FRIDAY, JULY 27, 1984

NEW ROAD FOR WO HOP SHEK

****

A 480-METRE-LONG ACCESS ROAD WILL BE BUILT CONNECTING TAI PO ROAD WITH THE NEW WO HOP SHEK CREMATORIUM.

BESIDES PROVIDING ACCESS TO THE CREMATORIUM, IT WILL SERVE AS AN ALTERNATIVE ACCESS TO WO HOP SHEK CEMETERY.

A PLAN SHOWING THE PROPOSED WORK CAN BE SEEN AT THE FOLLOWING PLACES:

* CENTRAL AND WESTERN DISTRICT OFFICE, ENQUIRY SUB-OFF ICE,

CENTRAL GOVERNMENT OFFICES, WEST WING ENTRANCE, HONG KONG

* DISTRICT LANDS OFFICE (NORTH), OLD DISTRICT OFFICE

BUILDING, TAI PO MARKET;

* DISTRICT LANDS OFFICE (TAI PO), TAI PO GOVERNMENT OFFICES

BUILDING, 1ST FLOOR, TING KOK ROAD, TAI PO MARKET; AND

* TAI PO DISTRICT OFF ICE, TAI PO GOVERNMENT OFFICES, SECOND

FLOOR, TING KOK ROAD, TAI PO.

ANY OBJECTION SHOULD BE IN WRITING TO THE SECRETARY FOR LANDS AND WORKS BY SEPTEMBER 25.

REFUSE COLLECTION POINT FOR CAUSEWAY BAY

****

WORK WILL START SHORTLY ON BUILDING A THREE-STOREY STRUCTURE IN CAUSEWAY BAY TO HOUSE A REFUSE COLLECTION POINT, A BATHHOUSE AND A PUBLIC TOILET,

THE STRUCTURE WILL OCCUPY A 2 300-SQUARE-METRE SITE AT #156 HING STREET.

THE REFUSE COLLECTION POINT WILL BE ON THE GROUND FLOOR. FACILITIES WILL INCLUDE A REFUSE LOADING AREA, SPACES FOR HANDCARTS, A ROLL-CALL ROOM, AN OFFICE AND STOREROOM.

THE OTHER TWO FLOORS WILL ACCOMMODATE THE PUBLIC TOILET .... THE BATHHOUSE.

THE ARCHITECTURAL OFFICE OF THE BUILDING DEVELOPMENT DEPARTMENT IS INVITING TENDERS FOR THE PROJECT WHICH SHOULD BE SUBMITTED BY AUGUST 17.

PILING WORK UNDER A SEPARATE CONTRACT HAS ALREADY STARTED AND IS DUE FOR COMPLETION IN SEPTEMBER.

WORK ON BUILDING THE SUPERSTRUCTURE WILL THE BEGIN AND TAKE NINE MONTHS TO COMPLETE.