212. Miscellaneous.-The following is a brief description of the principal works executed under this head :—

Sham Shui Po Police Station-Concreting surfacing to compound. Lai Chi Kok Gaol-Renewal of part of the surrounding fence. Nullah east of Lai Chi Kok Prison-Demolition of Dams. Christian Chinese Cemetery-Diversion of Path. Ngau Shi Wan -Removal of truck line.

Estimates, Expenditure,

$10,000.00 $5,093.00

213. Water Works.-Only minor extensions necessitated by the installing of street fountains in developing districts, were carried out under this vote.

Estimates, Expenditure,

$4,000.00 $773.04

214. Port Works. Only minor works of a miscellaneous nature were carried out by daily labour under the above head during the year.

Estimates, Expenditure,

$1,000.00 $343.60

215. Waterloo Road Extension to foothills (100 feet) (surfacing chiefly). This work was referred to in paragraph 153 (a) of the Report for 1927 and in paragraph 170 of last year's Report.

No further work was undertaken, consequently no expenditure was incurred.

Estimates, Expenditure,

$8,000.00 Nil.

216. Kowloon Tong Development Area at Kowloon Tsai- Extension of roads (no surfacing).—This work was referred to in paragraph 172 of last year's Report.

Contract No. 24 of 1922 was closed on 17th September, 1929 owing to the dilatoriness of the Contractor Messrs. Li Hing & Bros. in finishing this work. The work of completion was let to Mr. Keng Tak Cheong on 4th November, 1929, under Contract No. 62 of 1929. This Contract totalling $14,907.00 comprised 3 sections, "A", "B" and "C". The above work being carried out as Part "A" for a sum of $11,910.00. Part "B" deals with "Kowloon Tong Development Scheme-Excavation and filling" and Part "C" with "Kowloon Tong Development Area- Connection of Stream North of Hill Area to main nullah" mentioned hereafter.

Edit History

2026-05-09 03:37:02 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
Q 97 P.W.E. New Kowloon. 212. Miscellaneous.-The following is a brief description of the principal works executed under this head :— Sham Shui Po Police Station-Concreting surfacing to compound. Lai Chi Kok Gaol-Renewal of part of the surrounding fence. Nullah east of Lai Chi Kok Prison-Demolition of Dams. Christian Chinese Cemetery-Diversion of Path. Ngau Shi Wan -Removal of truck line. Estimates, Expenditure, $10,000.00 $5,093.00 213. Water Works.-Only minor extensions necessitated by the installing of street fountains in developing districts, were carried out under this vote. Estimates, Expenditure, $4,000.00 $773.04 214. Port Works. Only minor works of a miscellaneous nature were carried out by daily labour under the above head during the year. Estimates, Expenditure, $1,000.00 $343.60 215. Waterloo Road Extension to foothills (100 feet) (surfacing chiefly). This work was referred to in paragraph 153 (a) of the Report for 1927 and in paragraph 170 of last year's Report. No further work was undertaken, consequently no expenditure was incurred. Estimates, Expenditure, $8,000.00 Nil. 216. Kowloon Tong Development Area at Kowloon Tsai- Extension of roads (no surfacing).—This work was referred to in paragraph 172 of last year's Report. Contract No. 24 of 1922 was closed on 17th September, 1929 owing to the dilatoriness of the Contractor Messrs. Li Hing & Bros. in finishing this work. The work of completion was let to Mr. Keng Tak Cheong on 4th November, 1929, under Contract No. 62 of 1929. This Contract totalling $14,907.00 comprised 3 sections, "A", "B" and "C". The above work being carried out as Part "A" for a sum of $11,910.00. Part "B" deals with "Kowloon Tong Development Scheme-Excavation and filling" and Part "C" with "Kowloon Tong Development Area- Connection of Stream North of Hill Area to main nullah" mentioned hereafter.
Baseline (Original)
! Q 97 P.W.E. New Kowloon. 212. Miscellaneous.-The following is a brief description of the principal works executed under this head :— Sham Shui Po Police Station-Concreting surfacing to compound. Lai Chi Kok Gaol-Renewal of part of the surrounding fence. Nullah east of Lai Chi Kok Prison-Demolition of Dams. Christian Chin- ese Cemetery-Diversion of Path. Ngau Shi Wan -Removal of truck line. Estimates, Expenditure, $10,000.00 $ 5,093.00 213. Water Works.-Only minor extensions necessitated by the installing of street fountains in developing districts, were carried out under this vote. Estimates, Expenditure, $4,000.00 $ 773.04 214. Port Works. Only minor works of a miscellaneous nature were carried out by daily labour under the above head during the year. Estimates, Expenditure, Communications: $1,000.00 $3 43.60 215. Waterloo Road Extension to foothills (100 feet) (sur- facing chiefly). This work was referred to in paragraph 153 (a) of the Report for 1927 and in paragraph 170 of last year's Re- port. No further work was undertaken, consequently no expendi- ture was incurred. Estimates, Expenditure, $8,000.00 Nil. 216. Kowloon Tong Development Area at Kowloon Tsai- Extension of roads (no surfacing).—This work was referred to in paragraph 172 of last year's Report. Contract No. 24 of 1922 was closed on 17th September, 1929 owing to the dilatoriness of the Contractor Messrs. Li Hing & Bros. in finishing this work. The work of completion was let to Mr. Keng Tak Cheong on 4th November, 1929, under Contract No. 62 of 1929. This Contract totalling $14,907.00 comprised 3 sections, "A", "B" and "C". The above work being carried out as Part "A" for a sum of $11,910.00. Part "B" deals with "Kowloon Tong Development Scheme-Excavation and filling" and Part "C" with "Kowloon Tong Development Area- Connection of Stream North of Hill Area to main nullah" men- tioned hereafter.
2026-05-09 03:37:02 · Baseline
View content

!

Q 97

P.W.E. New Kowloon.

212. Miscellaneous.-The following is a brief description of the principal works executed under this head :—

Sham Shui Po Police Station-Concreting surfacing to compound. Lai Chi Kok Gaol-Renewal of part of the surrounding fence. Nullah east of Lai Chi Kok Prison-Demolition of Dams. Christian Chin- ese Cemetery-Diversion of Path. Ngau Shi Wan

-Removal of truck line.

Estimates,

Expenditure,

$10,000.00

$ 5,093.00

213. Water Works.-Only minor extensions necessitated by the installing of street fountains in developing districts, were carried out under this vote.

Estimates, Expenditure,

$4,000.00

$ 773.04

214. Port Works. Only minor works of a miscellaneous nature were carried out by daily labour under the above head during the year.

Estimates, Expenditure,

Communications:

$1,000.00

$3

43.60

215. Waterloo Road Extension to foothills (100 feet) (sur- facing chiefly). This work was referred to in paragraph 153 (a) of the Report for 1927 and in paragraph 170 of last year's Re- port.

No further work was undertaken, consequently no expendi- ture was incurred.

Estimates,

Expenditure,

$8,000.00 Nil.

216. Kowloon Tong Development Area at Kowloon Tsai- Extension of roads (no surfacing).—This work was referred to in paragraph 172 of last year's Report.

Contract No. 24 of 1922 was closed on 17th September, 1929 owing to the dilatoriness of the Contractor Messrs. Li Hing & Bros. in finishing this work. The work of completion was let to Mr. Keng Tak Cheong on 4th November, 1929, under Contract No. 62 of 1929. This Contract totalling $14,907.00 comprised 3 sections, "A", "B" and "C". The above work being carried out as Part "A" for a sum of $11,910.00. Part "B" deals with "Kowloon Tong Development Scheme-Excavation and filling" and Part "C" with "Kowloon Tong Development Area- Connection of Stream North of Hill Area to main nullah" men- tioned hereafter.