The foundations of the Twin Storm-water Culverts for a distance of 110 lin. feet from the existing Praya wall towards the new seawall were completed during the year, also, a length of 200 feet of storm-water Culvert as an extension to the Culvert in Wanchai Road.

A total quantity of about 44,000 cubic feet of granite ashlar facing for the sea-wall and some 27,500 cubic feet of granite sets have been prepared at the quarry at Cheungshawan; and 2,100 cubic yards in cement concrete blocks for the foundations of the quay and seawall have been moulded at the blockyard at Wanchai.

Owing to the approach of the excavations at Morrison Hill, it was found necessary to remove houses Nos. 5 and 6. This work was commenced at the end of the year by Messrs. Sang Lee & Co., who purchased the material to be obtained by pulling down these houses.

1923 Estimates,.....$71,000.00 Total Revised 1923 Sup. Vote, 26,000.00

Estimates,

$97,000.00 Expenditure to 1923 Expenditure,..$96,069.00 | 31.12.23,

.$640,460.00

$192,138.00

(b.) Road Improvements at Arsenal Street,—Resumption and alteration of buildings.—This item was referred to in paragraph 141 (b) of last year's Report. The necessary resumption has not been effected at the end of the year. No expenditure was incurred during the year.

(c.) Road Improvements at East Point.-This work was referred to in paragraph 141 (c) of last year's Report.

The work under this Contract was completed in March, with the exception of the reconstruction of the boundary wall on the South side of M.L. 52. This latter work was not completed at the end of the year as the Hongkong Tramway Co.'s track encroaches on the new alignment of the boundary wall and arrangements were being made for the removal of the track. 1923 Estimates, .. ..$30,000.00 | Total Estimates,.....$40,000.00

Expenditure to

31.12.23,

1923 Expenditure,..$16,139.85

.....

$27,227.85

(d.) Morrison Hill District Development, Retaining Walls and Storm-water Culverts.-The construction was completed of a length of retaining wall to support the North side of Gap Road from near the Monument and extending westwards to a distance of about 260 lin. feet.

The work of re-drainage of the existing developed area between Arsenal Street, Causeway Bay, Queen's Road and the existing Praya, rendered necessary by the scheme, was continued during the year.

Edit History

2026-05-07 05:43:17 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
Q 101 P.W.E. Hongkong. The foundations of the Twin Storm-water Culverts for a distance of 110 lin. feet from the existing Praya wall towards the new seawall were completed during the year, also, a length of 200 feet of storm-water Culvert as an extension to the Culvert in Wanchai Road. A total quantity of about 44,000 cubic feet of granite ashlar facing for the sea-wall and some 27,500 cubic feet of granite sets have been prepared at the quarry at Cheungshawan; and 2,100 cubic yards in cement concrete blocks for the foundations of the quay and seawall have been moulded at the blockyard at Wanchai. Owing to the approach of the excavations at Morrison Hill, it was found necessary to remove houses Nos. 5 and 6. This work was commenced at the end of the year by Messrs. Sang Lee & Co., who purchased the material to be obtained by pulling down these houses. 1923 Estimates,.....$71,000.00 Total Revised 1923 Sup. Vote, 26,000.00 Estimates, $97,000.00 Expenditure to 1923 Expenditure,..$96,069.00 | 31.12.23, .$640,460.00 $192,138.00 (b.) Road Improvements at Arsenal Street,—Resumption and alteration of buildings.—This item was referred to in paragraph 141 (b) of last year's Report. The necessary resumption has not been effected at the end of the year. No expenditure was incurred during the year. (c.) Road Improvements at East Point.-This work was referred to in paragraph 141 (c) of last year's Report. The work under this Contract was completed in March, with the exception of the reconstruction of the boundary wall on the South side of M.L. 52. This latter work was not completed at the end of the year as the Hongkong Tramway Co.'s track encroaches on the new alignment of the boundary wall and arrangements were being made for the removal of the track. 1923 Estimates, .. ..$30,000.00 | Total Estimates,.....$40,000.00 Expenditure to 31.12.23, 1923 Expenditure,..$16,139.85 ..... $27,227.85 (d.) Morrison Hill District Development, Retaining Walls and Storm-water Culverts.-The construction was completed of a length of retaining wall to support the North side of Gap Road from near the Monument and extending westwards to a distance of about 260 lin. feet. The work of re-drainage of the existing developed area between Arsenal Street, Causeway Bay, Queen's Road and the existing Praya, rendered necessary by the scheme, was continued during the year.
Baseline (Original)
Q 101 P.W.E. Hongkong. The foundations of the Twin Storm-water Culverts for a distance of 110 liu. feet from the existing Praya wall towards the new seawall were completed during the year, also, a length of 200 feet of storm-water Culvert as an extension to the Culvert in Wanchai Road. A total quantity of about 44,000 cubic feet of granite ashlar facing for the sea-wall and some 27,500 cubic feet of granite sets have been prepared at the quarry at Cheungshawan; and 2,100 cubic yards in cement concrete blocks for the foundations of the quay and seawall have been moulded at the blockyard at Wanchai. Owing to the approach of the excavations at Morrison Hill, it was found necessary to remove houses Nos. 5 and 6. This work was commenced at the end of the year by Messrs. Sang Lee & Co.. who purchased the material to be obtained by pulling down these houses. 1923 Estimates,.....$ 71,000.00 Total Revised 1923 Sup. Vote, 26,000.00 Estimates, $ 97,000.00 Expenditure to 1923 Expenditure,..$ 96,069.00 | 31.12.23, .$640,460.00 $192,138.00 (b.) Road Improvements at Arsenal Street,—Resumption and alteration of buildings.—This item was referred to in paragraph 141 (b) of last year's Report. The necessary resumption has not been effected at the end of the year. No expenditure was incurred during the year. (c.) Road Improvements at East Point.-This work was referred to in paragraph 141 (c) of last year's Report. The work under this Contract was completed in March, with the exception of the reconstruction of the boundary wall on the South side of M.L. 52. This latter work was not completed at the end of the year as the Hongkong Tramway Co.'s track encroaches on the new alignment of the boundary wall and arrangements were being made for the removal of the track. 1923 Estimates, .. ..$ 30,000.00 | Total Estimates,.....$ 40,000.00 Expenditure to 31.12.23, 1923 Expenditure,..$ 16,139.85 ..... $ 27,227.85 (d.) Morrison Hill District Development, Retaining Walls and Storm-water Culverts.-The construction was completed of a length of retaining wall to support the North side of Gap Road from near the Monument and extending westwards to a distance of about 260 lin. feet. The work of re-drainage of the existing developed area · between Arsenal Street, Causeway Bay, Queen's Road and the existing Praya, rendered necessary by the scheme, was continued during the year.
2026-05-07 05:43:17 · Baseline
View content

Q 101

P.W.E. Hongkong.

The foundations of the Twin Storm-water Culverts for a distance of 110 liu. feet from the existing Praya wall towards the new seawall were completed during the year, also, a length of 200 feet of storm-water Culvert as an extension to the Culvert in Wanchai Road.

A total quantity of about 44,000 cubic feet of granite ashlar facing for the sea-wall and some 27,500 cubic feet of granite sets have been prepared at the quarry at Cheungshawan; and 2,100 cubic yards in cement concrete blocks for the foundations of the quay and seawall have been moulded at the blockyard at Wanchai.

Owing to the approach of the excavations at Morrison Hill, it was found necessary to remove houses Nos. 5 and 6. This work was commenced at the end of the year by Messrs. Sang Lee & Co.. who purchased the material to be obtained by pulling down these houses.

1923 Estimates,.....$ 71,000.00 Total Revised 1923 Sup. Vote, 26,000.00

Estimates,

$ 97,000.00 Expenditure to 1923 Expenditure,..$ 96,069.00 | 31.12.23,

.$640,460.00

$192,138.00

(b.) Road Improvements at Arsenal Street,—Resumption and alteration of buildings.—This item was referred to in paragraph 141 (b) of last year's Report. The necessary resumption has not been effected at the end of the year. No expenditure was incurred during the year.

(c.) Road Improvements at East Point.-This work was referred to in paragraph 141 (c) of last year's Report.

The work under this Contract was completed in March, with the exception of the reconstruction of the boundary wall on the South side of M.L. 52. This latter work was not completed at the end of the year as the Hongkong Tramway Co.'s track encroaches on the new alignment of the boundary wall and arrangements were being made for the removal of the track. 1923 Estimates, .. ..$ 30,000.00 | Total Estimates,.....$ 40,000.00

Expenditure to

31.12.23,

1923 Expenditure,..$ 16,139.85

.....

$ 27,227.85

(d.) Morrison Hill District Development, Retaining Walls and Storm-water Culverts.-The construction was completed of a length of retaining wall to support the North side of Gap Road from near the Monument and extending westwards to a distance of about 260 lin. feet.

The work of re-drainage of the existing developed area

· between Arsenal Street, Causeway Bay, Queen's Road and the existing Praya, rendered necessary by the scheme, was continued during the year.

Comments

Approved members can add comments, bookmarks, and private notes.

No comments yet.

Private Research Note

Private notes are available after approval.