P.W.E. Hong Kong.
Q 84
124. Training Nullahs:
(a) Conduit and Hatton Roads Development Scheme.—This work, referred to in paragraph 129 (a) of last year's Report, was continued.
1925 Estimates, $8,000.00 Total Estimates, $16,000.00
1925 Expenditure, $434.28 Expenditure to 31.12.25, $6,290.70
(b) Wongneichong Nullah. The extension of this nullah in the direction of Blue Pool was commenced about the middle of the year and good progress was made. The widening and reconstruction of the existing nullah between the race stand and Wongneichong was also commenced.
1925 Estimates, $50,000.00 Total Estimates, ...
1925 Expenditure, $19,442.94 Expenditure to 31.12.25, $19,442.94
(c) General Work.—Owing to the difficulty of obtaining satisfactory tenders, only a small amount of training work was done during the year. The following are the more important stream courses dealt with:
Locality STREAM COURSESPosition of stream course Length Re-trained marks Barker Road North of R.B.L. 150 283' 0" Completed. Stubbs Road. Between ILs. 2365 and 2354, South of Stubbs Road (above road) 648' 0" – Pokfulam Road. South-east of R.B. L. 203, Pokfulam Road 184' 0" .. Whitfield Bowen Road In roadway N. of I L. 2301 ** Barker Road Diversion and Training stream course South of L.L. 2365... 370' 3" North-east of R.B.L. 121. 279' 0" 15 Chatham Path South of R.B Ls. 228 and 229 306' 0" 11 Pokfulam Road.... West of I.L. 2378 165' 0" Lugard Road East of R.B.Ls. 152 & 197 483' 0" West of K.B.L. 191 302' 0" " Severn Road East of I.L. 2383 118' 0" Stubbs Road. Between 1.Ls 2465 & 2476 Not Com- do. pleted. 19