AnnualReport-1926 — Page 592

Administrative Reports 行政報告書 All AI Reviewed

P.W.R. Hong Kong.

Q 50

80. Maintenance of Public Recreation Grounds.-The various grounds were maintained in good order. The use of departmental labour for the purpose of mowing grass, cleansing ditches, etc., was continued.

61. Dredging Foreshores.-The No. 1 Grab Dredger was employed at the following places and removed quantities of material as stated hereunder during the year:-

Drain outfalls Cubic Yards.
25,294 Sanitary and other Piers Causeway Bay 12,499 On hire 446 TOTAL 1,723
39,962

The above material was deposited on the reclamation sites at Sham Shui Po, North Point, and Kennedy Town and also outside the Harbour.

It was not found possible to put the Dredger on the slip for the annual overhaul, owing to the increased amount of dredging it had to undertake after the heavy rainstorm of July.

For the hire of the Dredger a sum of $317.63 was received during the year.

1926 Estimates 1926 Expenditure $12,000.00 $11,548.23

62. Typhoon and Rainstorm Damages.—On the morning of 18th July, 1926, a typhoon entered the coast of the mainland of China one hundred miles to the East of Hong Kong and was followed on the 19th idem by a torrential rainfall and thunderstorm causing extensive damage to many parts of the Colony.

So heavy, indeed, was the rainfall that 20.015 inches was recorded within the short space of eight hours. This record has not been approached since 30th May, 1898, when a fall of 20.493 inches was registered in sixteen hours.

This terrific deluge falling upon precipitous country caused tons of earth, boulders, sand and silt to be washed down the hillsides blocking and bursting numerous nullahs and channels, with the consequent flooding of the main roads of the City, the water finding its way into houses and godowns causing heavy damage. In several cases private houses were severely shaken necessitating shoring, but fortunately no collapse occurred.

Edit History

2026-05-07 13:35:27 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
P.W.R. Hong Kong. Q 50 80. Maintenance of Public Recreation Grounds.-The various grounds were maintained in good order. The use of departmental labour for the purpose of mowing grass, cleansing ditches, etc., was continued. 61. Dredging Foreshores.-The No. 1 Grab Dredger was employed at the following places and removed quantities of material as stated hereunder during the year:- Drain outfalls Cubic Yards.25,294 Sanitary and other Piers Causeway Bay 12,499 On hire 446 TOTAL 1,72339,962 The above material was deposited on the reclamation sites at Sham Shui Po, North Point, and Kennedy Town and also outside the Harbour. It was not found possible to put the Dredger on the slip for the annual overhaul, owing to the increased amount of dredging it had to undertake after the heavy rainstorm of July. For the hire of the Dredger a sum of $317.63 was received during the year. 1926 Estimates 1926 Expenditure $12,000.00 $11,548.23 62. Typhoon and Rainstorm Damages.—On the morning of 18th July, 1926, a typhoon entered the coast of the mainland of China one hundred miles to the East of Hong Kong and was followed on the 19th idem by a torrential rainfall and thunderstorm causing extensive damage to many parts of the Colony. So heavy, indeed, was the rainfall that 20.015 inches was recorded within the short space of eight hours. This record has not been approached since 30th May, 1898, when a fall of 20.493 inches was registered in sixteen hours. This terrific deluge falling upon precipitous country caused tons of earth, boulders, sand and silt to be washed down the hillsides blocking and bursting numerous nullahs and channels, with the consequent flooding of the main roads of the City, the water finding its way into houses and godowns causing heavy damage. In several cases private houses were severely shaken necessitating shoring, but fortunately no collapse occurred.
Baseline (Original)
P.W.R. Hong Kong. Q 50 80. Maintenance of Public Recreation Grounds.-The various grounds were maintained in good order. The use of departmental labour for the purpose of mowing grass, cleansing ditches, etc., was continued. 61. Dredging Foreshores.-The No. 1 Grab Dredger was employed at the following places and removed quantities of material as stated hereunder during the year:- Drain outfalls Sanitary and other Piers Causeway Bay On hire TOTAL Cubic Yards. 25,294 12,499 1,723 446 39,962 The above material was deposited on the reclamation sites at Sham Shui Po, North Point, and Kennedy Town and also outside the Harbour. It was not found possible to put the Dredger on the slip for the annual overhaul, owing to the increased amount of dredging it had to undertake after the heavy rainstorm of July. For the hire of the Dredger a sum of $317.63 was received during the year. 1926 Estimates 1926 Expenditure $12,000.00 $11,548.23 62. Typhoon and Rainstorm Damages.—On the morning of 18th July, 1926, a typhoon entered the coast of the mainland of China one hundred miles to the East of Hong Kong and was followed on the 19th idem by a torrential rainfall and thunder- storm causing extensive damage to many parts of the Colony. So heavy, indeed, was the rainfall that 20.015 inches was recorded within the short space of eight hours. This record has. not been approached since 30th May, 1898, when a fall of 20.493 inches was registered in sixteen hours. This terrific deluge falling upon precipitous country caused tons of earth, boulders, sand and silt to be washed down the hillsides blocking and bursting numerous nullahs and channels, with the consequent flooding of the main roads of the City, the water finding its way into houses and godowns causing heavy damage. In several cases private houses were severely shaken necessitating shoring, but fortunately no collapse occurred.
2026-05-07 13:35:27 · Baseline
View content

P.W.R. Hong Kong.

Q 50

80. Maintenance of Public Recreation Grounds.-The various grounds were maintained in good order. The use of departmental labour for the purpose of mowing grass, cleansing ditches, etc., was continued.

61. Dredging Foreshores.-The No. 1 Grab Dredger was employed at the following places and removed quantities of material as stated hereunder during the year:-

Drain outfalls

Sanitary and other Piers Causeway Bay

On hire

TOTAL

Cubic Yards.

25,294

12,499

1,723

446

39,962

The above material was deposited on the reclamation sites at Sham Shui Po, North Point, and Kennedy Town and also outside the Harbour.

It was not found possible to put the Dredger on the slip for the annual overhaul, owing to the increased amount of dredging it had to undertake after the heavy rainstorm of July.

For the hire of the Dredger a sum of $317.63 was received during the year.

1926 Estimates

1926 Expenditure

$12,000.00 $11,548.23

62. Typhoon and Rainstorm Damages.—On the morning of 18th July, 1926, a typhoon entered the coast of the mainland of China one hundred miles to the East of Hong Kong and was followed on the 19th idem by a torrential rainfall and thunder- storm causing extensive damage to many parts of the Colony.

So heavy, indeed, was the rainfall that 20.015 inches was recorded within the short space of eight hours. This record has. not been approached since 30th May, 1898, when a fall of 20.493 inches was registered in sixteen hours.

This terrific deluge falling upon precipitous country caused tons of earth, boulders, sand and silt to be washed down the hillsides blocking and bursting numerous nullahs and channels, with the consequent flooding of the main roads of the City, the water finding its way into houses and godowns causing heavy damage. In several cases private houses were severely shaken necessitating shoring, but fortunately no collapse occurred.

Comments

Approved members can add comments, bookmarks, and private notes.

No comments yet.

Private Research Note

Private notes are available after approval.