P.W.E. New Kowloon.

Fresh tenders were called for and in April Mr. Man Gang was awarded the contract for one year. By the end of the year approximately 6.6 acres of ground had been filled in to a level above extreme high water.

The requirements of the Sanitary Department as regards provision of covering spoil etc. were met throughout the year.

1928 Estimates, 1928 Expenditure,

$7,500.00 Expenditure up to 31.12.28, $6,025.43

$54,576.81

181. Filling in areas at Tong Mi and Kowloon Tong.—This work was referred to in paragraph 162 of last year's Report.

The Contract was completed by the end of the year,

1928 Estimates, $201,000.00

$50,000.00 Total Estimates, Expenditure up to 31.12.28, $33,185.41

1928 Expenditure, $23,897.41

182. Chinese Cemeteries, Laying out new areas.—Work carried out under this head has already been alluded to in paragraph 31 of this report.

Estimates, Expenditure,

$2,000.00 $1,999.49

183. Exhumation, Chinese Cemeteries.—Certain exhumation work was carried out for this Department by the Sanitary Department.

Estimates, Expenditure,

$20,000.00 $...

184. Lai Chi Kok Gaol, Fire Fighting Appliances.—This work consisted of purchasing and installing a number of Fire Extinguishers and Hose Pipes in advantageous positions recommended by the Fire Brigade in the various Government Buildings.

The work was commenced in November and satisfactorily completed in December.

Estimates, Expenditure,

Waterworks: $5,600.00 $1,003.39

185. New Mains to Kowloon Tong Estate. A further length of 3,190 feet of 6″ main was laid during the year.

$10,000.00 Total Estimates, Expenditure up to 31.12.28, $8,580.97

1928 Estimates, $90,000.00

1928 Expenditure, $85,163.90

Edit History

2026-05-09 00:35:18 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
Q 79 P.W.E. New Kowloon. Fresh tenders were called for and in April Mr. Man Gang was awarded the contract for one year. By the end of the year approximately 6.6 acres of ground had been filled in to a level above extreme high water. The requirements of the Sanitary Department as regards provision of covering spoil etc. were met throughout the year. 1928 Estimates, 1928 Expenditure, $7,500.00 Expenditure up to 31.12.28, $6,025.43 $54,576.81 181. Filling in areas at Tong Mi and Kowloon Tong.—This work was referred to in paragraph 162 of last year's Report. The Contract was completed by the end of the year, 1928 Estimates, $201,000.00 $50,000.00 Total Estimates, Expenditure up to 31.12.28, $33,185.41 1928 Expenditure, $23,897.41 182. Chinese Cemeteries, Laying out new areas.—Work carried out under this head has already been alluded to in paragraph 31 of this report. Estimates, Expenditure, $2,000.00 $1,999.49 183. Exhumation, Chinese Cemeteries.—Certain exhumation work was carried out for this Department by the Sanitary Department. Estimates, Expenditure, $20,000.00 $... 184. Lai Chi Kok Gaol, Fire Fighting Appliances.—This work consisted of purchasing and installing a number of Fire Extinguishers and Hose Pipes in advantageous positions recommended by the Fire Brigade in the various Government Buildings. The work was commenced in November and satisfactorily completed in December. Estimates, Expenditure, Waterworks: $5,600.00 $1,003.39 185. New Mains to Kowloon Tong Estate. A further length of 3,190 feet of 6″ main was laid during the year. $10,000.00 Total Estimates, Expenditure up to 31.12.28, $8,580.97 1928 Estimates, $90,000.00 1928 Expenditure, $85,163.90
Baseline (Original)
Q 79 P.W.E. New Kowloon. Fresh tenders were called for and in April Mr. Man Gang was awarded the contract for one year. By the end of the r approximately 6.6 acres of ground had been filled in to a insl above extreme high water. The requirements of the Sanitary Department as regards provision of covering spoil etc. were met throughout the year. 1928 Estimates, 1928 Expenditure, $7,500.00 Expenditure up $6,025.43 to 31.12.28, $54,576.81 181. Filling in areas at Tong Mi and Kowloon Tong.—This work was referred to in paragraph 162 of last year's Report. The Contract was completed by the end of the year, 1928 Estimates, $201.000.00 $50,000.00 Total Estimates, Expenditure up to 31.12.28, $ 33.185.41 1928 Expenditure, . $23,897.41 182. Chinese Cemetries, Laying out new areas.—Work car- ried out under this head has already been alluded to in para- graph 31 of this report. Estimates, Expenditure, $2,000.00 $1,999.49 183. Exhumation, Chinese Cemeteries.-Certain exhuma- tion work was carried out for this Department by the Sanitary Department. Estimates, Expenditure, $20,000.00 $ . 184. Lai Chi Kok Gaol, Fire Fighting Appliances.—This work consisted of purchasing and installing a number of Fire Extinctures and Hose Pipes in advantageous positions recom- mended by the Fire Brigade in the various Government Build- ings. The work was commenced in November and satisfactorily completed in December. Estimates, Expenditure, Waterworks:--- $5,600.00 $1,003.39 185. New Mains to Kowloon Tong Estate. A further length of 3,190 feet of 6′′ main was laid during the year. $10,000.00 Total Estimates, Expenditure up to 31.12.28, 1928 Estimates, 1928 Expenditure, . $ 8,580.97 $90,000.00 $85,163.90
2026-05-09 00:35:18 · Baseline
View content

Q 79

P.W.E. New Kowloon.

Fresh tenders were called for and in April Mr. Man Gang was awarded the contract for one year. By the end of the r approximately 6.6 acres of ground had been filled in to a insl above extreme high water.

The requirements of the Sanitary Department as regards provision of covering spoil etc. were met throughout the year.

1928 Estimates, 1928 Expenditure,

$7,500.00 Expenditure up $6,025.43 to 31.12.28,

$54,576.81

181. Filling in areas at Tong Mi and Kowloon Tong.—This work was referred to in paragraph 162 of last year's Report.

The Contract was completed by the end of the year,

1928 Estimates,

$201.000.00

$50,000.00

Total Estimates, Expenditure up

to 31.12.28,

$ 33.185.41

1928 Expenditure, . $23,897.41

182. Chinese Cemetries, Laying out new areas.—Work car- ried out under this head has already been alluded to in para- graph 31 of this report.

Estimates, Expenditure,

$2,000.00 $1,999.49

183. Exhumation, Chinese Cemeteries.-Certain exhuma- tion work was carried out for this Department by the Sanitary Department.

Estimates, Expenditure,

$20,000.00 $

.

184. Lai Chi Kok Gaol, Fire Fighting Appliances.—This work consisted of purchasing and installing a number of Fire Extinctures and Hose Pipes in advantageous positions recom- mended by the Fire Brigade in the various Government Build- ings.

The work was commenced in November and satisfactorily completed in December.

Estimates, Expenditure,

Waterworks:---

$5,600.00 $1,003.39

185. New Mains to Kowloon Tong Estate. A further length of 3,190 feet of 6′′ main was laid during the year.

$10,000.00 Total Estimates,

Expenditure up to 31.12.28,

1928 Estimates,

1928 Expenditure, . $ 8,580.97

$90,000.00

$85,163.90