168. Anglo-Chinese School, Cheung Chau.-Plans for this school containing six Class Rooms, Masters' Rooms, Caretaker's Quarters, Store, etc., to accommodate 192 pupils were prepared.

Tenders were obtained in November and were under consideration at the end of the year.

1927 Estimates, $40,000.00 Nil.

1927 Expenditure,

169. Gardeners' Quarters at Sheung Shui.-These quarters afford accommodation for one married gardener and four other single men, with the usual offices to each set.

A Contract for this work was let to Mr. Tang Tim on 23rd June for the sum of $3,687.35, which was completed by the end of November when the quarters were handed over to the Botanical and Forestry Department.

Total Estimates, $5,000.00

Expenditure to 31.12.27, $3,139.81

1927 Estimates, $5,000.00

1927 Expenditure, $3,139.81

170. General Works:-

$10,000.00

$3,139.81

(a.) Roads. The formation of roads in connection with Lots 875, 876, 877, 830 and 854 at Tai Po Market was carried out during the year. Macadam was laid on carriageway and tar painted, and the scavenging lanes were treated with granolithic paving.

1927 Estimates, $5,000.00

1927 Expenditure, $2,896.54

(b.) Drainage :-

(i.) Training Nullahs.-Several channels were swamps filled in at Tai Po and Tai Po Market:

laid and

1927 Estimates, $1,000.00

1927 Expenditure, $979.39

(ii) Miscellaneous Drainage Works.-Several small extensions to sewers and additional gully connections were made.

1927 Estimates, $1,000.00 1927 Expenditure, $561.85

Edit History

2026-05-07 21:08:18 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
Q 85 P.W.E. New Territories P. W. E. NEW TERRITORIES. 168. Anglo-Chinese School, Cheung Chau.-Plans for this school containing six Class Rooms, Masters' Rooms, Caretaker's Quarters, Store, etc., to accommodate 192 pupils were prepared. Tenders were obtained in November and were under consideration at the end of the year. 1927 Estimates, $40,000.00 Nil. 1927 Expenditure, 169. Gardeners' Quarters at Sheung Shui.-These quarters afford accommodation for one married gardener and four other single men, with the usual offices to each set. A Contract for this work was let to Mr. Tang Tim on 23rd June for the sum of $3,687.35, which was completed by the end of November when the quarters were handed over to the Botanical and Forestry Department. Total Estimates, $5,000.00 Expenditure to 31.12.27, $3,139.81 1927 Estimates, $5,000.00 1927 Expenditure, $3,139.81 170. General Works:- $10,000.00 $3,139.81 (a.) Roads. The formation of roads in connection with Lots 875, 876, 877, 830 and 854 at Tai Po Market was carried out during the year. Macadam was laid on carriageway and tar painted, and the scavenging lanes were treated with granolithic paving. 1927 Estimates, $5,000.00 1927 Expenditure, $2,896.54 (b.) Drainage :- (i.) Training Nullahs.-Several channels were swamps filled in at Tai Po and Tai Po Market: laid and 1927 Estimates, $1,000.00 1927 Expenditure, $979.39 (ii) Miscellaneous Drainage Works.-Several small extensions to sewers and additional gully connections were made. 1927 Estimates, $1,000.00 1927 Expenditure, $561.85
Baseline (Original)
Q 85 P.W.E. New Territories P. W. E. NEW TERRITORIES. 168. Anglo-Chinese School, Cheung Chau.-Plans for this school containing six Class Rooms, Masters' Rooms, Caretaker's Quarters, Store, etc., to accommodate 192 pupils were prepared. Tenders were obtained in November and were under con- sideration at the end of the year. 1927 Estimates, 1927 Expenditure, $40,000.00 Nil. 169. Gardeners' Quarters at Sheung Shui.-These quarters afford accommodation for one married gardener and four other single men, with the usual offices to each set. A Contract for this work was let to Mr. Tang Tim on 23rd June for the sum of $3,687.35, which was completed by the end of November when the quarters were handed over to the Botanical and Forestry Department. $5,000.00 Total Estimates, Expenditure to 31.12.27, 1927 Estimates, 1927 Expenditure, .. $3,139.81 170. General Works:- $10,000.00 $ 3,139.81 (a.) Roads. The formation of roads in connection with Lots 875, 876, 877, 830 and 854 at Tai Po Market was carried cut during the year. Macadam was laid on carriageway and tar painted, and the scavenging lanes were treated with granolithic paving. 1927 Estimates, 1927 Expenditure, $5,000.00 $2,896.54 (b.) Drainage :- (i.) Training Nullahs.-Several channels were swamps filled in at Tai Po and Tai Po Market: laid and 1927 Estimates, 1927 Expenditure, $1,000.00 $ 979.39 (ii) Miscellaneous Drainage Works.-Several small exten- sions to sewers and additional gully connections were made. 1927 Estimates, 1927 Expenditure, $1,000.00 $ 561.85
2026-05-07 21:08:18 · Baseline
View content

Q 85

P.W.E. New Territories

P. W. E. NEW TERRITORIES.

168. Anglo-Chinese School, Cheung Chau.-Plans for this school containing six Class Rooms, Masters' Rooms, Caretaker's Quarters, Store, etc., to accommodate 192 pupils were prepared.

Tenders were obtained in November and were under con- sideration at the end of the year.

1927 Estimates,

1927 Expenditure,

$40,000.00 Nil.

169. Gardeners' Quarters at Sheung Shui.-These quarters afford accommodation for one married gardener and four other single men, with the usual offices to each set.

A Contract for this work was let to Mr. Tang Tim on 23rd June for the sum of $3,687.35, which was completed by the end of November when the quarters were handed over to the Botanical and Forestry Department.

$5,000.00 Total Estimates,

Expenditure to

31.12.27,

1927 Estimates,

1927 Expenditure, .. $3,139.81

170. General Works:-

$10,000.00

$ 3,139.81

(a.) Roads. The formation of roads in connection with Lots 875, 876, 877, 830 and 854 at Tai Po Market was carried cut during the year. Macadam was laid on carriageway and tar painted, and the scavenging lanes were treated with granolithic paving.

1927 Estimates,

1927 Expenditure,

$5,000.00 $2,896.54

(b.) Drainage :-

(i.) Training Nullahs.-Several channels were swamps filled in at Tai Po and Tai Po Market:

laid and

1927 Estimates,

1927 Expenditure,

$1,000.00 $ 979.39

(ii) Miscellaneous Drainage Works.-Several small exten- sions to sewers and additional gully connections were made.

1927 Estimates, 1927 Expenditure,

$1,000.00

$ 561.85