SUNDAY, JULY 22, 1984

FOOTBRIDGES PLANNED FOR QUEENSWAY

****

THE ENGINEERING DEVELOPMENT DEPARTMENT IS PLANNING CONSTRUCT A COVERED FOOTBRIDGE SYSTEM AT THE JUNCTIONS C: QUEENSWAY-QUEEN'S ROAD EAST AND HENNESSY ROAD-ARSENAL STREET TO PROVIDE SAFER ROAD CROSSINGS FOR PEDESTRIANS.

THE SYSTEM WILL ALSO LESSEN INTERRUPTIONS TO VEHICULAR TRAFFIC ALONG THESE ROADS IN WAN CHAI.

CONSTRUCTION OF THE FOOTBRIDGES WILL REQUIRE MODIFICATIONS TO MONMOUTH PARK IN QUEEN'S ROAD EAST.

A PLAN SHOWING THE PROPOSED WORKS CAN BE SEEN AT THE CENTRAL AND WESTERN DISTRICT OFFICE, CENTRAL ENQUIRY SUB-OFFICE, CENTRAL GOVERNMENT OFFICES, WEST WING, MAIN ENTRANCE LOBBY, HONG KONG; THE DISTRICT LANDS OFFICE, HONG KONG NORTH, 12TH FLOOR, HARBOUR CENTRE, HARBOUR ROAD, HONG KONG; AND THE WAN CHAI DISTRICT OFFICE, TUNG WAH MANSIONS, 201 HENNESSY ROAD, GROUND FLOOR, HONG KONG.

ANY PERSON OBJECTING TO THE PROPOSAL SHOULD WRITE TO THE SECRETARY FOR LANDS AND WORKS BY SEPTEMBER 18.

SEAWALL AT ALDRICH BAY

***

A SEAWALL IS TO BE BUILT AT ALDRICH BAY IN CONNECTION WITH STAGE THREE OF ISLAND EASTERN CORRIDOR.

RECLAMATION OF 1.3 HECTARES OF LAND WILL BE CARRIED OUT BEHIND THE SEAWALL.

A SECTION OF ISLAND EASTERN CORRIDOR FROM SHAU KE1 WAN TO CHAI WAN WILL BE BUILT ON PART OF THE RECLAIMED LAND.

THE REST WILL BE USED FOR INDUSTRIAL DEVELOPMENT, PROVISION

OF OPEN SPACE AND SEWAGE FACILITIES.

THE CIVIL ENGINEERING OFFICE OF THE ENGINEERING DEVELOPMENT DEPARTMENT IS INVITING TENDERS FOR BUILDING THE 200-METRE SEAWALL.

WORK ON THE 10-MONTH CONTRACT WILL START IN SEPTEMBER,

19