P.W.E. Hong Kong.

Sketch schemes, therefore, were prepared to place one storey hutments on the site to accommodate 18 families.

After the collapse of the retaining wall South of In Mi Lane which is in the near vicinity, it was decided not to use this site in its present form.

No work was, therefore, undertaken during the year and consequently there was no expenditure under this heading.

1925 Estimates, $30,000.00

1925 Expenditure, Nil.

122. Public Latrines, Urinals and Bath-houses.-Contracts for the undermentioned public conveniences were let as follows:-

(a.) Underground Trough Closet and Bath-house at the junction of Second and Western Streets, Sept. 1923. (b.) Cross Lane Bath-house, Nov. 1923. (c.) Whitfield Trough Closet, Dec. 1923. (d.) Sai Wan Ho Trough Closet, July 1924.

All the above conveniences were described in paragraph 111 of the Report for last year.

(a.) was completed in November, 1925. (b.) (c.) do. March, 1925. (d.)

1925 Estimates, $25,000.00

1925 Sup. Vote, $16,000.00

Total Estimates, $41,000.00

1925 Expenditure, $40,983.80

Expenditure to 31.12.25, $101,949.84

123. Roads:

(a). Improving & widening road through Quarry Bay Village. -This was referred to in paragraph 124 (a) of last year's Report.

The Contract for this work was let, and the work started towards the end of the year. Satisfactory progress was made.

1925 Estimates, $50,000.00

1925 Expenditure, $49,777.68

(b.) Road contouring the hillside in Wongneichong and Tai Hung Valleys, Extension. 2nd Section-Bowen Road to connect with Tai Hang proposed Road.—This work was referred to in paragraphs 120 (e) of the Report for 1923 and 124 (e) of last year's Report.

Edit History

2026-05-07 10:50:20 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
Q 77 P.W.E. Hong Kong. Sketch schemes, therefore, were prepared to place one storey hutments on the site to accommodate 18 families. After the collapse of the retaining wall South of In Mi Lane which is in the near vicinity, it was decided not to use this site in its present form. No work was, therefore, undertaken during the year and consequently there was no expenditure under this heading. 1925 Estimates, $30,000.00 1925 Expenditure, Nil. 122. Public Latrines, Urinals and Bath-houses.-Contracts for the undermentioned public conveniences were let as follows:- (a.) Underground Trough Closet and Bath-house at the junction of Second and Western Streets, Sept. 1923. (b.) Cross Lane Bath-house, Nov. 1923. (c.) Whitfield Trough Closet, Dec. 1923. (d.) Sai Wan Ho Trough Closet, July 1924. All the above conveniences were described in paragraph 111 of the Report for last year. (a.) was completed in November, 1925. (b.) (c.) do. March, 1925. (d.) 1925 Estimates, $25,000.00 1925 Sup. Vote, $16,000.00 Total Estimates, $41,000.00 1925 Expenditure, $40,983.80 Expenditure to 31.12.25, $101,949.84 123. Roads: (a). Improving & widening road through Quarry Bay Village. -This was referred to in paragraph 124 (a) of last year's Report. The Contract for this work was let, and the work started towards the end of the year. Satisfactory progress was made. 1925 Estimates, $50,000.00 1925 Expenditure, $49,777.68 (b.) Road contouring the hillside in Wongneichong and Tai Hung Valleys, Extension. 2nd Section-Bowen Road to connect with Tai Hang proposed Road.—This work was referred to in paragraphs 120 (e) of the Report for 1923 and 124 (e) of last year's Report.
Baseline (Original)
Q 77 P.W.E. Hong Kong. Sketch schemes, therefore, were prepared to place one storey hutments on the site to accommodate 18 families. After the collapse of the retaining wall South of In Mi Lane which is in the near vicinity, it was decided not to use this site in its present form. No work was, therefore, undertaken during the year and con- sequently there was no expenditure under this heading. 1925 Estimates, 1925 Expenditure, $ 30,000.00 Nil. 122. Public Latrines, Urinals and Bath-houses.-Contracts for the undermentioned public conveniences were let as follows:- (a.) Underground Trough Closet and Bath-house at the junction of Second and Western Streets, (b.) Cross Lane Bath-house, (c.) Whitfield Trough Closet, (d.) Sai Wan Ho Trough Closet, ... Sept. 1923. Nov. 1923. Dec. 1923. July 1924. All the above conveniences were described in paragraph 111 of the Report for last year. (a.) was completed in November, 1925. (b.) (c.) do. March, 1925. (d.)) 1925 Estimates, 1925 Sup. Vote, $ 25,000,00 Total Estimates, 16,000.00 $ $ 41,000.00 1925 Expenditure, $ 40,983.80 Expenditure to 31.12.25, $101,949.84 123. Roads :--- · (a). Improving & widening road through Quarry Bay Village. -This was referred to in paragraph 124 (a) of last year's Report. The Contract for this work was let, and the work started towards the end of the year. Satisfactory progress was made. 1925 Estimates, 1925 Expenditure, $50,000.00 49,777.68 (b.) Road contouring the hillside in Wongneichong and Tai Hung Valleys, Extension. 2nd Section-Bowen Road to con- nect with Tai Hang proposed Road.—This work was referred to in paragraphs 120 (e) of the Report for 1923 and 124 (e) of last year's Report.
2026-05-07 10:50:20 · Baseline
View content

Q 77

P.W.E. Hong Kong.

Sketch schemes, therefore, were prepared to place one storey hutments on the site to accommodate 18 families.

After the collapse of the retaining wall South of In Mi Lane which is in the near vicinity, it was decided not to use this site in its present form.

No work was, therefore, undertaken during the year and con- sequently there was no expenditure under this heading.

1925 Estimates,

1925 Expenditure,

$ 30,000.00

Nil.

122. Public Latrines, Urinals and Bath-houses.-Contracts for the undermentioned public conveniences were let as follows:-

(a.) Underground Trough Closet and Bath-house at the

junction of Second and Western Streets,

(b.) Cross Lane Bath-house,

(c.) Whitfield Trough Closet,

(d.) Sai Wan Ho Trough Closet,

...

Sept. 1923. Nov. 1923. Dec. 1923.

July 1924.

All the above conveniences were described in paragraph 111

of the Report for last year.

(a.) was completed in November, 1925.

(b.)

(c.)

do.

March, 1925.

(d.))

1925 Estimates,

1925 Sup. Vote,

$ 25,000,00 Total Estimates,

16,000.00

$

$ 41,000.00 1925 Expenditure, $ 40,983.80

Expenditure to

31.12.25,

$101,949.84

123. Roads :---

·

(a). Improving & widening road through Quarry Bay Village. -This was referred to in paragraph 124 (a) of last year's Report.

The Contract for this work was let, and the work started towards the end of the year. Satisfactory progress was made.

1925 Estimates,

1925 Expenditure,

$50,000.00 49,777.68

(b.) Road contouring the hillside in Wongneichong and Tai Hung Valleys, Extension. 2nd Section-Bowen Road to con- nect with Tai Hang proposed Road.—This work was referred to in paragraphs 120 (e) of the Report for 1923 and 124 (e) of last year's Report.