Q 80

Item (v). Some of the pipes recovered, in the execution of item (i), from the old rising mains supplying the Hill District were utilized for intercepting the waters of another stream to the north-westward of the filter-beds and service reservoir recently constructed near Sywan Gap for the supply of the Shaukiwan District, thus augmenting the supply.

Item (vi). The principal object of this main was to increase the supply of water to properties to the eastward of Causeway Bay and to afford an alternative means of supply to such properties in the event of a burst occurring in the neighbourhood of East Point. As the district indicated has hitherto been dependent for its supply upon one line of main, the risk of interruption of the supply owing to bursts was very great.

No progress was made with the extension of Fire Hydrants, etc., Kennedy Road, referred to in the Report for 1914 as the diversion of Kennedy Road has not been carried out.

P.W.E. KOWLOON.

136. Quarters for Subordinate Officers, adjoining King's Park. — This work was completed in 1914 and was fully described in last year's Report. The payments in 1915 consisted of balances of $7,200.00 due under the Contract for the construction of the buildings and of $716.54 for the electric light installation.

1915 Estimates, ... $8,000.00 Total Estimates,

1915 Expenditure, 7,916.54

137. Market at Shamshuipo.

$74,000.00

Expenditure to 31/12/15,...... 76,347.02

Kowloon British School, Additions.

It was decided to postpone the execution of these works and no expenditure was incurred on either of them.

138. Royal Observatory :-

(a.) Installing wireless receiving apparatus.-No expenditure was incurred in connection with this item.

(b.) Bathroom.-A new bathroom, 6′ 6″ square, was added to the quarters on first floor, being supported on brick piers. To afford access to it from the compound, a reinforced concrete staircase was erected.

1915 Estimates, $700.00

1915 Expenditure, 678.72

(c.) Seismograph Room.-No expenditure was incurred in connection with this item.

Edit History

2026-05-06 10:52:25 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
P.W.E. Hong Kong. Q 80 Item (v). Some of the pipes recovered, in the execution of item (i), from the old rising mains supplying the Hill District were utilized for intercepting the waters of another stream to the north-westward of the filter-beds and service reservoir recently constructed near Sywan Gap for the supply of the Shaukiwan District, thus augmenting the supply. Item (vi). The principal object of this main was to increase the supply of water to properties to the eastward of Causeway Bay and to afford an alternative means of supply to such properties in the event of a burst occurring in the neighbourhood of East Point. As the district indicated has hitherto been dependent for its supply upon one line of main, the risk of interruption of the supply owing to bursts was very great. No progress was made with the extension of Fire Hydrants, etc., Kennedy Road, referred to in the Report for 1914 as the diversion of Kennedy Road has not been carried out. P.W.E. KOWLOON. 136. Quarters for Subordinate Officers, adjoining King's Park. This work was completed in 1914 and was fully described in last year's Report. The payments in 1915 consisted of balances of $7,200.00 due under the Contract for the construction of the buildings and of $716.54 for the electric light installation. 1915 Estimates, ... $8,000.00 Total Estimates, 1915 Expenditure, 7,916.54 137. Market at Shamshuipo. $74,000.00 Expenditure to 31/12/15,...... 76,347.02 Kowloon British School, Additions. It was decided to postpone the execution of these works and no expenditure was incurred on either of them. 138. Royal Observatory :- (a.) Installing wireless receiving apparatus.-No expenditure was incurred in connection with this item. (b.) Bathroom.-A new bathroom, 6′ 6″ square, was added to the quarters on first floor, being supported on brick piers. To afford access to it from the compound, a reinforced concrete staircase was erected. 1915 Estimates, $700.00 1915 Expenditure, 678.72 (c.) Seismograph Room.-No expenditure was incurred in connection with this item.
Baseline (Original)
P.W.E. Hong kong. Q 80 Item (v). Some of the pipes recovered, in the execution of item (i), from the old rising mains supplying the Hill District were utilized for intercepting the waters of another stream to the north- westward of the filter-beds and service reservoir recently constructed near Sywan Gap for the supply of the Shaukiwan District, thus augmenting the supply. Item (vi). The principal object of this main was to increase the supply of water to properties to the eastward of Causeway Bay and to afford an alternative means of supply to such properties in the event of a burst occurring in the neighbourhood of East Point. As the district indicated has hitherto been dependent for its supply upon one line of main, the risk of interruption of the supply owing to bursts was very great. No progress was made with the extension of Fire Hydrants, etc., Kennedy Road, referred to in the Report for 1914 as the diversion of Kennedy Road has not been carried out. P.W.E. KOWLOON. 136. Quirters for Subordinate Officers, adjoining King's Park. This work was completed in 1914 and was fully described in last year's Report. The payments in 1915 consisted of balances of $7,200.00 due under the Contract for the construction of the build- ings and of $716.54 for the electric light installation. 1915 Estimates, ... $8,000.00 Total Estimates, 1915 Expenditure, 7,916.54 137. Market at Shamshuipo. .$74,000.00 Expenditure to 31/12/15,...... 76,347.02 Kowloon British School, Additions. It was decided to postpone the execution of these works and no expenditure was incurred on either of them. 138. Royal Observatory :- (a.) Installing wireless receiving apparatus.-No expenditure was incurred in connection with this item. (b.) Bathroom.-A new bathroom, 6′ 6′′ square, was added to the quarters on first floor, being supported on brick piers. To afford access to it from the compound, a reinforced concrete stair- case was erected. 1915 Estimates,. 1915 Expenditure, $700.00 678.72 (c.) Seismograph Room.-No expenditure was incurred in connection with this item.
2026-05-06 10:52:25 · Baseline
View content

P.W.E. Hong kong.

Q 80

Item (v). Some of the pipes recovered, in the execution of item (i), from the old rising mains supplying the Hill District were utilized for intercepting the waters of another stream to the north- westward of the filter-beds and service reservoir recently constructed near Sywan Gap for the supply of the Shaukiwan District, thus augmenting the supply.

Item (vi). The principal object of this main was to increase the supply of water to properties to the eastward of Causeway Bay and to afford an alternative means of supply to such properties in the event of a burst occurring in the neighbourhood of East Point. As the district indicated has hitherto been dependent for its supply upon one line of main, the risk of interruption of the supply owing to bursts was very great.

No progress was made with the extension of Fire Hydrants, etc., Kennedy Road, referred to in the Report for 1914 as the diversion of Kennedy Road has not been carried out.

P.W.E. KOWLOON.

136. Quirters for Subordinate Officers, adjoining King's Park. — This work was completed in 1914 and was fully described in last year's Report. The payments in 1915 consisted of balances of $7,200.00 due under the Contract for the construction of the build- ings and of $716.54 for the electric light installation.

1915 Estimates, ... $8,000.00 Total Estimates,

1915 Expenditure,

7,916.54

137. Market at Shamshuipo.

.$74,000.00

Expenditure to

31/12/15,......

76,347.02

Kowloon British School, Additions.

It was decided to postpone

the execution of these works and no expenditure was incurred on either of them.

138. Royal Observatory :-

(a.) Installing wireless receiving apparatus.-No expenditure was incurred in connection with this item.

(b.) Bathroom.-A new bathroom, 6′ 6′′ square, was added to the quarters on first floor, being supported on brick piers. To afford access to it from the compound, a reinforced concrete stair- case was erected.

1915 Estimates,.

1915 Expenditure,

$700.00

678.72

(c.) Seismograph Room.-No expenditure was incurred in connection with this item.