P.W.E. New Territories.

(1.) Trough Closet (24 seats and 4 Trough Urinals) at junction of Apliu Street with Kweilin Street, Shanshuipo.

(2.) Trough Closet (32 seats and 4 Trough Urinals) at junction of Yee Kuk Street with Pei Ho Street, Shamshuipo.

The roof of (2) has been constructed of sufficient strength to form the floor of a probable future bath-house.

1921 Estimates,...... $15,000.00 | Total Estimates,...
Expenditure to 31/12/21,
1921 Expenditure, $10,510.58
$10,510.58

162. Roads :—

(a.) Tai Po Road,— Widening and improving road between Shatin and Tai Po.—This work referred to in paragraph 151 of last year's Report was completed in May.

1921 Estimates,.. $9,000.00 | Total Estimates,...
1921 Expenditure, $7,497.84
Expenditure to 31/12 21,.. $7,497.84

(b.) Taipo Road,— Widening and improving road between 3rd & 5th milestones.—The improvements to this road referred to in paragraph 167 of last year's Report were completed. The surfacing to the whole of this section was treated with asphaltum.

1921 Estimates,............................ $15,000.00
1921 Sup. Vote,.......... 20,700.00
1921 Expenditure, $35,700.00
$35,428.22

(c.) Metalling and tar-painting hilly portions of Lai Chi Kok-Castle Peak and Taipo Roads.—Sections of the Coastal Road between Lai Chi Kok and Castle Peak, for a distance of 7 miles, and the section of the Taipo Road between 13-15 miles were surfaced with ordinary macadam tar painted, cement concrete margins being formed where found desirable.

1921 Estimates,. $70,000.00
1921 Expenditure, $69,446.31

(d.) Metalling and tarring Taipo-Fanling Road. The whole length of this road was macadamized and tarpainted, cement concrete margins being formed where found desirable.

1921 Estimates,. $30,000.00
1921 Expenditure,....... $29,946.00

Edit History

2026-05-07 01:01:18 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
Q 77 P.W.E. New Territories. (1.) Trough Closet (24 seats and 4 Trough Urinals) at junction of Apliu Street with Kweilin Street, Shanshuipo. (2.) Trough Closet (32 seats and 4 Trough Urinals) at junction of Yee Kuk Street with Pei Ho Street, Shamshuipo. The roof of (2) has been constructed of sufficient strength to form the floor of a probable future bath-house. 1921 Estimates,...... $15,000.00 | Total Estimates,... Expenditure to 31/12/21, 1921 Expenditure, $10,510.58 $10,510.58 162. Roads :— (a.) Tai Po Road,— Widening and improving road between Shatin and Tai Po.—This work referred to in paragraph 151 of last year's Report was completed in May. 1921 Estimates,.. $9,000.00 | Total Estimates,... 1921 Expenditure, $7,497.84 Expenditure to 31/12 21,.. $7,497.84 (b.) Taipo Road,— Widening and improving road between 3rd & 5th milestones.—The improvements to this road referred to in paragraph 167 of last year's Report were completed. The surfacing to the whole of this section was treated with asphaltum. 1921 Estimates,............................ $15,000.00 1921 Sup. Vote,.......... 20,700.00 1921 Expenditure, $35,700.00 $35,428.22 (c.) Metalling and tar-painting hilly portions of Lai Chi Kok-Castle Peak and Taipo Roads.—Sections of the Coastal Road between Lai Chi Kok and Castle Peak, for a distance of 7 miles, and the section of the Taipo Road between 13-15 miles were surfaced with ordinary macadam tar painted, cement concrete margins being formed where found desirable. 1921 Estimates,. $70,000.00 1921 Expenditure, $69,446.31 (d.) Metalling and tarring Taipo-Fanling Road. The whole length of this road was macadamized and tarpainted, cement concrete margins being formed where found desirable. 1921 Estimates,. $30,000.00 1921 Expenditure,....... $29,946.00
Baseline (Original)
Q 77 P.W.E. New Territories. (1.) Trough Closet (24 seats and 4 Trough Urinals) at junction of Apliu Street with Kweilin Street, Shanshuipo. (2.) Trough Closet (32 seats and 4 Trough Urinals) at junction of Yee Kuk Street with Pei Ho Street, Shamshuipo. The roof of (2) has been constructed of sufficient strength to form the floor of a probable future bath-house. 1921 Estimates,...... $ 15,000.00 | Total Estimates,... Expenditure to 31/12/21, 1921 Expenditure, 10,510.58 162. Roads :— $ 10,510.58 (a.) Tai Po Road,— Widening and improving road between Shatin and Tai Po.—This work referred to in paragraph 151 of last year's Report was completed in May. 1921 Estimates,.. $ 9,000.00 | Total Estimates,... 1921 Expenditure, 7,497.84 Expenditure to 31/12 21,.. $ 7,497.84 (b.) Taipo Road,—-— Widening and improving road between 3rd & 5th milestones.—The improvements to this road referred to in paragraph 167 of last year's Report were completed. The surfacing to the whole of this section was treated with asphaltum. 1921 Estimates,............................ 1921 Sup. Vote,.......... 1921 Expenditure, .$ 15,000.00 20,700.00 $ 35,700.00 35,428.22 (c.) Metalling and tar-painting hilly portions of Lai Chi Kok- Custle Peak and Taipo Roads.—Sections of the Coastal Road between Lai Chi Kok and Castle Peak, for a distance of 7 miles, and the section of the Taipo Road between 13-15 miles were surfaced with ordinary macadam tar painted, cement concrete margins being formed where found desirable. 1921 Estimates,. 1921 Expenditure, $ 70,000.00 69,446.31 (d.) Metalling and tarring Taipo-Fanling Road. The whole length of this road was macadamized and tarpainted, cement concrete margins being formed where found desirable. 1921 Estimates,. 1921 Expenditure,....... $30,000.00 29,946.00
2026-05-07 01:01:18 · Baseline
View content

Q 77

P.W.E. New Territories.

(1.) Trough Closet (24 seats and 4 Trough Urinals) at junction of Apliu Street with Kweilin Street, Shanshuipo.

(2.) Trough Closet (32 seats and 4 Trough Urinals) at junction of Yee Kuk Street with Pei Ho Street, Shamshuipo.

The roof of (2) has been constructed of sufficient strength to form the floor of a probable future bath-house.

1921 Estimates,...... $ 15,000.00 | Total Estimates,...

Expenditure to

31/12/21,

1921 Expenditure,

10,510.58

162. Roads :—

$ 10,510.58

(a.) Tai Po Road,— Widening and improving road between Shatin and Tai Po.—This work referred to in paragraph 151 of last year's Report was completed in May.

1921 Estimates,.. $ 9,000.00 | Total Estimates,...

1921 Expenditure,

7,497.84

Expenditure to 31/12 21,..

$ 7,497.84

(b.) Taipo Road,—-— Widening and improving road between 3rd & 5th milestones.—The improvements to this road referred to in paragraph 167 of last year's Report were completed. The surfacing to the whole of this section was treated with asphaltum.

1921 Estimates,............................ 1921 Sup. Vote,..........

1921 Expenditure,

.$ 15,000.00 20,700.00

$ 35,700.00 35,428.22

(c.) Metalling and tar-painting hilly portions of Lai Chi Kok- Custle Peak and Taipo Roads.—Sections of the Coastal Road between Lai Chi Kok and Castle Peak, for a distance of 7 miles, and the section of the Taipo Road between 13-15 miles were surfaced with ordinary macadam tar painted, cement concrete margins being formed where found desirable.

1921 Estimates,.

1921 Expenditure,

$ 70,000.00 69,446.31

(d.) Metalling and tarring Taipo-Fanling Road. The whole length of this road was macadamized and tarpainted, cement concrete margins being formed where found desirable.

1921 Estimates,. 1921 Expenditure,.......

$30,000.00 29,946.00