G 121

P.W.E. New Territories.

(g.) Waterloo Road Extension (100 feet wide) Section between Kowloon Boundary to foot of hills S. E. of Tunnel (estimate for 50 foot width).—This work was referred to in paragraphs 196 (3) of the Report for 1923 and 205 (g) of that for last year.

Good progress was maintained and by the end of the year the road was well advanced.

1925 Estimates, $4,500.00 1925 Sup. Vote, $5,000.00 Total Estimates, $9,500.00 Expenditure to 31.12.25, $20,100.00 1925 Expenditure, $5,647.50

(h.) Fanling-Shataukok Road. This work was referred to in paragraphs 245 of the Report for 1923 and 205 (j) of that for last year.

The 1st section of the road was handed over to the Roads Maintenance Office in March, which was strengthened, surfaced with ordinary macadam and tar painted. Work on the 2nd section proceeded satisfactorily and when the railway has been re-aligned the road should be completed within 3 months.

1925 Estimates, $40,000.00 1925 Sup. Vote, $75,000.00 Total Estimates, $115,000.00 Expenditure to 31.12.25, $139,563.68 1925 Expenditure, $73,879.00

(i.) Path from Ta Ku Ling to Lin Ma Hang for patrol purposes.—A preliminary survey for alignment was made, but it was not found possible to proceed with this work during the year; consequently no expenditure was incurred.

1925 Estimates, $15,000.00 1925 Expenditure, Nil.

(j) Road to Shun Wan.—A survey was made for improving and realigning the existing path, but no actual work was commenced; consequently there was no expenditure under this heading.

1925 Estimates, $10,000.00 1925 Expenditure, Nil.

Edit History

2026-05-07 10:55:53 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
G 121 P.W.E. New Territories. (g.) Waterloo Road Extension (100 feet wide) Section between Kowloon Boundary to foot of hills S. E. of Tunnel (estimate for 50 foot width).—This work was referred to in paragraphs 196 (3) of the Report for 1923 and 205 (g) of that for last year. Good progress was maintained and by the end of the year the road was well advanced. 1925 Estimates, $4,500.00 1925 Sup. Vote, $5,000.00 Total Estimates, $9,500.00 Expenditure to 31.12.25, $20,100.00 1925 Expenditure, $5,647.50 (h.) Fanling-Shataukok Road. This work was referred to in paragraphs 245 of the Report for 1923 and 205 (j) of that for last year. The 1st section of the road was handed over to the Roads Maintenance Office in March, which was strengthened, surfaced with ordinary macadam and tar painted. Work on the 2nd section proceeded satisfactorily and when the railway has been re-aligned the road should be completed within 3 months. 1925 Estimates, $40,000.00 1925 Sup. Vote, $75,000.00 Total Estimates, $115,000.00 Expenditure to 31.12.25, $139,563.68 1925 Expenditure, $73,879.00 (i.) Path from Ta Ku Ling to Lin Ma Hang for patrol purposes.—A preliminary survey for alignment was made, but it was not found possible to proceed with this work during the year; consequently no expenditure was incurred. 1925 Estimates, $15,000.00 1925 Expenditure, Nil. (j) Road to Shun Wan.—A survey was made for improving and realigning the existing path, but no actual work was commenced; consequently there was no expenditure under this heading. 1925 Estimates, $10,000.00 1925 Expenditure, Nil.
Baseline (Original)
+ G 121 P.W.E. New Territories. (g.) Waterloo Road Extension (100 feet wide) Section be- tween Kowloon Boundary to foot of hills S. E. of Tunnel (esti- mate for 50 foot width).—This work was referred to in paragraphs 196 (3) or the Report for 1923 and 205 (g) of that for last year. Good progress was maintained and by the end of the year the road was well advanced. 1925 Estimates, 1925 Sup. Vote, $ 5,000.00 Total Estimates, 4,500.00 $9,500.00 Expenditure to 31.12.25, 1925 Expenditure, $ 5,647.50 ་་ $ $ 20,100.00 (h.) Fanling-Shataukok Road. This work was referred to in paragraphs 245 of the Report for 1923 and 205 (j) of that for last year. 1 The 1st section of the road was handed over to the Roads Maintainance Office in March, which was strengthened, surfaced with ordinary macadam and tar painted. Work on the 2nd section proceeded satisfactorily and when the railway has been re-aligned the road should be completed within 3 months. 1925 Estimates, 1925 Sup. Vote, ... .$ 75,000.00 Total Estimates, ...$168,000.00 40,000.00 $115,000.00 Expenditure to 1925 Expenditure, $ 73,879.00 31.12.25, $139,563.68 (i.) Path from Ta Ku Ling to Lin Ma Hang for patrol pur- poses.-A preliminary survey for alignment was made, but it was not found possible to proceed with this work during the year; consequently no expenditure was incurred. 1925 Estimates, 1925 Expenditure, $ 15,000.00 Nil. (j) Road to Shun Wan.-A survey was made for improving and realigning the existing path, but no actual work was com- menced; consequently there was no expenditure under this heading. 1925 Estimates, 1925 Expenditure, $ 10,000.00 Nil.
2026-05-07 10:55:53 · Baseline
View content

+

G 121

P.W.E. New Territories.

(g.) Waterloo Road Extension (100 feet wide) Section be- tween Kowloon Boundary to foot of hills S. E. of Tunnel (esti- mate for 50 foot width).—This work was referred to in paragraphs 196 (3) or the Report for 1923 and 205 (g) of that for last year.

Good progress was maintained and by the end of the year the road was well advanced.

1925 Estimates, 1925 Sup. Vote,

$ 5,000.00 Total Estimates,

4,500.00

$9,500.00 Expenditure to

31.12.25,

1925 Expenditure, $ 5,647.50

་་

$

$ 20,100.00

(h.) Fanling-Shataukok Road. This work was referred to in paragraphs 245 of the Report for 1923 and 205 (j) of that for last year.

1

The 1st section of the road was handed over to the Roads Maintainance Office in March, which was strengthened, surfaced with ordinary macadam and tar painted. Work on the 2nd section proceeded satisfactorily and when the railway has been re-aligned the road should be completed within 3 months.

1925 Estimates, 1925 Sup. Vote,

...

.$ 75,000.00 Total Estimates, ...$168,000.00

40,000.00

$115,000.00 Expenditure to

1925 Expenditure, $ 73,879.00

31.12.25,

$139,563.68

(i.) Path from Ta Ku Ling to Lin Ma Hang for patrol pur- poses.-A preliminary survey for alignment was made, but it was not found possible to proceed with this work during the year; consequently no expenditure was incurred.

1925 Estimates,

1925 Expenditure,

$ 15,000.00

Nil.

(j) Road to Shun Wan.-A survey was made for improving and realigning the existing path, but no actual work was com- menced; consequently there was no expenditure under this heading.

1925 Estimates, 1925 Expenditure,

$ 10,000.00

Nil.