P.W.E. Hongkong.
Q 62
Village, to join the road from Island Bay to Big Wave Bay. In November, this latter Contract was extended to include the half mile required to link up the 3rd mile with Shek-O Gap. Substantial progress was made with these two Contracts. The total length of the road from Taitam Gap to Shek-O will be 5.63 miles of which 2.73 miles have been completed.
1922 Estimates.... $180,000.00 | Total Estimates.... $492,000.00
Expenditure to 31/12/22
1922 Expenditure $119,534.50 $204,891.24(c) Extending 20 foot road from Magazine Gap to Peak Tram Station, Chamberlain Road.---A description of this work was given in last year's Report, paragraph 101 (k). Its progress during the year under review was not satisfactory; labour trouble and rainstorm damages retarded the progress for many months. The section from Magazine Gap to Peak Church was, however, practically completed, and considerable advance was made with the remaining section to Victoria Gap. A coating of tar macadam was laid over that portion of it between Magazine Gap and the junction of Barker Road. The cost for this (tar macadam) was met from the Vote, P.W.R. 7, Improvements to Roads Outside City.
1922 Estimates $80,000.00 Total Estimates.... $198,600.00 1922 Sup. Vote $80,178.07 1922 Expenditure $80,174.15 Expenditure to 31/12/22 $147,855.07(d) Road from Bowen Road to Repulse Bay.
The section from Bowen Road to Wongneichong Gap was completed last year as mentioned in paragraph 101 (h) of last year's Report.
The total cost of this section being $50,558.27.
The road from Wongneichong Gap to Repulse Bay Road, which is to be 25 feet wide, will be 1.81 miles in length.
It was not found possible to let a Contract for the whole length of 1.84 miles from Wongneichong Gap to Repulse Bay Road, but a Contract for about a mile at Repulse Bay Road end was let in September.
1922 Estimates $75,000.00 Total Estimates $234,000.00 1922 Expenditure $17,476.23 Expenditure to 31/12/22 $63,707.85P.W.E. Hongkong.
Q 62
Village, to join the road from Island Bay to Big Wave Bay. In November, this latter Contract was extended to include the half mile required to link up the 3rd mile with Shek-O Gap. Substantial progress was made with these two Contracts. The total length of the road from Taitam Gap to Shek-O will be 5′63 miles of which 2-73 miles have been completed.
1922 Estimates.... $180,000.00 | Total Estimates,... $492,000,00
Expenditure to
1922 Expenditure, 119,534.50 31/12/22
204.891.24
(c) Extending 20 foot road from Magazine Gap_to_Peak Tram Station, Chamberlain Road.---A description of this work was given in last year's Report, paragraph 101 (k). Its progress during the year under review was not satisfactory; labour trouble and rainstorm damages retarded the progress for many months. The section from Magazine Gap to Peak Church was, however, practically completed, and considerable advance was made with the remaining section to Victoria Gap. A coating of " of tar macadam was laid over that portion of it between Magazine Gap and the junction of Barker Road. The cost for this (tar macadam) was met from the Vote, P.W.R. 7,- Improvements to Roads Outside City".
$80,000.00 | Total Estimates....$ 198,600.00
178.07
1922 Estimates. 1922 Sup. Vote,
$ 80,178.07
1922 Expenditure,
80,174.15
Expenditure to 31/12, 22 .....
147.855.07
(d.) Roud from Bowen Road to Repulse Bay.
Bug.-The section from Bowen Road to Wongneichong Gap was completed last as mentioned in paragraph 101 (h) of last year's Report.
The total cost of this section being $50,558.27.
The road from Wongneichong Gap to Repulse Bay Road, which is to be 25 feet wide, will be 181 miles in length.
It was not found possible to let a Contract for the whole length of 184 miles from Wongneichong Gap to Repulse Bay Road, but a Contract for about a mile at Repulse Bay Road end was let in September.
1922 Estimates, ...$75,000.00 Total Estimates, ...$234,000.00
|
1922 Expenditure,
17,476.23
Expenditure to
31/12/22
63,707.85