P.W.E. New Territories.

207. Magnetic Huts.-Owing to the plans not being ready, it was not found possible to proceed with this work; consequently there was no expenditure under this heading.

1925 Estimates, $40,000.00

1925 Expenditure, Nil.

208. Open Market, Kowloon City.-Though plans were prepared, it was not found possible to proceed with this work; consequently no expenditure was incurred.

1925 Estimates, $15,000.00

1925 Expenditure, Nil.

209. Sanitary Inspector's Quarters, Kowloon City.-It was not found possible to proceed with this work; consequently there was no expenditure under this heading.

1925 Estimates, $25,000.00

1925 Expenditure, Nil.

210. Public Latrines, Urinals and Bath-houses.

Trough Closet, Taipo Market. This work was referred to in paragraphs 195 of the report for 1923 and 199 of that for last year.

A Contract was let to Mr. Tang Tim of Un Long on 11th May, 1925. Progress during the year was slow, the foundation and walls being completed and portion of reinforced concrete roof laid before the end of the year.

1925 Estimates, $25,000.00

1925 Expenditure, $3,430.02

211. Roads:-

(a.) Metalling and tar painting hilly portions of Laichikok, Castle Peak, and Taipo Roads. This work was referred to in paragraph 205 (a) of last year's Report.

Sections of the Coastal Road from Laichikok, and Taipo Road from the 5th to 9th miles, were channelled, surfaced with 4" macadam, and tar painted.

1925 Estimates, $30,000.00

1925 Expenditure, $16,876.74

(b.) Taipo Market,-Kerbing, Channelling, &c.-This was referred to in paragraph 205 (c) of last year's Report.

Edit History

2026-05-07 10:55:40 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
Q 119 P.W.E. New Territories. 207. Magnetic Huts.-Owing to the plans not being ready, it was not found possible to proceed with this work; consequently there was no expenditure under this heading. 1925 Estimates, $40,000.00 1925 Expenditure, Nil. 208. Open Market, Kowloon City.-Though plans were prepared, it was not found possible to proceed with this work; consequently no expenditure was incurred. 1925 Estimates, $15,000.00 1925 Expenditure, Nil. 209. Sanitary Inspector's Quarters, Kowloon City.-It was not found possible to proceed with this work; consequently there was no expenditure under this heading. 1925 Estimates, $25,000.00 1925 Expenditure, Nil. 210. Public Latrines, Urinals and Bath-houses. Trough Closet, Taipo Market. This work was referred to in paragraphs 195 of the report for 1923 and 199 of that for last year. A Contract was let to Mr. Tang Tim of Un Long on 11th May, 1925. Progress during the year was slow, the foundation and walls being completed and portion of reinforced concrete roof laid before the end of the year. 1925 Estimates, $25,000.00 1925 Expenditure, $3,430.02 211. Roads:- (a.) Metalling and tar painting hilly portions of Laichikok, Castle Peak, and Taipo Roads. This work was referred to in paragraph 205 (a) of last year's Report. Sections of the Coastal Road from Laichikok, and Taipo Road from the 5th to 9th miles, were channelled, surfaced with 4" macadam, and tar painted. 1925 Estimates, $30,000.00 1925 Expenditure, $16,876.74 (b.) Taipo Market,-Kerbing, Channelling, &c.-This was referred to in paragraph 205 (c) of last year's Report.
Baseline (Original)
Q 119 P.W.E. New Territories. 207. Magretic Huts.-Owing to the plans not being ready, it was not found possible to proceed with this work; consequently there was no expenditure under this heading. 1925 Estimates, 1925 Expenditure, $ 40,000.00 Nil. 208. Open Market, Kowloon City.-Though plans were pre- pared, it was not found possible to proceed with this work; con- sequently no expenditure was incurred. 1925 Estimates, 1925 Expenditure, $ 15,000.00 Nil. 209. Sanitary Inspector's Quarters, Kowloon City.-It was not found possible to proceéd with this work; consequently there was no expenditure under this heading. 1925 Estimates, 1925 Expenditure, $ 25,000.00 Nil. 210. Public Latrines, Urinals and Bath-houses. Trough Closet, Taipo Market. This work was referred to in paragraphs 195 of the report for 1923 and 199 of that for last year. A Contract was let to Mr. Tang Tim of Un Long on 11th May, 1925. Progress during the year was slow, the foundation and walls being completed and portion of reinforced concrete roof laid before the end of the year. 1925 Estimates, 1925 Expenditure, 211. Roads:- $25,000.00 .$ 3,430.02 (a.) Metalling and tar painting hilly portions of Laichikok Castle Peak, and Taipo Roads.This work was reterred to m paragraph 205 (a) or last year's Report. --:་ Sections of the Coastal Road from Laichikok, and Taipo Road from the 5th to 9th miles, were channelled, surfaced with 4" macadam, and tar painted. 1925 Estimates, 1925 Expenditure, $ 30,000.00 $ 16,876.74 (b.) Taipo Market,-Kerbing, Channelling, &c.-This was. referred to in paragraph 205 (c) of last year's Report.
2026-05-07 10:55:40 · Baseline
View content

Q 119

P.W.E. New Territories.

207. Magretic Huts.-Owing to the plans not being ready, it was not found possible to proceed with this work; consequently there was no expenditure under this heading.

1925 Estimates,

1925 Expenditure,

$ 40,000.00 Nil.

208. Open Market, Kowloon City.-Though plans were pre- pared, it was not found possible to proceed with this work; con- sequently no expenditure was incurred.

1925 Estimates,

1925 Expenditure,

$ 15,000.00

Nil.

209. Sanitary Inspector's Quarters, Kowloon City.-It was not found possible to proceéd with this work; consequently there was no expenditure under this heading.

1925 Estimates,

1925 Expenditure,

$ 25,000.00 Nil.

210. Public Latrines, Urinals and Bath-houses.

Trough Closet, Taipo Market. This work was referred to in paragraphs 195 of the report for 1923 and 199 of that for last

year.

A Contract was let to Mr. Tang Tim of Un Long on 11th May, 1925. Progress during the year was slow, the foundation and walls being completed and portion of reinforced concrete roof laid before the end of the year.

1925 Estimates,

1925 Expenditure,

211. Roads:-

$25,000.00 .$ 3,430.02

(a.) Metalling and tar painting hilly portions of Laichikok Castle Peak, and Taipo Roads.This work was reterred to m paragraph 205 (a) or last year's Report.

--:་

Sections of the Coastal Road from Laichikok, and Taipo Road from the 5th to 9th miles, were channelled, surfaced with 4" macadam, and tar painted.

1925 Estimates,

1925 Expenditure,

$ 30,000.00

$ 16,876.74

(b.) Taipo Market,-Kerbing, Channelling, &c.-This was. referred to in paragraph 205 (c) of last year's Report.