TUESDAY, MAY 24, 1988
NEW SERVICE RESERVOIR FOR EAST KOWLOON
* * * * *
RESERVOIR
THE
THE GOVERNMENT IS TO BUILD A NEW FRESH WATER SERVICE AND ASSOCIATED INLET AND OUTLET MAINS AT HAMMER HILL TO COPE WITH INCREASING WATER DEMAND IN KOWLOON EAST HIGH LEVEL AREAS.
INVOLVES THE A WITH WATER MAINS
TENDERS ARE BEING INVITED FOR THE PROJECT, WHICH
OF A CONSTRUCTION
REINFORCED CONCRETE SERVICE RESERVOIR CAPACITY OF 11,000 CUBIC METRES AND LAYING 500 METRES OF OF 600 MM IN DIAMETER.
WAN HIGH
LEVEL FRESH WATER SERVICE
WILL TAKE ABOUT 15.
WORKS ON THIS NGAU CHI RESERVOIR IS EXPECTED TO START IN SEPTEMBER AND MONTHS TO COMPLETE.
WATER CUT IN WESTERN DISTRICT
FRESH WATER SUPPLY TO
CERTAIN PREMISES IN WESTERN DISTRICT WILL BE TURNED OFF FROM 11 PM ON FRIDAY (MAY 27) TO 6 AM THE NEXT DAY FOR WATER MAINS WORK.
THE AREA AFFECTED IS BOUNDED BY POK FU LAM ROAD, BONHAM ROAD, EASTERN STREET, QUEEN'S ROAD WEST, MORRISON STREET, WATERFRONT, KENNEDY TOWN PRAYA, QUEEN'S ROAD WEST, BELCHER'S STREET AND BELCHER GARDENS.
TRAFFIC LANES ON LION ROCK TUNNEL ROAD TO BE CLOSED TEMPORARILY
* *
MOTORISTS SHOULD BE ON THE ALERT FOR TEMPORARY CLOSURES OF NORTHBOUND TRAFFIC LANES ON LION ROCK TUNNEL ROAD IN SHA ΤΙΝ TO BE IMPLEMENTED BETWEEN END OF THIS MONTH AND MID-JUNE.
THE CLOSURES ARE TO FACILITATE ROAD MAINTENANCE WORK AND WILL BE IMPLEMENTED ONLY IN LATE EVENINGS AND EARLY MORNINGS.
/A 130-METRE