7

Tuesday, February 5, 1974

IMPROVEMENT OF WATER SUPPLY

To Stanley And Repulse Bay Area

A new break-pressure tank, capable of holding 12,500 gallons of

water, will be built shortly at West Bay to improve the water supply to

the Stanley and Repulse Bay area.

At the same time, about 200 feet of main will be laid in conjunction

with the project.

The new tank will replace the existing one which serves premises

at Headland Road and the low lying area of Repulse Bay.

Work on the project will begin next month and is expected to take

about four months to complete.

Commenting on the project, a spokesman for the Public Works

Department said that the existing tank, which only has a capacity of

11,000 gallons, was built before the war and cracks and leakage had

developed resulting in wastage of water and the possibility of contamination.

"To cope with the present demand a bigger tank with larger inlet

pipe is necessary, " he said.

a

18

-