FOOTBRIDGES TO TUEN MUN TOWN PARK BEING BUILT
*****
GRADE-SEPARATED PEDESTRIAN ACCESS TO TUEN MUN TOWN PARK AND NEARBY DEVELOPMENTS WILL BE PROVIDED IN 15 MONTHS WHEN TWO COVERED FOOTBRIDGES ACROSS TUEN MUN HEUNG SZE WUI ROAD ARE COMPLETED.
THE BRIDGES, ONE 75-METRE-LONG AND THE OTHER 100-METRE-LONG WILL LINK THE TOWN PARK WITH THE FUTURE LIGHT RAIL TRANSIT SYSTEM, THE CENTRAL BUS STATION AND THE CIVIC AND CULTURAL COMPLEX.
THE TERRITORY DEVELOPMENT DEPARTMENT RECENTLY AWARDED A $15.5 MILLION CONTRACT TO SHUN SHING CONSTRUCTION AND ENGINEERING COMPANY LIMITED FOR THE PROJECT, WORK ON WHICH HAS ALREADY STARTED.
ROAD CLOSED IN WAN CHAI FOR CABLE-LAYING
*****
FOR THE LAYING OF ELECTRIC CABLE ACROSS FLEMING ROAD, THE FOLLOWING ROAD SECTIONS IN WAN CHAT WILL BE CLOSED TO TRAFFIC BETWEEN 8 AM AND 11 PM ON SUNDAY (JUNE 15);
*
THE SLIP ROAD LEADING FROM SOUTHBOUND FLEMING ROAD TO EASTBOUND GLOUCESTER ROAD WILL BE CLOSED. VEHICLES ON SOUTHBOUND FLEMING ROAD HEADING FOR GLOUCESTER ROAD WILL BE DIVERTED TO THE LOOP ROAD BELOW THE FLEMING ROAD FLYOVER, FLEMING ROAD NORTHBOUND, HARBOUR ROAD AND FENWICK STREET,
* THE SLIP ROAD LEADING FROM EASTBOUND GLOUCESTER ROAD TO
NORTHBOUND FLEMING ROAD WILL ALSO BE CLOSED, DURING WHICH VEHICLES ON EASTBOUND GLOUCESTER ROAD HEADING FOR FLEMING ROAD WILL HAVE TO TRAVEL VIA TONNOCHY ROAD AND HARBOUR ROAD.