P.W.E. Kowloon,
Q.72
Progress during the year was slow, the delay being due to the large percentage of bed rock met with.
...
1927 Estimates, $20,000.00 Total Estimates, 1927 Expenditure, $1,550.00 Expenditure to $60,500.00 31.12.27, $27,151.94
(e.) Surfacing Road to Kowloon Hospital (Waterloo Road).--- That portion of Waterloo Road from the Railway Bridge to the Eastern Entrance to the Hospital was kerbed, channelled, macadamized and tar painted.
1927 Estimates, 1927 Expenditure, $85,000.00 $32,103.68
140. Miscellaneous Drainage Works:—
(a.) Mong Kok Tsui Nullah, East. This work was referred to in paragraphs 178 (a.) of the Report for 1925 and 139 (a.) of that for last year.
This item formed part of Contract No. 24 of 1922. As already mentioned in a previous paragraph, the Contractors, Messrs. Li Hing & Bros., were involved in litigation over this Contract, and the decision come to in that case applied equally to this work.
A further length of decking under the No. 8 Railway Bridge was laid by the end of the year.
1927 Estimates, 1927 Expenditure, $5,000.00 Total Estimates, $162,003.00 Expenditure to $4,996.78 31.12.27, $161,598.93
(b.) Kau Lung Tong Village Area,--Stormwater Drain to Mong Kok Tsui Nullah.-A reference to this work appeared in paragraph 140 (c.) of last year's Report.
The section that was considered necessary to meet the present requirements was completed during the year.
1927 Estimates, 1927 Expenditure, $30,000.00 $17,208.21
(c.) Training Stream Course in the New Cemetery Area, Ho Mun Tin.—A Contract was let and a commencement made with this work after the rainy season. Although good progress was made it was not found possible to complete it within the year.
1927 Estimates, 1927 Expenditure, $40,000.00 $14,045.74
P.W.E. Kowloon,
Q.72
Progress during the year was slow, the delay being due to the large percentage of bed rock met with.
...
1927 Estimates, $20,000.00 Total Estimates, 1927 Expenditure,. $ 1,550.00 Expenditure to
$60,500.00
31.12.27,
$27,151.94
(e.) Surfacing Road to Kowloon Hospital (Waterloo Road).--- That portion of Waterloo Road from the Railway Bridge to the Eastern Entrance to the Hospital was kerbed, channelled, maca- damized and tar painted.
1927 Estimates,
1927 Expenditure,
140. Miscellaneous Drainage Works:—
$85,000.00 $32,103.68
(a.) Mong Kok Tsui Nullah, East. This work was referred to in paragraphs 178 (a.) of the Report for 1925 and 139 (a.) of that for last year.
This item formed part of Contract No. 24 of 1922. As already mentioned in a previous paragraph, the Contractors, Messrs. Li Hing & Bros., were involved in litigation over this Contract, and the decision come to in that case applied equally to this work.
A further length of decking under the No. 8 Railway Bridge was laid by the end of the year.
1927 Estimates,
1927 Expenditure,
$5,000.00 Total Estimates, . $162,003.00
Expenditure to
$4,996.78 31.12.27,
$161,598.93
(b.) Kau Lung Tong Village Area,--Stormwater Drain to Mong Kok Tsui Nullah.-A reference to this work appeared in paragraph 140 (c.) of last year's Report.
The section that was considered necessary to meet the present requirements was completed during the year.
1927 Estimates,
1927 Expenditure,
$30,000.00 $17,208.21
(c.) Training Stream Course in the New Cemetery Area, Ho Mun Tin.—A Contract was let and a commencement made with this work after the rainy season. Although good progress was made it was not found possible to complete it within the
year.
1927 Estimates, 1927 Expenditure,
$40,000.00 $14,045.74