AnnualReport-1924 — Page 697

Administrative Reports 行政報告書 All AI Reviewed

Works not appearing in Estimate,-Hongkong.

148

in the Peak District, a retaining wall was erected, and nullahs culverted, in the Valley at Wanchai Gap, between Mount Cameron and Coombe Roads.

1924 Estimates,
1924 Expenditure,

$ 5,000.00
$ 4,964.64

224. Reconstruction of Recreation Grounds at Happy Valley. New turf was laid to those portions of the Civil Service Club ground damaged by the debris washed down from the adjoining hillside during the storms of the previous year.

1924 Estimates,
1924 Expenditure,

$ 2,500.00
$ 1,078.17

225. Conduit Road Widening. This work, referred to in paragraph 120 (s) (ii) of last year's Report, was practically completed by the end of the year.

1924 Estimates,
1924 Expenditure,

$45,000.00
$44,844.05

226. Alterations to Tramway Track between Ice House Street and Causeway Bay. That portion of the track near Jardine Bazaar was raised to the approved level.

1924 Estimates,
1924 Expenditure,

$ 7,890.00
$ 7,171.79

227. Road connecting Broadwood Road with Wongneichong Gap Road.--This work, referred to in paragraph 120 (m) of last year's Report, was completed during the year.

1924 Estimates,
1924 Expenditure,

$15,000.00
$15,360.71

228. Shaukiwan Road widening near the Eastern Gate of the Taikoo Dock. It was considered necessary to widen the road to 80 feet at a dangerous bend near the Eastern Gate of the Taikoo Dock, and the work was well in hand at the end of the year.

1924 Estimates,
1924 Expenditure,

$40,000.00
$28,659.12

229. Shek O Road, Surfacing.-A short section of this road was strengthened by the application of 4" tar macadam.

1924 Estimates,
1924 Expenditure,

$25,000.00
$ 3,954.50

Edit History

2026-05-07 08:12:28 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
Works not appearing in Estimate,-Hongkong. 148 in the Peak District, a retaining wall was erected, and nullahs culverted, in the Valley at Wanchai Gap, between Mount Cameron and Coombe Roads. 1924 Estimates, 1924 Expenditure, $ 5,000.00 $ 4,964.64 224. Reconstruction of Recreation Grounds at Happy Valley. New turf was laid to those portions of the Civil Service Club ground damaged by the debris washed down from the adjoining hillside during the storms of the previous year. 1924 Estimates, 1924 Expenditure, $ 2,500.00 $ 1,078.17 225. Conduit Road Widening. This work, referred to in paragraph 120 (s) (ii) of last year's Report, was practically completed by the end of the year. 1924 Estimates, 1924 Expenditure, $45,000.00 $44,844.05 226. Alterations to Tramway Track between Ice House Street and Causeway Bay. That portion of the track near Jardine Bazaar was raised to the approved level. 1924 Estimates, 1924 Expenditure, $ 7,890.00 $ 7,171.79 227. Road connecting Broadwood Road with Wongneichong Gap Road.--This work, referred to in paragraph 120 (m) of last year's Report, was completed during the year. 1924 Estimates, 1924 Expenditure, $15,000.00 $15,360.71 228. Shaukiwan Road widening near the Eastern Gate of the Taikoo Dock. It was considered necessary to widen the road to 80 feet at a dangerous bend near the Eastern Gate of the Taikoo Dock, and the work was well in hand at the end of the year. 1924 Estimates, 1924 Expenditure, $40,000.00 $28,659.12 229. Shek O Road, Surfacing.-A short section of this road was strengthened by the application of 4" tar macadam. 1924 Estimates, 1924 Expenditure, $25,000.00 $ 3,954.50
Baseline (Original)
Works not appearing in Estimate,-Hongkong. 148 in the Peak District, a retaining wall was erected, and nullahs culverted, in the Valley at Wanchai Gap, between Mount Cameron and Coombe Roads. 1924 Estimates, 1924 Expenditure, $ 5,000.00 $ 4,964.64 224. Reconstruction of Recreation Grounds at Happy Valley. New turf was laid to those portions of the Civil Service Club ground damaged by the debris washed down from the adjoining hillside during the storms of the previous year. 1924 Estimates, 1924 Expenditure, $ 2,500.00 $ 1,078.17 225. Conduit Road Widening. This work, referred to in paragraph 120 (s). (ii) of last year's Report, was practically com- pleted by the end of the year. 1924 Estimates, 1924 Expenditure, $45,000.00 $44,844.05 226. Alterations to Tramway Track between Ice House Street and Causeway Bay. That portion of the track near Jardine Bazaar was raised to the approved level. 1924 Estimates, 1924 Expenditure, $ 7,890.00 .$ 7,171.79 227. Road connecting Broadwood_Road_with_Wongneichong Gap Road.--This work, referred to in paragraph 120 (m) of last year's Report, was completed during the year. 1924 Estimates, 1924 Expenditure, $15,000.00 $15,360.71 228. Shaukiwan Road widening near the Eastern Gate of the Taikoo Dock. It was considered necessary to widen the road to 80 feet at a dangerous bend near the Eastern Gate of the Taikoo Dock, and the work was well in hand at the end of the year. 1924 Estimates, 1924 Expenditure, $40,000.00 $28,659.12 229. Shek O Road, Surfacing.-A short section of this road was strengthened by the application of 4" tar macadam. 1924 Estimates, 1924 Expenditure, $25,000.00 $ 3,954.50
2026-05-07 08:12:28 · Baseline
View content

Works not appearing in Estimate,-Hongkong.

148

in the Peak District, a retaining wall was erected, and nullahs culverted, in the Valley at Wanchai Gap, between Mount Cameron and Coombe Roads.

1924 Estimates,

1924 Expenditure,

$ 5,000.00

$ 4,964.64

224. Reconstruction of Recreation Grounds at Happy Valley. New turf was laid to those portions of the Civil Service Club ground damaged by the debris washed down from the adjoining hillside during the storms of the previous year.

1924 Estimates,

1924 Expenditure,

$ 2,500.00

$ 1,078.17

225. Conduit Road Widening. This work, referred to in paragraph 120 (s). (ii) of last year's Report, was practically com- pleted by the end of the year.

1924 Estimates,

1924 Expenditure,

$45,000.00

$44,844.05

226. Alterations to Tramway Track between Ice House Street and Causeway Bay. That portion of the track near Jardine Bazaar was raised to the approved level.

1924 Estimates,

1924 Expenditure,

$ 7,890.00 .$ 7,171.79

227. Road connecting Broadwood_Road_with_Wongneichong Gap Road.--This work, referred to in paragraph 120 (m) of last year's Report, was completed during the year.

1924 Estimates,

1924 Expenditure,

$15,000.00 $15,360.71

228. Shaukiwan Road widening near the Eastern Gate of the Taikoo Dock. It was considered necessary to widen the road to 80 feet at a dangerous bend near the Eastern Gate of the Taikoo Dock, and the work was well in hand at the end of the year.

1924 Estimates,

1924 Expenditure,

$40,000.00 $28,659.12

229. Shek O Road, Surfacing.-A short section of this road was strengthened by the application of 4" tar macadam.

1924 Estimates, 1924 Expenditure,

$25,000.00 $ 3,954.50

Comments

Approved members can add comments, bookmarks, and private notes.

No comments yet.

Private Research Note

Private notes are available after approval.