(iii.) Completion of nullah near Paper Mills at Aberdeen (completed),
(iv.) Extension of stormwater outfall, Stone Nullah Lane (completed),
(v.) Construction of stormwater drain, Shaukiwan Road, from nullah at Bay View Police Station to Inland Lot 1,462 (practically completed),
(vi.) May Road Sewer:-
Sewer from Peak Road to Inland Lot $3,155
2,841
2,084
1,772 (work completed in 1908), ...$556 Extension from Inland Lot 1,772 to near Tramway Bridge (completed),
794
1,350
(vii.) Extension of sewer for Marine Lot 29, Praya East (completed),.....
411
(viii.) Extension of sewer to new latrine, Wongneichong Village (completed),
310
(ix.) Extension of stormwater outfall opposite Tai Wo Street on account of reclamation (completed),
(x.) Drain Connections (completed),
KOWLOON.
(xi.) Construction of stormwater drain, Shangtung Street, from sea-front to Portland Street (practically completed),
(xii.) Redrainage of portion of Yaumati in consequence of reclamation in front of Police Station. (completed),
(xiii) Construction of sewer for Kowloon Mortuary (not completed),
(xiv.) Construction of sewers between Dundas Street and Nelson Street, Mongkoktsui (work completed in 1908),.
3,115
(xv.) Redrainage of portion of Yaumati in consequence of reclamation of Kowloon Marine Lot 89 (extension of K.M.L. 49), (work completed in 1908),
2,000
(xvi.) Extension of sewer, Argyle Street, for K.I.L.'s 951 and 952, $800-$300 contributed by lessee of lots (practically completed),
150
787
(xvii.) Extension of sewer, Salisbury Road, to K.M.L. 88 (completed),
424
(xviii.) Extension of sewer outfall at Boundary Street, Fuk Tsun Heung (completed),
168
(xix.) Drain Connections (completed),
80
NEW TERRITORIES.
(xx.) Drainage works at Tai Wo Shi, Tai Po (completed),
1909. Estimates, 1909. Expenditure,
$45,000.00.
38,773.51.
752
0 33
(iii.) Completion of nullah near Paper Mills at Aber-
deen (completed),
(iv.) Extension of stormwater outfall, Stone Nullah
Lane (completed),
(v.) Construction of stormwater drain, Shaukiwan Road, from nullah at Bay View Police Station to Inland Lot 1,462 (practically completed),
(vi.) May Road Sewer:-
Sewer from-Peak Road to Inland Lot
$3,155
2,841
2,084
1,772 (work completed in 1908), ...$556 Extension from Inland Lot 1,772 to near
Tramway Bridge (completed),
794
1,350
(vii.) Extension of sewer for Marine Lot 29, Praya
East (completed),.....
411
(viii.) Extension of sewer to new latrine, Wongneichong
Village (completed),
310
(ix.) Extension of stormwater outfall opposite Tai Wo Street on account of reclamation (com- pleted),
(x.) Drain Connections (completed),
KOWLOON.
(xi.) Construction of stormwater drain, Shangtung Street, from sea-front to Portland Street (practically completed),
(xii.) Redrainage of portion of Yaumati in consequence
of reclamation in front of Police Station. (completed),
(xiii) Construction of sewer for Kowloon Mortuary
(not completed),
(xiv.) Construction of sewers between Dundas Street and Nelson Street, Mongkoktsui (work completed in 1908),.
(xv.) Redrainage of portion of Yaumati in consequence of reclamation of Kowloon Marine Lot 89 (extension of K.M.L. 49), (work completed in 1908),
(xvi.) Extension of sewer, Argyle Street, for K.I.L.'s 951 and 952, $800-$300 contributed by lessee of lots (practically completed),
150
787
3.115
3,115
2,000
1.450
1,116
500
(xvii.) Extension of sewer, Salisbury Road, to K.M.L.
88 (completed),
424
(xviii.) Extension of sewer outfall at Boundary Street,
Fuk Tsun Heung (completed),
168
(xix.) Drain Connections (completed),
80
NEW TERRITORIES.
(xx.) Drainage works at Tai Wo Shi, Tai Po
(completed),
1909. Estimates, 1909. Expenditure,
$45,000.00.
38.773.51.