9
FRIDAY, FEBRUARY 26, 1988
KWAI CHUNG CONTAINER PORT ROAD TO BE IMPROVED
THE GOVERNMENT PROPOSES TO IMPROVE THE NORTHERN SECTION OF CONTAINER PORT ROAD IN KWAI CHUNG TO PROVIDE ADDITIONAL CAPACITY FOR TRAFFIC USING THE CONTAINER PORT.
THE IMPROVEMENTS INVOLVE THE REALIGNMENT AND EXTENSION OF NORTHERN CONTAINER PORT ROAD WHICH WILL COMPRISE THREE NORTHBOUND LANES AND TWO SOUTHBOUND LANES.
THE WORKS WILL ALSO INCLUDE THE WIDENING OF KWAI TAI ROAD, MODIFICATIONS TO THE JUNCTION OF KWAI TAI ROAD AND KWAI TSING ROAD, THE CONSTRUCTION OF A BOX CULVERT ADJACENT TO KWAI CHUNG NULLAH AND MINOR MODIFICATIONS TO THE EXISTING FOOTBRIDGE ACROSS KWAI CHUNG ROAD AT TSUEN WAN ROAD.
FROM
SECTIONS OF THE EXISTING CONTAINER PORT ROAD AND THE SLIP ROAD KWAI CHUNG ROAD TO CONTAINER PORT ROAD WILL NEED TO BE PERMANENTLY CLOSED.
THIS WILL BE DONE AFTER THE RESPECTIVE REPROVISIONING AFFECTED SLIP ROAD AND THE COMPLETION OF NEW CONTAINER ALONG ITS REVISED ALIGNMENT.
OF THE PORT ROAD
IT WILL ALSO BE NECESSARY TO DEMOLISH A STAIRCASE LEADING TO THE PEDESTRIAN FOOTBRIDGE CROSSING KWAI CHUNG ROAD AT TSUEN WAN ROAD AFTER CONSTRUCTION OF THE NEW STAIRCASE HAS BEEN COMPLETED.
THE WORKS WILL START LATE THIS YEAR AND WILL TAKE ABOUT TWO YEARS TO COMPLETE.
DETAILS OF THE WORKS WERE PUBLISHED IN THE GAZETTE TODAY (FRIDAY) AND A NOTICE HAS BEEN POSTED ON THE SITE.
PLANS SHOWING THE WORKS ARE AVAILABLE FOR INSPECTION AT THE CENTRAL AND WESTERN DISTRICT OFFICE, CENTRAL ENQUIRY SUB-OFFICE, CENTRAL GOVERNMENT OFFICES, WEST WING, MAIN ENTRANCE LOBBY; THE KWAI TSING DISTRICT LANDS OFFICE, 10TH-11TH FLOOR, TSUEN WAN STATION MULTI-STOREY CARPARK BUILDING, 174-208 CASTLE PEAK ROAD, TSUEN WAN: AND THE KWAI TSING DISTRICT OFFICE, 10TH FLOOR, KWAI HING GOVERNMENT OFFICES, 166-174 HING FONG ROAD, KWAI CHUNG.
ANY PERSON OBJECTING TO THE WORKS MUST SEND HIS OBJECTION IN WRITING TO THE SECRETARY FOR TRANSPORT, CENTRAL GOVERNMENT OFFICES, EAST WING, SECOND FLOOR, LOWER ALBERT ROAD, HONG KONG, NOT LATER THAN APRIL 26 THIS YEAR.
/10
Page 10Page 11