Q 65

P.W.E, Hong Kong.

Owing to dumping from other sources, the material available in Morrison Hill is more than the quantity required to fill in the Praya East Reclamation. The material on the top portion of the hill appeared to be more satisfactory for reclamation purposes; therefore, it was decided to cut down to a level of 55 feet above O.D. instead of to the levels originally decided.

$10,000.00 37,000.00

1927 Estimates,

1927 Sup. Vote,

$47,000.00

Expenditure to

1927 Expenditure,. $39,662.76 31.12.27,

$85,668.73

130. Construction of Nullah through Bowrington Canal from South of Praya to Leighton Hill Road.—This work was referred to under the heading **"Twin Culverts"** in Annexe L at page 166 of last year's Report.

The nullah is 1,052 feet in length and 30 feet in width, the East side thereof being formed for a distance of 635 feet by the existing wall of the Bowrington Canal which has been raised by about 3 feet 6 inches in height. Good progress was made with the construction of the remaining portion of the East wall, 185 feet being erected. 820 feet of the invert and a similar length of the West wall had been completed at the end of the year. This work necessitates the reconstruction of a portion of the bridge at Leighton Hill Road and of the bridge over the Bowrington Canal on the Praya East Roadway, but this reconstruction work has not been put in hand.

1927 Estimates,

$80,000.00 Total Estimates, . $200,000.00

Expenditure to

31.12.27,

1927 Expenditure,. $79,700.88

$ 79,700.88

131. Soldiers' and Sailors' Home.-This vote provided for the payment of compensation in connection with the removal of this Home then situated on I.L. 1212, Arsenal Street, to its new site, I.L. 2616, which was granted by the Government on the alignment of the new 100 foot road.

$75,000 Total Estimates,

1927 Estimates, 1927 Expenditure, $40,000 Expenditure to

31.12.27,

$90,350

$54,536

132. Compensation and Resumptions.-This vote provided for the resumption of areas required in connection with street widening and improvement schemes, new roads, the development of village areas in accordance with the provisions of the Public Health and Buildings Ordinance, 1903, and for resumptions for all other purposes.

Edit History

2026-05-07 21:01:31 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
Q 65 P.W.E, Hong Kong. Owing to dumping from other sources, the material available in Morrison Hill is more than the quantity required to fill in the Praya East Reclamation. The material on the top portion of the hill appeared to be more satisfactory for reclamation purposes; therefore, it was decided to cut down to a level of 55 feet above O.D. instead of to the levels originally decided. $10,000.00 37,000.00 1927 Estimates, 1927 Sup. Vote, $47,000.00 Expenditure to 1927 Expenditure,. $39,662.76 31.12.27, $85,668.73 130. Construction of Nullah through Bowrington Canal from South of Praya to Leighton Hill Road.—This work was referred to under the heading **"Twin Culverts"** in Annexe L at page 166 of last year's Report. The nullah is 1,052 feet in length and 30 feet in width, the East side thereof being formed for a distance of 635 feet by the existing wall of the Bowrington Canal which has been raised by about 3 feet 6 inches in height. Good progress was made with the construction of the remaining portion of the East wall, 185 feet being erected. 820 feet of the invert and a similar length of the West wall had been completed at the end of the year. This work necessitates the reconstruction of a portion of the bridge at Leighton Hill Road and of the bridge over the Bowrington Canal on the Praya East Roadway, but this reconstruction work has not been put in hand. 1927 Estimates, $80,000.00 Total Estimates, . $200,000.00 Expenditure to 31.12.27, 1927 Expenditure,. $79,700.88 $ 79,700.88 131. Soldiers' and Sailors' Home.-This vote provided for the payment of compensation in connection with the removal of this Home then situated on I.L. 1212, Arsenal Street, to its new site, I.L. 2616, which was granted by the Government on the alignment of the new 100 foot road. $75,000 Total Estimates, 1927 Estimates, 1927 Expenditure, $40,000 Expenditure to 31.12.27, $90,350 $54,536 132. Compensation and Resumptions.-This vote provided for the resumption of areas required in connection with street widening and improvement schemes, new roads, the development of village areas in accordance with the provisions of the Public Health and Buildings Ordinance, 1903, and for resumptions for all other purposes.
Baseline (Original)
Q 65 P.W.E, Hong Kong. Owing to dumping from other sources, the material available in Morrison Hill is more than the quantity required to fill in the Praya East Reclamation. The material on the top portion of the hill appeared to be more satisfactory for reclamation pur- poses; therefore, it was decided to cut down to a level of 55 feet above O.D. instead of to the levels originally decided. $10,000.00 37,000.00 1927 Estimates, 1927 Sup. Vote, $47,000.00 Expenditure to 1927 Expenditure,. $39,662.76 31.12.27, $85,668.73 130. Construction of Nullah through Bowrington Canal from South of Praya to Leighton Hill Road.—This work was referred to under the heading **Twin Culverts" in Annexe L at page 166 of last year's Report. The nullah is 1,052 feet in length and 30 feet in width, the East side thereof being formed for a distance of 635 feet by the existing wall of the Bowrington Canal which has been raised by about 3 feet 6 inches in height. Good progress was made with the construction of the remaining portion of the East wall, 185 feet being erected. 820 feet of the invert and a similar length of the West wall had been completed at the end of the year. This work necessitates the reconstruction of a portion of the bridge at Leighton Hill Road and of the bridge over the Bowrington Canal on the Praya East Roadway, but this recon- struction work has not been put in hand. 1927 Estimates, ,000.00 $80,000.00 Total Estimates, . $200,000.00 Expenditure to 31.12.27, 1927 Expenditure,. $79,700.88 $ 79,700.88 131. Soldiers' and Sailors' Home.-This vote provided for the payment of compensation in connection with the removal of this Home then situated on I.L. 1212, Arsenal Street, to its new site, I.L. 2616, which was granted by the Government on the alignment of the new 100 foot road. A $75,000 Total Estimates, 1927 Estimates, 1927 Expenditure, $40,000 Expenditure to 31.12.27, $90,350 $54,536 132. Compensation and Resumptions.-This vote provided for the resumption of areas required in connection with street widening and improvement schemes, new roads, the development of village areas in accordance with the provisions of the Public Health and Buildings Ordinance, 1993, and for resumptions for all other purposes.
2026-05-07 21:01:31 · Baseline
View content

Q 65

P.W.E, Hong Kong.

Owing to dumping from other sources, the material available in Morrison Hill is more than the quantity required to fill in the Praya East Reclamation. The material on the top portion of the hill appeared to be more satisfactory for reclamation pur- poses; therefore, it was decided to cut down to a level of 55 feet above O.D. instead of to the levels originally decided.

$10,000.00 37,000.00

1927 Estimates,

1927 Sup. Vote,

$47,000.00

Expenditure to

1927 Expenditure,. $39,662.76 31.12.27,

$85,668.73

130. Construction of Nullah through Bowrington Canal from South of Praya to Leighton Hill Road.—This work was referred to under the heading **Twin Culverts" in Annexe L at page 166 of last year's Report.

The nullah is 1,052 feet in length and 30 feet in width, the East side thereof being formed for a distance of 635 feet by the existing wall of the Bowrington Canal which has been raised by about 3 feet 6 inches in height. Good progress was made with the construction of the remaining portion of the East wall, 185 feet being erected. 820 feet of the invert and a similar length of the West wall had been completed at the end of the year. This work necessitates the reconstruction of a portion of the bridge at Leighton Hill Road and of the bridge over the Bowrington Canal on the Praya East Roadway, but this recon- struction work has not been put in hand.

1927 Estimates,

,000.00

$80,000.00 Total Estimates, . $200,000.00

Expenditure to

31.12.27,

1927 Expenditure,. $79,700.88

$ 79,700.88

131. Soldiers' and Sailors' Home.-This vote provided for the payment of compensation in connection with the removal of this Home then situated on I.L. 1212, Arsenal Street, to its new site, I.L. 2616, which was granted by the Government on the alignment of the new 100 foot road.

A

$75,000 Total Estimates,

1927 Estimates, 1927 Expenditure, $40,000 Expenditure to

31.12.27,

$90,350

$54,536

132. Compensation and Resumptions.-This vote provided for the resumption of areas required in connection with street widening and improvement schemes, new roads, the development of village areas in accordance with the provisions of the Public Health and Buildings Ordinance, 1993, and for resumptions for all other purposes.