THURSDAY, JANUARY 17, 1980

LANTAU DEVELOPMENTS TO GET WATER SUPPLY

****

WORK WILL BEGIN NEXT WEEK ON LANTAU ISLAND TO PROVIDE WATER SUPPLY FROM SHEK PIK RESERVOIR TO DEVELOPMENTS IN CHEUNG SHA.

A CONTRACT FOR THE PROJECT WAS SIGNED THIS (THURSDAY) MORNING BETWEEN MR LEE GUN-CHEUNG, CHIEF ENGINEER (CONSTRUCTION), OF THE WATER SUPPLIES DEPARTMENT AND A REPRESENTATIVE OF HUNG YUE AND CO.

WORK ON THE $1.5 MILLION PROJECT WILL INCLUDE THE CONSTRUCTION OF A GLASS-REINFORCED PLASTIC WATER STORAGE TANK AND THE LAYING OF A TOTAL OF 2 190 METRES OF MAINS.

THE PROJECT WILL TAKE ABOUT 10 MONTHS TO COMPLETE.