P.W.E. Hong Kong.

Q 84

124. Training Nullahs:

(a) Conduit and Hatton Roads Development Scheme.—This work, referred to in paragraph 129 (a) of last year's Report, was continued.

1925 Estimates, $8,000.00 Total Estimates, $16,000.00

1925 Expenditure, $434.28 Expenditure to 31.12.25, $6,290.70

(b) Wongneichong Nullah. The extension of this nullah in the direction of Blue Pool was commenced about the middle of the year and good progress was made. The widening and reconstruction of the existing nullah between the race stand and Wongneichong was also commenced.

1925 Estimates, $50,000.00 Total Estimates, ...

1925 Expenditure, $19,442.94 Expenditure to 31.12.25, $19,442.94

(c) General Work.—Owing to the difficulty of obtaining satisfactory tenders, only a small amount of training work was done during the year. The following are the more important stream courses dealt with:

Locality STREAM COURSES
Position of stream course Length Re-trained marks Barker Road North of R.B.L. 150 283' 0" Completed. Stubbs Road. Between ILs. 2365 and 2354, South of Stubbs Road (above road) 648' 0" – Pokfulam Road. South-east of R.B. L. 203, Pokfulam Road 184' 0" .. Whitfield Bowen Road In roadway N. of I L. 2301 ** Barker Road Diversion and Training stream course South of L.L. 2365... 370' 3" North-east of R.B.L. 121. 279' 0" 15 Chatham Path South of R.B Ls. 228 and 229 306' 0" 11 Pokfulam Road.... West of I.L. 2378 165' 0" Lugard Road East of R.B.Ls. 152 & 197 483' 0" West of K.B.L. 191 302' 0" " Severn Road East of I.L. 2383 118' 0" Stubbs Road. Between 1.Ls 2465 & 2476 Not Com- do. pleted. 19

Edit History

2026-05-07 10:51:19 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
P.W.E. Hong Kong. Q 84 124. Training Nullahs: (a) Conduit and Hatton Roads Development Scheme.—This work, referred to in paragraph 129 (a) of last year's Report, was continued. 1925 Estimates, $8,000.00 Total Estimates, $16,000.00 1925 Expenditure, $434.28 Expenditure to 31.12.25, $6,290.70 (b) Wongneichong Nullah. The extension of this nullah in the direction of Blue Pool was commenced about the middle of the year and good progress was made. The widening and reconstruction of the existing nullah between the race stand and Wongneichong was also commenced. 1925 Estimates, $50,000.00 Total Estimates, ... 1925 Expenditure, $19,442.94 Expenditure to 31.12.25, $19,442.94 (c) General Work.—Owing to the difficulty of obtaining satisfactory tenders, only a small amount of training work was done during the year. The following are the more important stream courses dealt with: Locality STREAM COURSESPosition of stream course Length Re-trained marks Barker Road North of R.B.L. 150 283' 0" Completed. Stubbs Road. Between ILs. 2365 and 2354, South of Stubbs Road (above road) 648' 0" Pokfulam Road. South-east of R.B. L. 203, Pokfulam Road 184' 0" .. Whitfield Bowen Road In roadway N. of I L. 2301 ** Barker Road Diversion and Training stream course South of L.L. 2365... 370' 3" North-east of R.B.L. 121. 279' 0" 15 Chatham Path South of R.B Ls. 228 and 229 306' 0" 11 Pokfulam Road.... West of I.L. 2378 165' 0" Lugard Road East of R.B.Ls. 152 & 197 483' 0" West of K.B.L. 191 302' 0" " Severn Road East of I.L. 2383 118' 0" Stubbs Road. Between 1.Ls 2465 & 2476 Not Com- do. pleted. 19
Baseline (Original)
P.W.E. Hong Kong. Q 84 124. Training Nullahs: (a.) Conduit and Hatton Roads Development Scheme.—This work, referred to in paragraph 129 (a) of last year's Report, was continued. 1925 Estimates, $8,000.00 Total Estimates, 1925 Expenditure, $ 434.28 Expenditure to 31.12.25, $16,000.00 $ 6,290.70 (b). Wongneichong Nullah. The extension of this nullah in the direction of Blue Pool was commenced about the middle of the year and good progress was made. The widening and reconstruction of the existing nullah between the race stand and Wongneichong was also commenced. 1925 Estimates, 1925 Expenditure, $50,000.00 Total Estimates, $19,442.94 Expenditure to 31.12.25, .... Nil. $19,442.94 (c). General Work.-Owing to the difficulty of obtaining satisfactory tenders, only a small amount of training work was done during the year. The following are the more important stream courses dealt with: Locality. STREAM COURSES. Position of stream course. Length Re- trained marks Barker Road North of R.B.L. 150 Stubbs Road. Pokfulam Road. Whitfield Bowen Road Barker Road do. Between ILs. 2365 and 2354, South of Stubbs Road (above road) South-east of R.B. L. 203, Pokfulam Road In roadway N. of I L. 2301 Diversion and Training stream course South of L.L. 2365... Com- 283' 0"pleted. 648' 0" 184′ 0′′ .. ** 370' 3" North-east of R.B.L. 121. 279′0′′ 15 306'0" 11 Chatham Path South of R.B Ls. 228 and 229 165'0′′ Pokfulam Road.... West of I.L. 2378 483' 0" Lugard Road East of R.B.Ls. 152 & 197 302' 0" " Severn Road West of K.B.L. 191 118' 0" Stubbs Road. East of I.L. 2383 Not Com- do. Between 1.Ls 2465 & 2476 pleted. 19 +
2026-05-07 10:51:19 · Baseline
View content

P.W.E. Hong Kong.

Q 84

124. Training Nullahs:

(a.) Conduit and Hatton Roads Development Scheme.—This work, referred to in paragraph 129 (a) of last year's Report, was continued.

1925 Estimates,

$8,000.00 Total Estimates,

1925 Expenditure, $ 434.28

Expenditure to 31.12.25,

$16,000.00

$ 6,290.70

(b). Wongneichong Nullah. The extension of this nullah in the direction of Blue Pool was commenced about the middle of the year and good progress was made. The widening and reconstruction of the existing nullah between the race stand and Wongneichong was also commenced.

1925 Estimates, 1925 Expenditure,

$50,000.00 Total Estimates, $19,442.94 Expenditure to

31.12.25,

....

Nil.

$19,442.94

(c). General Work.-Owing to the difficulty of obtaining satisfactory tenders, only a small amount of training work was done during the year. The following are the more important stream courses dealt with:

Locality.

STREAM COURSES.

Position of

stream course.

Length Re- trained marks

Barker Road

North of R.B.L. 150

Stubbs Road.

Pokfulam Road.

Whitfield Bowen Road

Barker Road

do.

Between ILs. 2365 and 2354, South of Stubbs Road (above road) South-east of R.B. L. 203,

Pokfulam Road In roadway N. of I L. 2301 Diversion and Training stream course South of L.L. 2365...

Com-

283' 0"pleted.

648' 0" – 184′ 0′′

..

**

370' 3"

North-east of R.B.L. 121.

279′0′′

15

306'0"

11

Chatham Path

South of R.B Ls. 228 and

229

165'0′′

Pokfulam Road....

West of I.L. 2378

483' 0"

Lugard Road

East of R.B.Ls. 152 & 197

302' 0"

"

Severn Road

West of K.B.L. 191

118' 0"

Stubbs Road.

East of I.L. 2383

Not Com-

do.

Between 1.Ls 2465 & 2476

pleted.