P.W.E. Hongkong.

(c.) Extending 20-foot road from Magazine Gap to Victoria Gap, Stubbs Road.—A description of this work was given in the 1921 Report, paragraph 101 (k), and referred to in paragraph 106 (c) of last year's Report. The progress during the year was not very satisfactory; alterations to alignment and levels, typhoon and rainstorm damage, and dilatoriness on the part of the Contractor, retarded the progress. At the close of the year, however, the road was so far advanced, that a small length of retaining wall only and some filling in near "Treverbyn" remained to be done.

1923 Estimates, $55,000.00 Total Estimates, ... $198,600.00
1923 Sup. Vote, $4,035.15 $59,035.15 Expenditure, to ... $59,035.15
1923 Expenditure, $59,035.15 31.12.23, .... $206,890.22

(d.) Road from Wongneichong Gap to Repulse Bay Road :— This work was referred to in paragraph 101 (h) of the 1921 Report and in paragraph 106 (d) of last year's Report as "Road from Bowen Road to Repulse Bay". The Contract for about half a mile at the Repulse Bay Road end, which was let in September, 1922, was completed in July at a cost of $51,298.34.

In August, a Contract was let to Mr. Ng Wah to complete the remaining 7,100 feet from Wongneichong Gap to link up the portion at Repulse Bay Road end. At the close of the year, this was well advanced.

1923 Estimates, ... $100,000.00 Total Estimates, $257,000.00
Expenditure to 31.12.23, $151,841.64
1923 Expenditure, $88,133.79

(e.) Road contouring hillside in Wongneichong and Tai Hang Valleys,―Extension.--2nd Section, Bowen Road to connect with Tai Hang proposed Road :-This work was referred to in paragraph 106 (e) of last year's Report. A Contract was let to Mr. Li Ng in February. At the close of the year the work was well advanced, all culverts and walls being completed.

1923 Estimates, ... $40,000.00 Total Estimates, ... $250,000.00
1923 Sup. Vote, $5,053.20 $45,053.20 Expenditure to ... $45,053.20
1923 Expenditure, $45,053.20 31.12.23, $221,367.99

(f.) Wanchai Road Widening to 42 feet:-This work was referred to in paragraph 106 (f) of last year's Report.

Edit History

2026-05-07 05:39:17 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
P.W.E. Hongkong. (c.) Extending 20-foot road from Magazine Gap to Victoria Gap, Stubbs Road.—A description of this work was given in the 1921 Report, paragraph 101 (k), and referred to in paragraph 106 (c) of last year's Report. The progress during the year was not very satisfactory; alterations to alignment and levels, typhoon and rainstorm damage, and dilatoriness on the part of the Contractor, retarded the progress. At the close of the year, however, the road was so far advanced, that a small length of retaining wall only and some filling in near "Treverbyn" remained to be done. 1923 Estimates, $55,000.00 Total Estimates, ... $198,600.00 1923 Sup. Vote, $4,035.15 $59,035.15 Expenditure, to ... $59,035.15 1923 Expenditure, $59,035.15 31.12.23, .... $206,890.22 (d.) Road from Wongneichong Gap to Repulse Bay Road :— This work was referred to in paragraph 101 (h) of the 1921 Report and in paragraph 106 (d) of last year's Report as "Road from Bowen Road to Repulse Bay". The Contract for about half a mile at the Repulse Bay Road end, which was let in September, 1922, was completed in July at a cost of $51,298.34. In August, a Contract was let to Mr. Ng Wah to complete the remaining 7,100 feet from Wongneichong Gap to link up the portion at Repulse Bay Road end. At the close of the year, this was well advanced. 1923 Estimates, ... $100,000.00 Total Estimates, $257,000.00 Expenditure to 31.12.23, $151,841.64 1923 Expenditure, $88,133.79 (e.) Road contouring hillside in Wongneichong and Tai Hang Valleys,―Extension.--2nd Section, Bowen Road to connect with Tai Hang proposed Road :-This work was referred to in paragraph 106 (e) of last year's Report. A Contract was let to Mr. Li Ng in February. At the close of the year the work was well advanced, all culverts and walls being completed. 1923 Estimates, ... $40,000.00 Total Estimates, ... $250,000.00 1923 Sup. Vote, $5,053.20 $45,053.20 Expenditure to ... $45,053.20 1923 Expenditure, $45,053.20 31.12.23, $221,367.99 (f.) Wanchai Road Widening to 42 feet:-This work was referred to in paragraph 106 (f) of last year's Report.
Baseline (Original)
79 P.W.E. Hongkong. (c.) Extending 20-foot road from Magazine Gap to Victoria Gap, Stubbs Road.—A description of this work was given in the 1921 Report, paragraph 101 (k), and referred to in paragraph 106 (c) of last year's Report. The progress during the year was not very satisfactory; alterations to alignment and levels, typhoon and rainstorm damage, and dilatoriness on the part of the Contrac- tor, retarded the progress. At the close of the At the close of the year, however, the road was so far advanced, that a small length of retaining wall only and some filling in near "Treverbyn " remained to be done. 1923 Estimates, 1923 Sup. Vote, 1923 Expenditure, | $55,000.00 Total Estimates, ...$198,600.00 4,035.15 $59,035.15 Expenditure, to . $59,035.15 31.12.23, ....$206,890.22 (d.) Road from Wongneichong Gap to Repulse Bay Road :— This work was referred to in paragraph 101 (h) of the 1921 Report and in paragraph 106 (d) of last year's Report as "Road from Bowen Road to Repulse Bay ". The Contract for about half a mile at the Repulse Bay Road end, which was let in September, 1922, was completed in July at a cost of $51,298.34. In August, a Contract was let to Mr. Ng Wah to complete the remaining 7,100 feet from Wongneichong Gap to link up the portion at Repulse Bay Road end. At the close of the year, this was well advanced. 1923 Estimates, | ...$100,000.00 Total Estimates, $257,000.00 Expenditure to 31.12.23, 1923 Expenditure, $ 88,133.79 .$151.841.64 (e.) Road contouring hillside in Wongneichong and Tai Hang Valleys,―Extension.--2nd Section, Bowen Road to connect with Tai Hang proposed Road :-This work was referred to in para- graph 106 (e) of last year's Report. A Contract was let to Mr. Li Ng in February. At the close of the year the work was well advanced, all culverts and walls being completed. 1923 Estimates, ... 1923 Sup. Vote, .$40,000.00 | Total Estimates, ...$250,000.00 5,053.20 $45,053.20 Expenditure to 1923 Expenditure, $45,053.20 31.12.23, $221,367.99 (f.) Wanchai Road Widening to 42 feet:-This work was referred to in paragraph 106 (ƒ) of last year's Report.
2026-05-07 05:39:17 · Baseline
View content

79

P.W.E. Hongkong.

(c.) Extending 20-foot road from Magazine Gap to Victoria Gap, Stubbs Road.—A description of this work was given in the 1921 Report, paragraph 101 (k), and referred to in paragraph 106 (c) of last year's Report. The progress during the year was not very satisfactory; alterations to alignment and levels, typhoon and rainstorm damage, and dilatoriness on the part of the Contrac- tor, retarded the progress. At the close of the

At the close of the year, however, the road was so far advanced, that a small length of retaining wall only and some filling in near "Treverbyn " remained to be done.

1923 Estimates,

1923 Sup. Vote,

1923 Expenditure,

|

$55,000.00 Total Estimates, ...$198,600.00

4,035.15

$59,035.15 Expenditure, to . $59,035.15

31.12.23,

....$206,890.22

(d.) Road from Wongneichong Gap to Repulse Bay Road :— This work was referred to in paragraph 101 (h) of the 1921 Report and in paragraph 106 (d) of last year's Report as "Road from Bowen Road to Repulse Bay ". The Contract for about half a mile at the Repulse Bay Road end, which was let in September, 1922, was completed in July at a cost of $51,298.34.

In August, a Contract was let to Mr. Ng Wah to complete the remaining 7,100 feet from Wongneichong Gap to link up the portion at Repulse Bay Road end. At the close of the year, this was well advanced.

1923 Estimates,

|

...$100,000.00 Total Estimates, $257,000.00

Expenditure to

31.12.23,

1923 Expenditure, $ 88,133.79

.$151.841.64

(e.) Road contouring hillside in Wongneichong and Tai Hang Valleys,―Extension.--2nd Section, Bowen Road to connect with Tai Hang proposed Road :-This work was referred to in para- graph 106 (e) of last year's Report. A Contract was let to Mr. Li Ng in February. At the close of the year the work was well advanced, all culverts and walls being completed.

1923 Estimates,

...

1923 Sup. Vote,

.$40,000.00 | Total Estimates, ...$250,000.00

5,053.20

$45,053.20

Expenditure to

1923 Expenditure, $45,053.20

31.12.23,

$221,367.99

(f.) Wanchai Road Widening to 42 feet:-This work was referred to in paragraph 106 (ƒ) of last year's Report.