P.W E. New Kowloon.
Q 102
231. Cheung Sha Wan-Forming site for exchanges.--It was considered inadvisable to undertake this work since the locality of this district did not warrant development on the lines of the Town Planning Layout, consequently no expenditure was incurred during the year.
Estimates, Expenditure,
$4,500.00
Nil.
232. Filling in Areas North West of Nan Cheong Street and West of Taipo Road.—This work was undertaken to bring the low lying areas West of Nan Cheong Street and South of Castle Peak Road to approved Formation Levels in accordance with the Town Planning Layout.
A Contract was let to Messrs. Fu On & Co. for a sum of $92,315.00 on 18th October, 1929 for the above work together with the continuation of the nullah wall and invert West of Shamshuipo Camp.
Little progress was made, however, since the Contract was not signed till late in the year.
Estimates,
Expenditure,
Waterworks:-
$30,000.00
$74.00
233. Kowloon Tong Estate-Mains. This work was completed by the laying of:
780 lineal feet of 6″ Cast Iron main and 740 lineal feet of 5″ Cast Iron main in Cornwall Street, at the Northern end of the Estate.
Estimates,
Expenditure,
$5,000.00
$3,663.32
234. Distributing Water Mains.-The following works were carried out under this vote:
(a) A connecting main 5,700 lineal feet in length was laid along Tin Liu and Un Chau Streets connecting up the Sham Shui Po system to Piper's Hill Service Reservoir. The main is mostly 6″ Cast Iron but a small portion temporarily is of 7″ Cast Iron.
(b) 600 lineal feet of 6″ main laid along Shek Kip Mei Street, Shamshuipo, northwards from Lai Chi Kok Road.
(c) 264 lineal feet of 6″ main laid along Maple Street,
Shamshuipo, northwards from Lai Chi Kok Road.
P.W E. New Kowloon.
Q 102
231. Cheung Sha Wan-Forming site for exchanges.--It was considered inadvisable to undertake this work since the locality of this district did not warrant development on the lines of the Town Planning Layout, consequently no expenditure was incurred during the year.
Estimates, Expenditure,
$4,500.00
Nil.
232. Filling in Areas North West of Nan Cheong Street and West of Taipo Road.—This work was undertaken to bring the low lying areas West of Nan Cheong Street and South of Castle Peak Road to approved Formation Levels in accordance with the Town Planning Layout.
A Contract was let to Messrs. Fu On & Co. for a sum of $92,315.00 on 18th October, 1929 for the above work together with the continuation of the nullah wall and invert West of Shamshuipo Camp.
Little progress was made, however, since the Contract was not signed till late in the year.
Estimates,
Expenditure,
Waterworks:-
$30,000.00
$
74.00
233. Kowloon Tong Estate-Mains. This work was com- pleted by the laying of:
780 lineal feet of 6′′ Cast Iron main and 740 lineal feet of 5′′ Cast Iron main in Cornwall Street, at the Northern end of the Estate.
Estimates,
Expenditure,
$5,000.00
$3,663.32
234. Distributing Water Mains.-The following works were carried out under this vote:
(a) A connecting main 5,700 lineal feet in length was laid along Tin Liu and Un Chau Streets connecting up the Sham Shui Po system to Piper's Hill Service Reservoir. The main is mostly 6" Cast Iron but a small portion temporarily is of 7" Cast Iron.
(b) 600 lineal feet of 6" main laid along Shek Kip Mei Street, Shamshuipo, northwards from Lai Chi Kok Road.
(c) 264 lineal feet of 6" main laid along Maple Street,
Shamshuipo, northwards from Lai Chi Kok Road.