FRIDAY, JUNE 25, 1976

STREET ALTERATIONS ARISING FROM WORK ON PRINCE EDWARD

STATION OF MTR

******

ACTUAL CONSTRUCTION OF PRINCE EDWARD STATION OF THE MASS TRANSIT RAILWAY IS EXPECTED TO BEGIN SHORTLY AND BECAUSE OF THIS CERTAIN ALTERATIONS TO NATHAN ROAD HAVE TO BE MADE.

CONSTRUCTION WORK, BY CUT-AND-COVER METHOD, WILL BE ON

THAT PART OF THE STATION WHICH LIES UNDER THE EASTERN HALF OF NATHAN ROAD FROM A POINT ABOUT 106 METRES SOUTH OF THE

JUNCTION WITH BOUNDARY STREET TO A POINT ABOUT 45 METRES SOUTH OF THE JUNCTION WITH PRINCE EDWARD ROAD.

TO FACILITATE CONSTRUCTION, NATHAN ROAD BETWEEN PRINCE EDWARD ROAD AND MONGKOK ROAD HAVE BEEN REDUCED TO THREE TRAFFIC LANES SOUTHBOUND.

DETAILS OF THE STREET ALTERATIONS ARE NOTIFIED IN TODAY'S GOVERNMENT GAZETTE.

PLANS SHOWING THE AREAS AFFECTED BY THE PROJECT MAY BE INSPECTED AT THE CITY DISTRICT OFFICE (CENTRAL AND WESTERN) ENQUIRY SUB-OFFICE, CENTRAL GOVERNMENT OFFICES, AND AT THE CROWN LANDS AND SURVEY OFFICE, 10TH FLOOR, KOWLOON GOVERNMENT OFFICES BUILDING, 405 NATHAN ROAD.

THE PLANS ARE ALSO ON DISPLAY AT THE C.D.O. (KOWLOON CITY) 379 PRINCE EDWARD ROAD, AND C.D.O. (MONG KOK), 751 NATHAN ROAD.

TODAY'S GAZETTE HOTICE STIPULATES THAT ANY PERSON MAKING A CLAIM FOR COMPENSATION MUST SEND IT IN WRITING TO THE DIRECTOR OF PUBLIC WORKS.

THE CLAIMS MUST REACH THE OFFICE OF THE DIRECTOR BEFORE THE EXPIRATION OF ONE YEAR FROM THE DATE OF CLOSURE OF THE STREET OR FROM THE COMPLETION OF THE SUBSTANTIAL ALTERATION WHICH IS ALLEGED TO HAVE CAUSED PECUNIARY LOSS OR DAMAGE.