CONTRACT SIGNING OF WAN CHAI TOWER III
**
* * *
THE DIRECTOR OF ARCHITECTURAL SERVICES, MR JOSE LEI, TODAY (FRIDAY) SIGNED A $498 MILLION CONTRACT FOR THE CONSTRUCTION 49-STOREY OFFICE BUILDING AT HARBOUR ROAD IN WAN CHAI.
OF A
THE CONSTRUCTION OF THE WAN CHAI TOWER III WILL BEGIN BY THE END OF THIS MONTH AND TAKE 32 MONTHS TO COMPLETE.
THE CONTRACT IS THE LARGEST AWARDED BY THE DEPARTMENT SO FAR THIS YEAR.
THIS TOWER IS THE THIRD AND THE LAST PHASE OF A GOVERNMENT COMPLEX AT A SITE BOUNDED BY HARBOUR ROAD TO THE NORTH AND GLOUCESTER ROAD TO THE SOUTH,
THE COMPLEX CONSISTS OF THREE MAJOR BUILDINGS, THAT I, II AND III.
IS, TOWER
TOWER III WILL BE COMPLETED IN TWO PHASES. PHASE I, WHICH WILL INVOLVE PUTTING UP 27 FLOORS FROM THE GROUND, IS EXPECTED то BE COMPLETED IN 25 MONTHS. THE REMAINING FLOORS WILL REQUIRE ANOTHER SEVEN MONTHS TO COMPLETE..
THE STRUCTURAL DESIGN OFFERS OFFICE AREAS ALL COLUMN FREE, THUS ALLOWING MAXIMUM FLEXIBILITY IN THE ALLOCATION AND PLANNING OF INTERIOR OFFICE SPACE.
IN
TO ALLOW FOR COMPUTERISATION OF CERTAIN GOVERNMENT SERVICES FUTURE, FOUR FLOORS WILL BE ESPECIALLY DESIGNED FOR COMPUTER INSTALLATIONS.
ON COMPLETION, A TOTAL OF 108,000 SQUARE METRES OF GROSS FLOOR AREA WILL BE AVAILABLE FOR A NUMBER OF GOVERNMENT DEPARTMENTS.
THE FIRST FIVE FLOORS OF THE BUILDING WILL BE LINKED BY 10
ESCALATORS.
/THE THREE
++