P.W.E. Kowloon.

By the end of the year, good progress had been made with the cutting, filling and nullah training.

The expenditure on this section during the year amounted to $26,895.00.

1920 Estimates, $150,000.00 Total Estimates,

Expenditure to 31/12/20, $69,225.93

1920 Expenditure, $68,963.64

(b). Extending Coronation Road northwards through hill (formerly) KEL. 11.—A Contract was let for this extension in June and consists of cutting and filling, the surplus filling being deposited in the low-lying area, East of Shanghai Street.

By the end of the year, good progress had been made with the work.

1920 Estimates, $30,000.00 Total Estimates,

1920 Expenditure, $3,986.10

Expenditure to 31/12/20, $3,986.10

(c). Road to China Light and Power Company's New Station. This work, referred to in paragraph 146 of last year's Report, was completed except surfacing, which is held over until the underground telephone and telegraph cables are diverted on to this road. The old cable routes being now within the area leased to the Hongkong and Whampoa Dock Company.

1920 Estimates, $40,000.00 Total Estimates, $50,000.00 Expenditure to 31/12/20, $42,443.16 1920 Expenditure, $39,552.14

(d). General Works.-The following is a brief statement of the principal works carried out under this heading:

Path alongside Kowloon-Canton Railway from Ho Mun Tin to Hunghom was widened, channelled and railings fixed.

Woosung Street, Pakhoi Street, Pitt Street, Canton Road, Shanghai Street, Changsha Street, Reclamation Street and Soy Street were all raised to their new levels.

The following roads were kerbed and channelled, the footpaths being paved with granolithic slabs and any necessary improvements being made in front of new buildings erected during the year:

Austin Road, Bowring Street, Coronation Road, Haitan Street, Hong Lok Street, Ivy Street, Kansu Street, Lai Chi Kok Road, Liberty Avenue, Ho Mun Tin, Nan Chang Street, Nathan Road, Ningpo Street, Path from Nathan Road to Jordan Road, Peace Avenue, Ho Mun Tin, Temple Street, Yu Chau Street, Yunnan Lane,

1920 Estimates, $50,000.00 1920 Sup. Vote, $29,450.00 Total $79,450.00 1920 Expenditure, $66,093.67

Edit History

2026-05-06 22:43:11 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
Q 59 P.W.E. Kowloon. By the end of the year, good progress had been made with the cutting, filling and nullah training. The expenditure on this section during the year amounted to $26,895.00. 1920 Estimates, $150,000.00 Total Estimates, Expenditure to 31/12/20, $69,225.93 1920 Expenditure, $68,963.64 (b). Extending Coronation Road northwards through hill (formerly) KEL. 11.—A Contract was let for this extension in June and consists of cutting and filling, the surplus filling being deposited in the low-lying area, East of Shanghai Street. By the end of the year, good progress had been made with the work. 1920 Estimates, $30,000.00 Total Estimates, 1920 Expenditure, $3,986.10 Expenditure to 31/12/20, $3,986.10 (c). Road to China Light and Power Company's New Station. This work, referred to in paragraph 146 of last year's Report, was completed except surfacing, which is held over until the underground telephone and telegraph cables are diverted on to this road. The old cable routes being now within the area leased to the Hongkong and Whampoa Dock Company. 1920 Estimates, $40,000.00 Total Estimates, $50,000.00 Expenditure to 31/12/20, $42,443.16 1920 Expenditure, $39,552.14 (d). General Works.-The following is a brief statement of the principal works carried out under this heading: Path alongside Kowloon-Canton Railway from Ho Mun Tin to Hunghom was widened, channelled and railings fixed. Woosung Street, Pakhoi Street, Pitt Street, Canton Road, Shanghai Street, Changsha Street, Reclamation Street and Soy Street were all raised to their new levels. The following roads were kerbed and channelled, the footpaths being paved with granolithic slabs and any necessary improvements being made in front of new buildings erected during the year: Austin Road, Bowring Street, Coronation Road, Haitan Street, Hong Lok Street, Ivy Street, Kansu Street, Lai Chi Kok Road, Liberty Avenue, Ho Mun Tin, Nan Chang Street, Nathan Road, Ningpo Street, Path from Nathan Road to Jordan Road, Peace Avenue, Ho Mun Tin, Temple Street, Yu Chau Street, Yunnan Lane, 1920 Estimates, $50,000.00 1920 Sup. Vote, $29,450.00 Total $79,450.00 1920 Expenditure, $66,093.67
Baseline (Original)
Q 59 P.W.E. Kowloon. By the end of the year, good progress had been made with the cutting, filling and nullah training. The expenditure on this section during the year amounted to $26,895.00. 1920 Estimates, 1920 Expenditure, ..$150,000.00 Total Estimates, Expenditure to 68,963.64 31/12/20, $69,225.93 (b). Ertending Coronation Road northwards through hill (formerly) KEL. 11.—A Contract was let for this extension in June and consists of cutting and filling, the surplus filling being deposited in the low-lying area, East of Shanghai Street. By the end of the year, good progress had been made with the work. 1920 Estimates, $30,000.00 Total Estimates, A 1920 Expenditure, ... 3,986.10 Expenditure to 31/12/20.. $3.986.10 (c). Road to China Light and Power Company's New Station. This work, referred to in paragraph 146 of last year's Report, was completed except surfacing, which is held over until the under- ground telephone and telegraph cables are diverted on to this road. The old cable routes being now within the area leased to the Hongkong and Whampoa Dock Company. 1920 Estimates, $40,000.00 | Total Estimates, Expenditure to 39,552.14 31/12/20, 1920 Expenditure, $50,000.00 42,443.16 (d), General Works.-The following is a brief statement of the principal works carried out under this heading: Path along side Kowloon-Canton Railway from Ho Mun Tin to Hunghom was widened, channelled and railings fixed. Woosung Street, Pakhoi Street, Pitt Street, Canton Road. Shanghai Street, Changsha Street, Reclamation Street and Soy Street were all raised to their new levels. The following roads were kerbed and channelled, the footpaths being paved with granolithic slabs and any necessary improvements being made in front new buildings erected during the Austin Road, Bowring Street, Coronation Road, Haitan Street, Hong Lok Street, Ivy Street, Kansu Street, Lai Chi Kok Road, Liberty Avenue, Ho Mun Tin, 1920 Estimates, year: Nan Chang Street. Nathan Road, Ningpo Street, Path from Nathan Road to Jordan Road, Peace Avenue, Ho Mun Tin, Temple Street. Yu Chau Street, Yunnan Laue, $50,000.00 29,450.00 1920 Sup. Vote, $79,450.00 1920 Expenditure, 66,093.67
2026-05-06 22:43:11 · Baseline
View content

Q 59

P.W.E. Kowloon.

By the end of the year, good progress had been made with the cutting, filling and nullah training.

The expenditure on this section during the year amounted to $26,895.00. 1920 Estimates,

1920 Expenditure,

..$150,000.00 Total Estimates, Expenditure to

68,963.64 31/12/20,

$69,225.93

(b). Ertending Coronation Road northwards through hill (formerly) KEL. 11.—A Contract was let for this extension in June and consists of cutting and filling, the surplus filling being deposited in the low-lying area, East of Shanghai Street.

By the end of the year, good progress had been made with the work.

1920 Estimates, $30,000.00 Total Estimates,

A

1920 Expenditure, ... 3,986.10

Expenditure to

31/12/20..

$3.986.10

(c). Road to China Light and Power Company's New Station. This work, referred to in paragraph 146 of last year's Report, was completed except surfacing, which is held over until the under- ground telephone and telegraph cables are diverted on to this road. The old cable routes being now within the area leased to the Hongkong and Whampoa Dock Company. 1920 Estimates, $40,000.00 | Total Estimates, Expenditure to 39,552.14 31/12/20,

1920 Expenditure,

$50,000.00

42,443.16

(d), General Works.-The following is a brief statement of the principal works carried out under this heading:

Path along side Kowloon-Canton Railway from Ho Mun Tin to Hunghom was widened, channelled and railings fixed.

Woosung Street, Pakhoi Street, Pitt Street, Canton Road. Shanghai Street, Changsha Street, Reclamation Street and Soy Street were all raised to their new levels.

The following roads were kerbed and channelled, the footpaths being paved with granolithic slabs and any necessary improvements being made in front new buildings erected during the

Austin Road,

Bowring Street, Coronation Road, Haitan Street,

Hong Lok Street,

Ivy Street,

Kansu Street,

Lai Chi Kok Road,

Liberty Avenue, Ho Mun Tin,

1920 Estimates,

year:

Nan Chang Street.

Nathan Road,

Ningpo Street,

Path from Nathan Road to

Jordan Road,

Peace Avenue, Ho Mun Tin, Temple Street. Yu Chau Street, Yunnan Laue,

$50,000.00 29,450.00

1920 Sup. Vote,

$79,450.00

1920 Expenditure,

66,093.67