CO537-(35-36) — Page 149

CO537 Colonial Confidential Records 理藩院機密檔案 All

64".

659

Mr. Raves.

pr Shelton Hooperi-

5026

At-

2017 08-

A:-

In your practice, have you ever found that there was sometime a longer time than necessary elapsed before buildings were pasŋed, before you got your certificate from either the Sanitary Board, or the Ruilding

Authority - An unreasonable time ?

Well, I have had some time to wait. I have been kept waiting for about two months in some cases,

For which certificate ? For the certificate from the

Sanitary Board, or the certificate from the Building

Authority?

}

5826

5027

Well, there is a case in Kowloon now, in Victoria View,

We have not got a permit yet.

A

5828

PUBLIC RECORD OFFICE

Reference:-

C.O. 537

5029

5028 98-

A:-

A permit to occupy, are you speaking of ↑

No, to do the work.

5029 01-

When did you apply. When did you send in the plans?

At-

a teration was made which shortens the time.

About two months ago, but then in that two months about three weeks after the plan was sent in, an

A

®à008-

That brings it down to five weeks ?

At-

YOU.

At-

5030

Since the amended plans were sent in ?

Yes.

5031

Have you heard anything in that five weeks permitting 5032

you to go on ?

35

RECORD OFFICE, LONDON OUT PERMISSION OF THE PUBLIC

CED PHOTOGRAPHICALLY WITH

PHOTOGRAPH - NOT TO BE

A‡-

No.

SD 32

Who are you waiting for that from?

At-

From the Building Authority.

5034 98-

At-

5035~090

At-

The Chairmani-

Have you made any application for an answer ?

I have not made a written application. I have been up

to see about it.

5031

And what reply did you get from them, for not receiving NON

an answer ↑

Oh, that it is with the Sanitary people.

Who did you ses ↑