P.W.E. Hong Kong.

Satisfactory progress was maintained until labour conditions became unsettled during the Summer months which adversely affected the work. Every endeavour was subsequently made to accelerate its completion and it is anticipated that the building itself will be finished within a few weeks of the Contract date in 1926.

By the end of the year, the whole of the brickwork has been completed, with the exception of a portion of the tower. The special plaster work and ceiling to Assembly Hall was in hand. Tiling to verandah floors and classroom walls has been completed. Doors, windows and metal casements were being hung, and grates and mantels fixed. Drawings for the various special fittings and furniture were prepared.

A few alterations and additions have been made to the original design, notably the provision of tile dados to all Classroom walls, and a granite Portico to the Main Entrance.

1925 Estimates, $300,000.00 Total Estimates, $555,000.00

1925 Expenditure, $277,544.88 Expenditure to 31.12.25, $480,759.09

103. New Queen's College, Site formation at Caroline Hill. This work was referred to in paragraph 108 of last year's Report.

The formation of the road encircling the site was completed and almost the whole was surfaced with macadam.

The slopes to the different formation levels were turfed, and the area at 50.00 A.O.D. was placed at the disposal of the Navy for recreation purposes. A revised sketch scheme was prepared for the buildings.

1925 Estimates, $30,000.00 Total Estimates, $1,000,000.00

1925 Sup. Vote, $6,000.00 $36,000.00

Expenditure to 31.12.25, $169,961.45

1925 Expenditure, $34,502.34

104. Extension to Lairage and Coolie Quarters, Kennedy Town. This work was referred to in paragraph 104 of last year's Report.

It was not found possible to proceed with the work during the year; there was consequently no expenditure under this heading.

1925 Estimates, $5,000.00 1925 Expenditure, $Nil

Total Estimates, $5,000.00 Expenditure to 31.12.25, $0.60

Edit History

2026-05-07 10:49:41 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
Q 71 P.W.E. Hong Kong. Satisfactory progress was maintained until labour conditions became unsettled during the Summer months which adversely affected the work. Every endeavour was subsequently made to accelerate its completion and it is anticipated that the building itself will be finished within a few weeks of the Contract date in 1926. By the end of the year, the whole of the brickwork has been completed, with the exception of a portion of the tower. The special plaster work and ceiling to Assembly Hall was in hand. Tiling to verandah floors and classroom walls has been completed. Doors, windows and metal casements were being hung, and grates and mantels fixed. Drawings for the various special fittings and furniture were prepared. A few alterations and additions have been made to the original design, notably the provision of tile dados to all Classroom walls, and a granite Portico to the Main Entrance. 1925 Estimates, $300,000.00 Total Estimates, $555,000.00 1925 Expenditure, $277,544.88 Expenditure to 31.12.25, $480,759.09 103. New Queen's College, Site formation at Caroline Hill. This work was referred to in paragraph 108 of last year's Report. The formation of the road encircling the site was completed and almost the whole was surfaced with macadam. The slopes to the different formation levels were turfed, and the area at 50.00 A.O.D. was placed at the disposal of the Navy for recreation purposes. A revised sketch scheme was prepared for the buildings. 1925 Estimates, $30,000.00 Total Estimates, $1,000,000.00 1925 Sup. Vote, $6,000.00 $36,000.00 Expenditure to 31.12.25, $169,961.45 1925 Expenditure, $34,502.34 104. Extension to Lairage and Coolie Quarters, Kennedy Town. This work was referred to in paragraph 104 of last year's Report. It was not found possible to proceed with the work during the year; there was consequently no expenditure under this heading. 1925 Estimates, $5,000.00 1925 Expenditure, $Nil Total Estimates, $5,000.00 Expenditure to 31.12.25, $0.60
Baseline (Original)
Q 71 P.W.E. Hong Kong. Satisfactory progress was maintained until labour conditions became unsettled during the Summer months which adversely affected the work. Every endeavour was subsequently made to accelerate its completion and it is anticipated that the building itself will be finished within a few weeks of the Contract date in 1926. By the end of the year, the whole of the brickwork has been completed, with the exception of a portion of the tower. The special plaster work and ceiling to Assembly Hall was in hand. Tiling to verandah floors and classroom walls has been com- pleted. Doors, windows and metal casements were being hung, and grates and mantels fixed. Drawings for the various special fittings and furniture were prepared. A few alterations and additions have been made to the original design, notably the provision of tile dados to all Class- room walls, and a granite Portico to the Main Entrance. 1925 Estimates, $300,000.00 Total Estimates, ..$555,000.00 1925 Expenditure, $277,544.88 Expenditure to 31.12.25, $480,759.09 103. New Queen's College,-Site formation at Caroline Hill. This work was referred to in paragraph 108 of last year's Report. The formation of the road encircling the site was completed and almost the whole was surfaced with macadam. The slopes to the different formation levels were turfed, and the area at 50.00 A.O.D. was placed at the disposal of the Navy for recreation purposes. A revised sketch scheme was prepared for the buildings. 1925 Estimates, ...$ 30,000.00 Total Estimates, $1,000,000.00 1925 Sup. Vote, 6,000.00 $ 36,000.00 Expenditure to 31.12.25, $169,961.45 1925 Expenditure, $ 34,502.34 104. Extension to Lairage and Coolie Quarters, Kennedy Town. This work was referred to in paragraph 104 of last year's Report. It was not found possible to proceed with the work during. the year; there was consequently no expenditure under this heading. 1925 Estimates, ...$ 5,000.00 1925 Expenditure, $ Total Estimates, Expenditure to 81.12.25, ........ $ 5.60
2026-05-07 10:49:41 · Baseline
View content

Q 71

P.W.E. Hong Kong.

Satisfactory progress was maintained until labour conditions became unsettled during the Summer months which adversely affected the work. Every endeavour was subsequently made to accelerate its completion and it is anticipated that the building itself will be finished within a few weeks of the Contract date in 1926.

By the end of the year, the whole of the brickwork has been completed, with the exception of a portion of the tower. The special plaster work and ceiling to Assembly Hall was in hand. Tiling to verandah floors and classroom walls has been com- pleted. Doors, windows and metal casements were being hung, and grates and mantels fixed. Drawings for the various special fittings and furniture were prepared.

A few alterations and additions have been made to the original design, notably the provision of tile dados to all Class- room walls, and a granite Portico to the Main Entrance.

1925 Estimates,

$300,000.00 Total Estimates, ..$555,000.00

1925 Expenditure, $277,544.88 Expenditure to

31.12.25,

$480,759.09

103. New Queen's College,-Site formation at Caroline Hill. This work was referred to in paragraph 108 of last year's Report.

The formation of the road encircling the site was completed and almost the whole was surfaced with macadam.

The slopes to the different formation levels were turfed, and the area at 50.00 A.O.D. was placed at the disposal of the Navy for recreation purposes. A revised sketch scheme was prepared for the buildings.

1925 Estimates, ...$ 30,000.00 Total Estimates, $1,000,000.00 1925 Sup. Vote,

6,000.00

$ 36,000.00

Expenditure to

31.12.25,

$169,961.45

1925 Expenditure, $ 34,502.34

104. Extension to Lairage and Coolie Quarters, Kennedy Town. This work was referred to in paragraph 104 of last year's Report.

It was not found possible to proceed with the work during. the year; there was consequently no expenditure under this heading.

1925 Estimates, ...$ 5,000.00 1925 Expenditure, $

Total Estimates, Expenditure to

81.12.25, ........

$

5.60