FRIDAY, FEBRUARY 20, 1987

24

APPLICATIONS CALLED FOR COMMUNITY PROJECT FUNDS

*****

LOCAL ORGANISATIONS IN YAU MA TEI WISHING TO ORGANISE COMMUNITY INVOLVEMENT ACTIVITIES OR PROJECTS BEFORE MID-MARCH CAN APPLY FOR SPONSORSHIP FROM THE DISTRICT BOARD.

APPLICATION FORMS ARE AVAILABLE AT THE YAU MA TEI DISTRICT

BOARD SECRETARIAT, 14TH FLOOR, 490 NATHAN ROAD.

COMPLETED FORMS SHOULD BE RETURNED TO THE SECRETARIAT BY FEBRUARY 24 FOR THE BOARD'S COMMUNITY BUILDING COMMITTEE TO CONSIDER AT ITS MEETING ON FEBRUARY 26.

EACH APPLICATION FORM SHOULD BE USED TO APPLY FOR SPONSORS HIP OF ONE ACTIVITY ONLY.

FURTHER ENQUIRIES CAN BE MADE ON 3-7700424.

TENDERS INVITED FOR LINK ROAD SECTION

*****

THE HIGHWAYS DEPARTMENT IS INVITING TENDERS FOR CONSTRUCTION OF A SECTION OF THE MA ON SHAN-NAI CHUNG LINK ROAD FROM LOK WO SHA TO NAI CHUNG.

THE SECTION FORMS PART OF A SCHEME TO LINK SHA TIN AND MA ON SHAN WITH THE SAI KUNG PENINSULA.

THE CONTRACT WILL COMPRISE CONSTRUCTION OF ABOUT 1.6 KILOMETRES OF TWO-WAY ROAD, TOGETHER WITH FOOTPATHS AND A CYCLE TRACK.

A BRANCH ROAD WILL ALSO BE CONSTRUCTED TO THE BEACH AT LOK WO SHA. CAR AND COACH PARKING FACILITIES WILL BE BUILT NEAR THE BEACH.

THE EXISTING CAR PARK AT NAI CHUNG WILL BE ENLARGED TO PROVIDE A BUS TERMINUS, A MAXICAB STAND AND COACH AND CAR PARKING SPACES.

DEADLINE FOR SUBMISSION OF TENDERS IS NOON ON MARCH 13.

CONSTRUCTION WORK IS EXPECTED TO BEGIN IN APRIL AND TAKE 16 MONT HS TO COMPLETE.