P.W.E. Hongkong.

0 80

The re-building and setting back to the new line of several properties in this road was completed during the year, and a commencement made in several other cases. Particulars of the properties dealt with are given in the schedule on page 35. By delaying the resumption of the land required for road widening until re-building takes place, a considerable saving has been effected on this vote. There was no expenditure incurred in connection with the making good of the road surface on the widened portions.

1923 Estimates, $25,000.00 | Total Estimates, $95,000.00

1923 Expenditure, $3,459.75 | Expenditure to 31.12.23, $46,007.82

(g.) Road from Causeway Bay to North Point:- This work was referred to in paragraph 106 (9) of last year's Report.

Considering the heavy rock and Fort concrete cutting involved, fair progress was made during the year; all spoil was trucked and tipped for reclamation purposes along the North Point foreshore.

1923 Estimates, $100,000.00 | Total Estimates,

1923 Expenditure, $27,126.85 | Expenditure to 31.12.23, $27,231.90

(h.) Shaukiwan Road,— Improvements in Shaukiwan Village.-- This was referred to in paragraph 106 (h) of last year's Report. The work was not commenced owing to the resumptions of certain properties not being completed.

1923 Estimates, $30,000.00 | 1923 Expenditure,

(i.) Victoria Road Improvements.- The widening of this road to give a minimum width of 25′ 0″ and open out dangerous bends referred to in paragraph 106 (i) of last year's Report was continued throughout the year.

1923 Estimates, $25,000.00 | 1923 Sup. Vote, $5,000.00 | $30,000.00

1923 Expenditure, $28,409.51

(j.) Road from Western end of Robinson Road to Conduit Road.- Owing to the necessary resumptions not being completed, it was impossible to proceed with this work. There was consequently no expenditure under this heading.

1923 Estimates, $25,000.00 | 1923 Expenditure,

Edit History

2026-05-07 05:39:25 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
P.W.E. Hongkong. 0 80 The re-building and setting back to the new line of several properties in this road was completed during the year, and a commencement made in several other cases. Particulars of the properties dealt with are given in the schedule on page 35. By delaying the resumption of the land required for road widening until re-building takes place, a considerable saving has been effected on this vote. There was no expenditure incurred in connection with the making good of the road surface on the widened portions. 1923 Estimates, $25,000.00 | Total Estimates, $95,000.00 1923 Expenditure, $3,459.75 | Expenditure to 31.12.23, $46,007.82 (g.) Road from Causeway Bay to North Point:- This work was referred to in paragraph 106 (9) of last year's Report. Considering the heavy rock and Fort concrete cutting involved, fair progress was made during the year; all spoil was trucked and tipped for reclamation purposes along the North Point foreshore. 1923 Estimates, $100,000.00 | Total Estimates, 1923 Expenditure, $27,126.85 | Expenditure to 31.12.23, $27,231.90 (h.) Shaukiwan Road,— Improvements in Shaukiwan Village.-- This was referred to in paragraph 106 (h) of last year's Report. The work was not commenced owing to the resumptions of certain properties not being completed. 1923 Estimates, $30,000.00 | 1923 Expenditure, (i.) Victoria Road Improvements.- The widening of this road to give a minimum width of 25′ 0″ and open out dangerous bends referred to in paragraph 106 (i) of last year's Report was continued throughout the year. 1923 Estimates, $25,000.00 | 1923 Sup. Vote, $5,000.00 | $30,000.00 1923 Expenditure, $28,409.51 (j.) Road from Western end of Robinson Road to Conduit Road.- Owing to the necessary resumptions not being completed, it was impossible to proceed with this work. There was consequently no expenditure under this heading. 1923 Estimates, $25,000.00 | 1923 Expenditure,
Baseline (Original)
P.W.E. Hongkong. 0 80 The re-building and setting back to the new line of several properties in this road was completed during the year, and a commencement made in several other cases. Particulars of the properties dealt with are given in the schedule on page 35. By delaying the resumption of the land required for road widening until re-building takes place, a considerable saving has been effected on this vote. There was no expenditure incurred in connection with the making good of the road surface on the widened portions. 1923 Estimates, 1923 Expenditure, $25,000.00 | Total Estimates, Expenditure to $3,459.75 31.12.23, $95,000,00 $46,007.82 (g.) Road from Causeway Bay to North Point:-This work was referred to in paragraph 106 (9) of last year's Report. Considering the heavy rock and Fort concrete cutting involved, fair progress was made during the year; all spoil was trucked and tipped. for reclamation purposes along the North Point foreshore. 1923 Estimates,... $100,000.00 Total Estimates, 1923 Expenditure, $ 27,126.85 | Expenditure to 31.12.23, $27,231.90 (h.) Shaukiwan Road,—-Improvements in Shaukiwan Village.-- This was referred to in paragraph 106 (h) of last year's Report. The work was not commenced owing to the resumptions of certain properties not being completed. 1923 Estimates, 1923 Expenditure,...... .$30,000.00 (i.) Victoria Road Improvements.-The widening of this road to give a minimum width of 25′ 00′′ and open out dangerous bends referred to in paragraph 106 () of last year's Report was contin- ued throughout the year. 1923 Estimates, 1923 Sup. Vote,.... $25,000.00 5,000.00 $30,000.00 $28,409.51 1923 Expenditure, (j.) Road from Western end of Robinson Road to Conduit Road.-Owing to the necessary resumptions not being completed, it was impossible to proceed with this work. There was conse- quently no expenditure under this heading. 1923 Estimates, 1923 Expenditure,.... $25,000.00
2026-05-07 05:39:25 · Baseline
View content

P.W.E. Hongkong.

0 80

The re-building and setting back to the new line of several properties in this road was completed during the year, and a commencement made in several other cases. Particulars of the properties dealt with are given in the schedule on page 35. By delaying the resumption of the land required for road widening until re-building takes place, a considerable saving has been effected on this vote. There was no expenditure incurred in connection with the making good of the road surface on the widened portions.

1923 Estimates,

1923 Expenditure,

$25,000.00 | Total Estimates,

Expenditure to

$3,459.75

31.12.23,

$95,000,00

$46,007.82

(g.) Road from Causeway Bay to North Point:-This work was referred to in paragraph 106 (9) of last year's Report.

Considering the heavy rock and Fort concrete cutting involved, fair progress was made during the year; all spoil was trucked and tipped. for reclamation purposes along the North Point foreshore.

1923 Estimates,... $100,000.00 Total Estimates,

1923 Expenditure, $ 27,126.85

|

Expenditure to

31.12.23,

$27,231.90

(h.) Shaukiwan Road,—-Improvements in Shaukiwan Village.-- This was referred to in paragraph 106 (h) of last year's Report. The work was not commenced owing to the resumptions of certain properties not being completed.

1923 Estimates,

1923 Expenditure,......

.$30,000.00

(i.) Victoria Road Improvements.-The widening of this road to give a minimum width of 25′ 00′′ and open out dangerous bends referred to in paragraph 106 () of last year's Report was contin- ued throughout the year.

1923 Estimates, 1923 Sup. Vote,....

$25,000.00

5,000.00

$30,000.00

$28,409.51

1923 Expenditure,

(j.) Road from Western end of Robinson Road to Conduit Road.-Owing to the necessary resumptions not being completed, it was impossible to proceed with this work. There was conse- quently no expenditure under this heading.

1923 Estimates, 1923 Expenditure,....