SUNDAY, FEBRUARY 2, 1986
18
ROAD WORK TO IMPROVE TRAFFIC
****
WORK WILL BE CARRIED OUT TO WIDEN CARPENTER ROAD IN KOWLOON, TO IMPROVE TRAFFIC CIRCULATION AND ALLEVIATE TRAFFIC CONGESTION.
AND STORMWATER DRAINS ALONG CARPENTER ROAD WILL BE DUPLICATED TO AVOID RECURRENCE OF FLOODING IN NEARBY LOW-LYING AREAS.
TENDERS ARE BEING CALLED BY THE ENGINEERING DEVELOPMENT DEPARTMENT FOR THE WORKS, WHICH WILL START IN APRIL AND TAKE 18 MONTHS TO COMPLETE.
TRAFFIC CHANGES
***
TRAFFIC CHANGES WILL BE IMPLEMENTED IN YUET LUN STREET, LAI CHI KOK FROM 10 AM ON WEDNESDAY (FEBRUARY 5) TO IMPROVE TRAFFIC FLOW.
THE CHANGES ARE:
* THE SOUTHERN SECTION OF YUET LUN STREET FROM ITS
JUNCTION WITH PO LUN STREET TO THE LAI CHI KOK INCINERATOR WILL BE RE-ROUTED FROM TWO-WAY TRAFFIC TO ONE-WAY WESTBOUND,
*
THE NORTHERN SECTION OF YUET LUN STREET WILL BE RE-ROUTED FROM TWO-WAY TRAFFIC TO ONE-WAY EASTBOUND, AND
* YUET LUN STREET BETWEEN LAI CHI KOK ROAD AND THE
LAI CHI KOK INCINERATOR WILL BE RE-OPENED TO TRAFFIC.
MEANWHILE, THE EXISTING BAN ON RIGHT TURNS FROM PRINCE EDWARD ROAD WEST EASTBOUND ONTO LA SALLE ROAD WILL CONTINUE FOR ABOUT NINE WEEKS, TO FACILITATE THE INSTALLATION OF A GAS PIPELINE AT THE JUNCTION OF PRINCE EDWARD ROAD WEST AND LA SALLE ROAD.
VEHICLES ON PRINCE EDWARD ROAD WEST EASTBOUND, HEADING FOR THE CUL-DE-SAC SECTION OF LA SALLE ROAD SOUTH OF PRINCE EDWARD ROAD WEST, WILL BE DIVERTED VIA KOWLOON CITY INTERCHANGE AND PRINCE EDWARD ROAD WEST WESTBOUND.
/19