FANLING SOUTH DEVELOPMENT TO START SOON
OUT
ROAD AND DRAINAGE WORKS AND SITE FORMATION WILL BE CARRIED IN WO HOP SHEK IN FANLING SOUTH FOLLOWING THE AWARD OF A $108 MILLION CONTRACT BY THE TERRITORY DEVELOPMENT DEPARTMENT.
THE WORK COMPRISES IMPROVEMENTS TO THE EXISTING WO HOP SHEK INTERCHANGE, CONSTRUCTION OF A 600-METRE LOCAL DISTRIBUTOR ROAD, A BUS TERMINUS, TWO CAR/LORRY PARKS, TWO PEDESTRIAN/CYCLIST SUBWAYS AND TWO FOOTBRIDGES.
ASSOCIATED STORMWATER AND FOUL DRAINAGE WORKS WILL ALSO BE CARRIED OUT.
THE PROJECT ALSO INCLUDES THE FORMATION OF SITES FOR A HOME OWNERSHIP SCHEME AND A SECONDARY SCHOOL IN THE AREA.
WORK IS SCHEDULED TO BEGIN NEXT WEEK AND TAKE ABOUT 27 MONTHS TO COMPLETE.