,817.21
Baseline (Original)
Q 103 P.W.E. New Kowloon. (d) 360 lineal feet of 6" main laid in Fir Street, Sham- shuipo. Estimates, Expenditure, $10,000.00 $ 9,629.48 235. Fillered water supply to Dairy Farm Lots at Diamond Hill.-A Galvanised Wrot Iron Pipe was laid from Sai Kung Road, Kowloon City to these lots, the total length of pipe being about 3,900 lineal feet. A start was made with the erection of a 30,000 gallons Mild Steel Plate Tank. The main consists of about 1,900 feet of 4" Wrot Iron Pipe from Sai Kung Road to Shek Ku Lung Village and from there to the lots the main is of 3" pipe about 2,000 feet in length. Estimates, Expenditure, Port Works:- $20,000.00 $ 9,394.27 236. Further Reclamation at Shamshuipo.-This work was referred to in paragraph 186 of last year's Report. The dredging of materials overlying the rubble mound foun- dations were completed, the deposit removed amounted to a total of about 12,500 cube yards. About 6,560 cube yards of rubble were deposited to bring the foundations to correct levels. The sea wall was completed for a distance of about 1,575 feet out of a total distance of 1,600 feet. A slipway was constructed for the use of the Military Au- thorities, this slipway takes up a distance of 25 feet frontage on the Western extremity of the reclamation. 33,860 cube yards of filling materials were deposited during the year, making a total of 46,860 cube yards of filling deposited under the present Contract. The foundations of the sea wall settled vertically for a distance of about 180 lineal feet, the maximum settlement amounted to about 6 feet. The settlement was apparently due to the displacement of a thick strata of mud beneath the foun- dations. The building of the settled portion of the sea wall to proper level was well advanced at the end of the year. Estimates, Expenditure, $60,000.00 Total Estimates, $783,662.00 Total Expenditure $53,817.21 to 31.12.29. $745,981.11
2026-05-09 03:37:56 · Baseline
View content

Q 103

P.W.E. New Kowloon.

(d) 360 lineal feet of 6" main laid in Fir Street, Sham-

shuipo.

Estimates,

Expenditure,

$10,000.00

$ 9,629.48

235. Fillered water supply to Dairy Farm Lots at Diamond Hill.-A Galvanised Wrot Iron Pipe was laid from Sai Kung Road, Kowloon City to these lots, the total length of pipe being about 3,900 lineal feet. A start was made with the erection of a 30,000 gallons Mild Steel Plate Tank.

The main consists of about 1,900 feet of 4" Wrot Iron Pipe from Sai Kung Road to Shek Ku Lung Village and from there to the lots the main is of 3" pipe about 2,000 feet in length.

Estimates,

Expenditure,

Port Works:-

$20,000.00

$ 9,394.27

236. Further Reclamation at Shamshuipo.-This work was referred to in paragraph 186 of last year's Report.

The dredging of materials overlying the rubble mound foun- dations were completed, the deposit removed amounted to a total of about 12,500 cube yards. About 6,560 cube yards of rubble were deposited to bring the foundations to correct levels. The sea wall was completed for a distance of about 1,575 feet out of a total distance of 1,600 feet.

A slipway was constructed for the use of the Military Au- thorities, this slipway takes up a distance of 25 feet frontage on the Western extremity of the reclamation.

33,860 cube yards of filling materials were deposited during the year, making a total of 46,860 cube yards of filling deposited under the present Contract.

The foundations of the sea wall settled vertically for a distance of about 180 lineal feet, the maximum settlement amounted to about 6 feet. The settlement was apparently due to the displacement of a thick strata of mud beneath the foun- dations. The building of the settled portion of the sea wall to proper level was well advanced at the end of the year.

Estimates,

Expenditure,

$60,000.00 Total Estimates, $783,662.00

Total Expenditure

$53,817.21 to 31.12.29. $745,981.11