P.W.E. New Territories.

118-

201. Police Station, Kowloon City.-This work was referred to in paragraph 193 of last year's Report.

The Contract was let on 16th May, 1924, to Mr. Ng Wah. The work progressed satisfactorily, the buildings being completed on 16th June, 1925, a month under the Contract time.

Total Estimates, $251,250.00

1925 Estimates, $162,000.00

1925 Sup. Vote, 40,000.00

$202,000.00

1925 Expenditure, $201,335.41

Expenditure to 31.12.25, $260,811.64

202. Police Station, Shamshuipo.-This work was referred to in paragraph 192 of last year's Report.

The Contract was let on 16th May, 1924, to the Wing Yick Company. The work progressed satisfactorily and the buildings were ready on 15th June, 1925, a month under the Contract time.

1925 Estimates, $162,000.00 Total Estimates, $251,250.00 1925 Sup. Vote, 43,000.00 $205,000.00 Expenditure to 31.12.25, $259,546.66 1925 Expenditure, $200,014.01

203. Cheung Chau School.-A scheme was prepared, but the work was not proceeded with during the year; consequently there was no expenditure under this heading.

1925 Estimates, $1,000.00

1925 Expenditure, Nil.

204. Un Long School.-This work was not proceeded with during the year; consequently there was no expenditure under this heading.

1925 Estimates, $1,000.00

1925 Expenditure, Nil.

205. Gardeners' Quarters, Sheung Shui.-It was not found possible to proceed with this work; consequently there was no expenditure under this heading.

1925 Estimates, $10,000.00

1925 Expenditure, Nil.

206. Taipo School.-Sketch plans were prepared, but it was not found possible to proceed with this work; consequently there was no expenditure under this heading.

1925 Estimates, $20,000.00

1925 Expenditure, Nil.

Edit History

2026-05-07 10:55:33 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
P.W.E. New Territories. 118- 201. Police Station, Kowloon City.-This work was referred to in paragraph 193 of last year's Report. The Contract was let on 16th May, 1924, to Mr. Ng Wah. The work progressed satisfactorily, the buildings being completed on 16th June, 1925, a month under the Contract time. Total Estimates, $251,250.00 1925 Estimates, $162,000.00 1925 Sup. Vote, 40,000.00 $202,000.00 1925 Expenditure, $201,335.41 Expenditure to 31.12.25, $260,811.64 202. Police Station, Shamshuipo.-This work was referred to in paragraph 192 of last year's Report. The Contract was let on 16th May, 1924, to the Wing Yick Company. The work progressed satisfactorily and the buildings were ready on 15th June, 1925, a month under the Contract time. 1925 Estimates, $162,000.00 Total Estimates, $251,250.00 1925 Sup. Vote, 43,000.00 $205,000.00 Expenditure to 31.12.25, $259,546.66 1925 Expenditure, $200,014.01 203. Cheung Chau School.-A scheme was prepared, but the work was not proceeded with during the year; consequently there was no expenditure under this heading. 1925 Estimates, $1,000.00 1925 Expenditure, Nil. 204. Un Long School.-This work was not proceeded with during the year; consequently there was no expenditure under this heading. 1925 Estimates, $1,000.00 1925 Expenditure, Nil. 205. Gardeners' Quarters, Sheung Shui.-It was not found possible to proceed with this work; consequently there was no expenditure under this heading. 1925 Estimates, $10,000.00 1925 Expenditure, Nil. 206. Taipo School.-Sketch plans were prepared, but it was not found possible to proceed with this work; consequently there was no expenditure under this heading. 1925 Estimates, $20,000.00 1925 Expenditure, Nil.
Baseline (Original)
P.W.E. New Territories. 118- 201. Police Station, Kowloon City.-This work was referred to in paragraph 193 of last year's Report. The Contract was let on 16th May, 1924, to Mr. Ng Wah. The work progressed satisfactorily, the buildings being completed on 16th June, 1925, a month under the Contract time. .$162,000.00 Total Estimates, ...$251,250.00 40,000.00 1925 Estimates, 1925 Sup. Vote, $202,000.00 1925 Expenditure, $201,335.41 Expenditure to 31.12.25, ...... $260,811.64 202. Police Station, Shamshuipo.-This work was referred to in paragraph 192 of last year's Report. The Contract was let on 16th May, 1924, to the Wing Yick Company. The work progressed satisfactorily and the buildings were ready on 15th June, 1925, a month under the Contract time. 1925 Estimates, ...$162,000.00 Total Estimates, 1925 Sup. Vote, 43,000.00 $205,000.00 Expenditure to 31.12.25, 1925 Expenditure, $200,014.01 ...... .$251,250.00 $259,546.66 203. Cheung Chau School.-A scheme was prepared, but the work was not proceeded with during the year; consequently there was no expenditure under this heading. 1925 Estimates, 1925 Expenditure, $ 1,000.00 Nil. 204. Un Long School.-This work was not proceeded with during the year; consequently there was no expenditure under this heading. 1925 Estimates, 1925 Expenditure, $ 1,000.00 Nil. 205. Gardeners' Quarters, Sheung Shui.-It was not found possible to proceed with this work; consequently there was no expenditure under this heading. 1925 Estimates, 1925 Expenditure. $ 10,000.00 Nil. 206. Taipo School.-Sketch plans were prepared, but it was not found possible to proceed with this work; consequently there was no expenditure under this heading. 1925 Estimates, 1925 Expenditure, $ 20,000.00 Nil.
2026-05-07 10:55:33 · Baseline
View content

P.W.E. New Territories.

118-

201. Police Station, Kowloon City.-This work was referred to in paragraph 193 of last year's Report.

The Contract was let on 16th May, 1924, to Mr. Ng Wah. The work progressed satisfactorily, the buildings being completed on 16th June, 1925, a month under the Contract time.

.$162,000.00 Total Estimates, ...$251,250.00

40,000.00

1925 Estimates,

1925 Sup. Vote,

$202,000.00

1925 Expenditure, $201,335.41 Expenditure to

31.12.25,

......

$260,811.64

202. Police Station, Shamshuipo.-This work was referred to in paragraph 192 of last year's Report.

The Contract was let on 16th May, 1924, to the Wing Yick Company. The work progressed satisfactorily and the buildings were ready on 15th June, 1925, a month under the Contract time.

1925 Estimates, ...$162,000.00 Total Estimates, 1925 Sup. Vote,

43,000.00

$205,000.00 Expenditure to

31.12.25,

1925 Expenditure, $200,014.01

......

.$251,250.00

$259,546.66

203. Cheung Chau School.-A scheme was prepared, but the work was not proceeded with during the year; consequently there was no expenditure under this heading.

1925 Estimates,

1925 Expenditure,

$ 1,000.00

Nil.

204. Un Long School.-This work was not proceeded with during the year; consequently there was no expenditure under this heading.

1925 Estimates,

1925 Expenditure,

$ 1,000.00 Nil.

205. Gardeners' Quarters, Sheung Shui.-It was not found possible to proceed with this work; consequently there was no expenditure under this heading.

1925 Estimates,

1925 Expenditure.

$ 10,000.00

Nil.

206. Taipo School.-Sketch plans were prepared, but it was not found possible to proceed with this work; consequently there was no expenditure under this heading.

1925 Estimates, 1925 Expenditure,

$ 20,000.00 Nil.