P.W.E. Kowloon
Q 88
P.W.E. KOWLOON.
134. Kowloon Hospital:-
(a.) Buildings and Furniture. (b.) Site.
This work was referred to in paragraph 153 of last year's Report.
(a.) The small amount of work remaining to be done to complete the preliminary scheme was carried out early in the year and the building entirely handed over to the Department.
Medical
(b.) The site formation was completed by the end of the year but the laying-out and turfing still remained to be undertaken.
(a) 1926 Estimates, $35,000.00 Total Estimates, $604,000.00
1926 Sup. Vote, 80,000.00 $115,000.00
(b) 1926 Estimates, $20,000.00
1926 Sup. Votes, 18,500.00
(a) 1926 Expenditure, $38,500.00
(b) 1926 Expenditure, $112,606.36 38,387.94
Expenditure to 31.12.26, 913,670.09
135. Hung Hom Market Extension.-12 Fish Stalls with Tanks. This work, referred to in paragraph 160 of last year's Report, was satisfactorily completed before the end of the year.
1926 Estimates, $5,500.00 Total Estimates, $10,000.00
1926 Sup. Vote, $4,500.00
Expenditure to 31.12.26, $12,000.00
1926 Expenditure, $9,967.62 $14,880.18
136. Workshop and Quarters for the Electrical and Telephone Staff. This work, referred to in paragraph 165 of last year's report, was completed early in the year.
1926 Estimates, $5,000.00 Total Estimates, $62,000.00
Expenditure to 31.12.26, $53,043.94
1926 Expenditure, $4,708.76
137. Public Latrines and Urinals.-The release of retention moneys was made in respect of:
(a) Man Ming Lane Trough Closet and
(b) Dock Lane Latrine Site, Hung Hom.
(b) This site was levelled during 1925, the total cost of the work being $7,120.75.
Page 630
Page 631
P.W.E. Kowloon
سي يعد
Q 88
P.W.E. KOWLOON.
134. Kowloon Hospital:-
(a.) Buildings and Furniture. (b.) Site.
This work was referred
to in paragraph 153 of last year's Report.
(a.) The small amount of work remaining to be done to complete the preliminary scheme was carried out early in the year and the building entirely handed over to the Department.
Medical
(b.) The site formation was completed by the end of the year but the laying-out and turfing still remained to be under- taken.
(a) 1926 Estimates, $35,000.00 Total Estimates, ..$604,000.00
1926 Sup. Vote, 80,000.00
$115,000,00
(b) 1926 Estimates, $20,000.00
1926 Sup. Votes, 18,500.00
(a) 1926 Expendi-
ture,
(b) 1926 Expendi-
ture,
$38,500.00
$112,606.36
38,387.94
Expenditure to
31.12.26,
913.670.09
135. Hung Hom Market Extension.-12 Fish Stalls with Tanks. This work, referred to in paragraph 160 of last year's Report, was satisfactorily completed before the end of the year.
1926 Estimates, $ 5,500.00 Total Estimates, 1926 Sup. Vote, ....$ 4,500.00
$10,000.00 Expenditure to
31.12.26,
1926 Expenditure, $ 9,967.62
136. Workshop and Quarters for the
$12,000.00
$14,880.18
Electrical and
Telephone Staff. This work, referred to in paragraph 165 of last year's report, was completed early in the year.
1926 Estimates,
$5,000.00 Total Estimates,
31.12.26,
1926 Expenditure, ..$4,708.76 Expenditure to
..$62,000.00
$53,043.94
137. Public Latrines and Urinals.-The release of retention
moneys was made in respect or:
(a) Man Ming Lane Trough Closet and
(b) Dock Lane Latrine Site, Hung Hom.
(b) This site was levelled during 1925, the total cost of the work being $7,120.75.
Page 630Page 631