P.W.E. Hong Kong.
F
Q 54
(d.) Stubbs Road, Improvements to junction with Morrison Gap Road. The portion of Morrison Gap Road at its junction with Stubbs Road was regraded and surfaced with tar macadam.
1927 Estimates, $10,000.00
1927 Expenditure, $9,066.34
(e.) Garden Road, Improvements to Island at the junction with Lower Albert Road. The work of improving this island was completed during the year.
1927 Estimates, $2,000.00
1927 Expenditure, $407.95
111. Training Nullahs:-
L
(a.) Wong Nei Chong Nullah, Section No. 1—from near Blue Pool to the existing nullah. This work, which was referred to in paragraph 115 (a.) of last year's Report, was completed during the year.
1927 Estimates, $20,000.00
Total Estimates, $124,500.00
1927 Expenditure, $19,485.58
Expenditure to 31.12.27, $103,944.71
(b.) Reconstruction of Wong Nei Chong Nullah, Section No. 2—through Happy Valley from Wong Nei Chong to Race Stands. This work, which was referred to in paragraph 115 (b.) of last year's Report, was completed during the year.
1927 Estimates, $20,000.00
1927 Sup. Vote, $726.00
Total Estimates, $80,000.00
1927 Expenditure, $20,725.08
Expenditure to 31.12.27, $75,149.55
(c.) Reconstruction of Wong Nei Chong Nullah, Section No. 3—from Bowrington Canal to the Chinese Stand.—A Contract for this work was let in June, and operations were commenced after the rainy season. Very good progress was made with the foundations, walling, and flooring by the end of the year.
1927 Estimates, $100,000.00
Total Estimates, $100,000.00
Expenditure to 31.12.27, $42,005.53
1927 Expenditure, $42,005.53
Page 540
Page 541
P.W.E. Hong Kong.
F
Q 54
(d.) Stubbs Road, Improvements to junction with Morrison Gap Road. The portion of Morrison Gap Road at its junction with Stubbs Road was regraded and surfaced with tar macadam.
1927 Estimates,
1927 Expenditure,
$10,000.00 $ 9,066.34
(e.) Garden Road, Improvements to Island at the junction with Lower Albert Road. The work of improving this island was completed during the year.
1927 Estimates,
1927 Expenditure,
111. Training Nullahs:-
L
$2,000.00
$ 407.95
(a.) Wong Nei Chong Nullah, Section No. 1—from near Blue Pool to the existing nullah. This work, which was referred to in paragraph 115 (a.) of last year's Report, was completed during the year.
$20,000.00 Total Estimates, ..$124,500.00
1927 Estimates,
1927 Expenditure,
Expenditure to
$19,485.58 31.12.27,
$103,944.71
(b.) Reconstruction of Wong Nei Chong Nullah, Section No. 2-through Happy Valley from Wong Nei Chong to Race Stands. -This work, which was referred to in paragraph 115 (b.) of last year's Report, was completed during the year.
1927 Estimates,
1927 Sup. Vote,
$20,000.00 Total Estimates,
726.00
$80,000.00
1927 Expenditure,
$20,726.00 Expenditure to $20,725.08 31.12.27,
$75,149.55
(c.) Reconstruction of Wong Nei Chong Nullah, Section No. 3-from Bowrington Canal to the Chinese Stand.—A Con- tract for this work was let in June, and operations were com- menced after the rainy season. Very good progress was made with the foundations, walling, and flooring by the end of the
year.
1927 Estimates, $100,000.00 Total Estimates,
...
•
$100,000.00
Expenditure to
$ 42,005.53
1927 Expenditure, ..$ 42,005.53 31.12.27,
Page 540Page 541