Works carried out for the

Military Authorities.

94

(e.) Roads.-A length of road, 20 feet wide and approximately 800 yards long, was surfaced with dry macadam along the North-East boundary of the reclamation in order to give access to the works at the Eastern end of the reclamation.

Estimates, $65,000.00 $2,796.45

WORKS CARRIED OUT FOR THE

MILITARY AUTHORITY.

233. Erection of three Conveniences at Shamshuipo.—This work was referred to in paragraph 189 of the Report for last year.

The two Trough Closets were completed by March of this year and together with the temporary conveniences were handed over to the Sanitary Department.

Total Estimates, $10,000.00 Estimates for Military Contribution 1928 $16,000.00 Expenditure, to 31.12.28, $13,914.38 $3,500.37

234. Pill Boxes on Frontier of New Territories.-At the request of the M.A. several pill boxes were erected on the border between British and Chinese Territories.

A large one was built near the Shum Chun River at Lo Wu halt. At Sha Tau Kok Police Station, a hut and two small pill-boxes were built and a large one was constructed at the terminus of the road at Shataukok.

The work which was let to Mr. Yeung Tham for the sum of $11,953.62 was completed by about the middle of August and the buildings handed over to the M.A. on the 28th of the same month:

Expenditure, $14,017.16

235. Shamshuipo Camp.-Two V-shaped stormwater channels on the north and south sides of the camp area at Shamshuipo and subsidiary field drains were constructed.

Expenditure, $7,509.85

Edit History

2026-05-09 00:37:24 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
Works carried out for the Military Authorities. 94 (e.) Roads.-A length of road, 20 feet wide and approximately 800 yards long, was surfaced with dry macadam along the North-East boundary of the reclamation in order to give access to the works at the Eastern end of the reclamation. Estimates, $65,000.00 $2,796.45 WORKS CARRIED OUT FOR THE MILITARY AUTHORITY. 233. Erection of three Conveniences at Shamshuipo.—This work was referred to in paragraph 189 of the Report for last year. The two Trough Closets were completed by March of this year and together with the temporary conveniences were handed over to the Sanitary Department. Total Estimates, $10,000.00 Estimates for Military Contribution 1928 $16,000.00 Expenditure, to 31.12.28, $13,914.38 $3,500.37 234. Pill Boxes on Frontier of New Territories.-At the request of the M.A. several pill boxes were erected on the border between British and Chinese Territories. A large one was built near the Shum Chun River at Lo Wu halt. At Sha Tau Kok Police Station, a hut and two small pill-boxes were built and a large one was constructed at the terminus of the road at Shataukok. The work which was let to Mr. Yeung Tham for the sum of $11,953.62 was completed by about the middle of August and the buildings handed over to the M.A. on the 28th of the same month: Expenditure, $14,017.16 235. Shamshuipo Camp.-Two V-shaped stormwater channels on the north and south sides of the camp area at Shamshuipo and subsidiary field drains were constructed. Expenditure, $7,509.85
Baseline (Original)
Works carried out for the Military Authorities. 94 (e.) Roads.-A length of road, 20 feet wide and approx- imately 800 yards long, was surfaced with dry macadam along the North-East boundary of the reclamation in order to give access to the works at the Eastern end of the reclamation. Estimates, Expenditure, $65,000.00 $ 2,796.45 WORKS CARRIED OUT FOR THE MILITARY AUTHORITY. 233. Erection of three Conveniences at Shamshuipo.—This work was referred to in paragraph 189 of the Report for last year. The two Trough Closets were completed by March of this year and together with the temporary conveniences were handed over to the Sanitary Department. Total Estimates, Estimates for Military Contribution 1928 Expenditure, . $3,500.37 to 31.12.28, $10,000.00 Expenditure up $16,000.00 $13,914.38 234. Pill Boxes on Frontier of New Territories.-At the request of the M.A. several pill boxes were erected on the border between British and Chinese Territories. A large one was built near the Shum Chun River at Lo Wu halt. At Sha Tau Kok Police Station, a hut and two small pill-boxes were built and a large one was constructed at the terminus of the road at Shataukok. The work which was let to Mr. Yeung Tham for the sum of $11,953.62 was completed by about the middle of August and the buildings handed over to the M.A. on the 28th of the same month: Expenditure, $14,017.16 235. Shamshuipo Camp.-Two V-shaped stormwater chan- nels on the north and south sides of the camp area at Sham- shuipo and subsidiary fielddrains were constructed. Expenditure, $7,509.85
2026-05-09 00:37:24 · Baseline
View content

Works carried out for the

Military Authorities.

94

(e.) Roads.-A length of road, 20 feet wide and approx- imately 800 yards long, was surfaced with dry macadam along the North-East boundary of the reclamation in order to give access to the works at the Eastern end of the reclamation.

Estimates, Expenditure,

$65,000.00 $ 2,796.45

WORKS CARRIED OUT FOR THE

MILITARY AUTHORITY.

233. Erection of three Conveniences at Shamshuipo.—This work was referred to in paragraph 189 of the Report for last year.

The two Trough Closets were completed by March of this year and together with the temporary conveniences were handed over to the Sanitary Department.

Total Estimates,

Estimates for Military

Contribution 1928 Expenditure, . $3,500.37 to 31.12.28,

$10,000.00 Expenditure up

$16,000.00

$13,914.38

234. Pill Boxes on Frontier of New Territories.-At the request of the M.A. several pill boxes were erected on the border between British and Chinese Territories.

A large one was built near the Shum Chun River at Lo Wu halt. At Sha Tau Kok Police Station, a hut and two small pill-boxes were built and a large one was constructed at the terminus of the road at Shataukok.

The work which was let to Mr. Yeung Tham for the sum of $11,953.62 was completed by about the middle of August and the buildings handed over to the M.A. on the 28th of the same month:

Expenditure,

$14,017.16

235. Shamshuipo Camp.-Two V-shaped stormwater chan- nels on the north and south sides of the camp area at Sham- shuipo and subsidiary fielddrains were constructed.

Expenditure,

$7,509.85